| 1 | Admitted-Finance | Admitted-Finance |
| 2 | Admitted-Finance | Admitted-Finance |
Tender Value
₹26.1 L
EMD Value
₹26,200
Closing Date
16 Mar 2022, 3:00 pmClosed
Additional Collector (Dev.), DRDA
DRDA, Collectorate Campus, Vengikkal, Tiruvannamalai
Strengthening of Road in Package No.TVM/2021-22/12 Polur Block of Tiruvannamalai District under TNRRIS 2021-22 Scheme
2022_RDTN_223236_1
R.C.No.A7/6262/2021 Dt.16.02.2022 TVM12
Open Tender
Civil Works - Roads
Lump-sum
180 days
Polur
Please refer Tender documents.
3 documents required · 3 mandatory
₹0
₹26,200
22 Mar 2022
28 Feb 2022
16 Mar 2022
28 Feb 2022
16 Mar 2022
28 Feb 2022
Amount
Strengthening of Krishnapuram Kollaimedu to Krishnapuram Road KM 0/0 - 1/200 R145
Clearing and grubbing road land including uprooting wild vegetation, grass, bushes, scrubs,saplings and trees of girths upto 300mm, removal of stumps of such trees cut earlie and disposal of unserviceable material and stacking of serviceable materials to be used or auctioned, upto a lead of 1000m including removal and disposal of top organic soil not exceeding 150mm thickness as per technical specification clause 201. etc. comp.
Picking old metalled surface / BT surface upto 10cm thick and as directed by the departmental officers
Earth work excavation in all classes of soils except hard rock requiring blasting depositing on bank with initial lead of 10M and lift of 2M including all labour charges and incidental charges such as shoring, strutting, providing coffer dams, bailing out of water and other item which may be necessary or convenient to the succesful completion of the excavation in a compacted condition a quality of materials not exceeding the amount of excavation including all machinery charges for T&P employed etc., complete for cutting side drains and forming berms as per standard specifications.
Providing and laying including cost and conveyance of gravel from approved sources to work site including labour for spreading, watering and compacting by power roller to achieve the required Proctor density at 100% compaction at Optimum moisture content and hire fuel charges for powerroller, watersprinkler and all other incidental charges such as traffic barricading and providing dangerlights etc. comp for base-course and side berms
Providing and laying spreading and compacting graded stone aggregate to Wet Mix Macadam(WMM) specification including premixing the material with water at OMC in machanical mix plant carriage of mixed material by tipper to site laying in uniform layers 250mm thick with pavers in SubBase/Base course on well prepared surface and compacting with vibratory roller to achieve the desired density including cost of material,labour charges, rentals for machinery, fuel and all other incidental charges etc., complete.
Applying PRIMECOAT over WMB/ WMM surface at 7.00Kg of SS-1 Bitumen Emulsion / 10 sq.m including labour for spraying, hire charges for bitumen sprayer etc. Comp.
Applying tack coat over Un Primed WMB/ WMM surface at 2.5Kg / 10 Sqm. area including cost of bituminous binder at the site including labour charges for preparing the surface and applying the required quantity of bituminous binder as tack coat including hire charges and fuel charges for bitumen boiler and all other tools and plants employed etc., complete as per clause 503 of MOST specification.
Providing and laying Premix Carpet with Seal Coat Type -A to 20mm thick using 0.18cum of 13.2mm, 0.09 cum of 11.20mm and .09cum of 6.70mm with 24.40 Kgs of VG 30 Bitumen for premixing per 10sqm including cost and conveyance of all materials to CMP site, heating the bitumen and aggregate to required temperature and mixing them in required temperature in Central Hot Mix Plant 20-30T capacity, conveying the mix by tipper trucks to paver site, spreading the mix to uniform thickness of 20mm with mechanical paver to the specified grades and cross section and consolidated by 8-10T vibratory/pneumatic roller to the required density etc., including labour for attending to paver to site, hire & fuel charges for 20-30T CMP with bitumen boiler, tipper trucks, paver finisher, vibratory/pneumatic roller and all other tools and plants required, including fuel and other incidental charges etc., complete
Providing KM stones
Providing HM stones
Provision for Name Board
Provision for Sign Board
GST Amount for providing Service to Government Contract Works for the above Construction Works. { GST Amount is the Total GST Amount for total overall quoted amount above this row in column "BB" for all works in this package}
CHANDRAN
stage.html
html • 0.03 MB
tech_bid_open.pdf
tech_eval.pdf
fin_bid_open.pdf
boq_comp_chart.xlsx
xlsx
Tap a document below to read it instantly. You can also download everything as a ZIP if you prefer.
details.html
html • 0.04 MB
Download all tender documents and submit your bid
Disclaimer: TenderKart has made every reasonable effort to ensure that the information on this page is accurate and authentic, however it cannot be held liable for any third-party claims or losses or any damages. TenderKart makes no warranty, expressed or implied, as to the results obtained from the use of this information. If you notice any error or omission, please let us know at .