Loading…
Loading…
Tender Value
₹2.5 Cr
EMD Value
₹2.7 L
Closing Date
6 Apr 2026, 12:00 pmClosed
No
No
Single Packet System
Normal Tender
No
Not Applicable
Lowest to Highest
60 days
Expenditure
Capital (Works)
Above/Below/Par
TRD
14 conditions · 3 needing a document upload
The tenderer must have minimum average annual contractual turnover of V/N or 'V' whichever is less; where V= Advertised value of the tender in crores of Rupees N= Number of years prescribed for completion of work for which bids have been invited. The average annual contractual turnover shall be calculated as an average of "total contractual payments" in the previous three financial years, as per the audited balance sheet. However, in case balance sheet of the previous year is yet to be prepared/ audited, the audited balance sheet of the fourth previous year shall be considered for calculating average annual contractual turnover. The tenderers shall submit requisite information as per Annexure-VIB, along with copies of Audited Balance Sheets duly certified by the Chartered Accountant/ Certificate from Chartered Accountant duly supported by Audited Balance Sheet
The tenderer must have successfully completed or substantially completed any one of the following categories of work(s) during last 07 (seven) years, ending last day of month previous to the one in which tender is invited: (i)Three similar works each costing not less than the amount equal to 30% of advertised value of the tender, or (ii)Two similar works each costing not less than the amount equal to 40% of advertised value of the tender, or (iii)One similar work costing not less than the amount equal to 60% of advertised value of the tender. Similar work means - ""Execution of 25kV/2x25kV Electrification work OR Execution of 25kV/2x25kV feeder wire work OR Execution of 25kV/2x25kV OHE modification work OR Execution of 25kV/2x25kV OHE upgradation work OR Execution of 25kV/2x25kV OHE maintenance work OR Execution of 25kV/2x25kV OHE AMC work OR Execution of 25kV/2x25kV OHE rehabilitation work OR Execution of 25kV/2x25kV OHE replacement work i.e. catenary wire/contact wire/feeder wire/ ATD/ cantilever assembly OR Execution of 66kV or higher voltage overhead Transmission line work OR Execution of 66kV or higher voltage Sub-Station work.".
The Tenderer/Firm must have valid Electrical Contractor License (ECL) and copy of license must be uploaded in IREPS site during bid. In case Tenderers submitted with ECL issued in the name of other firms/ tenderers will be summarily rejected. In case the ECL is not valid on the date of opening of tender, details of renewal should be submitted.
16 conditions · 10 needing a document upload
I/ We have read the check list and furnish the documents as per check list.
Goods & Services Tax (GST) registration certificate copy should be attached.
In case of Sole Proprietorship Concern firm has to submit Affidavit certifying the sole Proprietorship of the firm. This affidavit shall be notarized. Or In case of a Partnership Firm, Firm has to submit (a) Notary certified copy of the Partnership Deed. (b) A copy of power of Attorney firm has to submit (duly registered as per prevailing Law) in favour of an individual to tender for the work, sign the agreement etc., and create liability against the Firm. Or In case Tenderer is a Company registered under Companies Act-2013. The tenderer shall submit: (a)The copies of MOA (Memorandum of Association)/AOA (Articles of Association) of the company.(b) A copy of Certificate of Incorporation. (c) A copy of authorization/ Power of Attorney issued by the Company (backed by the resolution of Board of Directors) in favour of the individual to sign the tender on behalf of company and create liability against the company. Or In case Tenderer is LLP (Limited Liability Partnership); If the tender is submitted on behalf of a LLP registered under LLP Act-2008, the Tenderer shall submit along with tender: (a) A copy of LLP Agreement (b) A copy of Certificate of Incorporation (c) A copy of Power of Attorney/Authorization issued by the LLP in favour of the individual to sign the tender on behalf of the LLP and create liability against the LLP. Or In case of a tenderer is registered Society and Registered trust. The tenderer shall submit: (a) A copy of certificate of registration. (b) A copy of Memorandum of Association of Society/Trust Deed (c)A copy of Power of Attorney in favour of the individual to sign the tender documents and create liability against the society/ Trust.
PAN Card copy should be attached..
EPFO registration certificate copy should be attached.
ESI registration certificate copy should be attached.
Please enter the percentage of local content in the material being offered. Please enter 0 for fully imported items, and 100 for fully indigenous items. The definition and calculation of local content shall be in accordance with the Make in India policy as incorporated in the tender conditions.
OHE safety and reliability improvement works including superblocks, replacement of leaning/critical masts in Railway Siding and loop lines, asset rehabilitation, and bonding in Raipur Division.
TRD-R-2025-E20
TRD-R-2025-E20
Open
Works - General
18 Months
Raipur, Chhattisgarh
₹0
₹2.7 L
6 Apr 2026
11 Mar 2026
23 Mar 2026
466 items across 7 schedules
| # | Description | Unit | Qty | Rate | Amount |
|---|---|---|---|---|---|
| — | — | — | 61,08,176.5 | ||
| — | 80.00 | — | — | ||
| Concrete for foundation & Plinth In other than Hard & Rocky soil | — | — | — | 5,69,760 | |
| — | 8.00 | — | — | ||
| Supply of Galvanised traction Mast,TTC, Portal, Special type portal (Rolled orFabricated), Fabricated Steel, SPS & Drop Arm etc. | — | — | — | 10,67,224 | |
| — | 12.00 | — | — | ||
| Erection of Galvanised traction Mast,TTC, Portal, Special type portal (Rolled orFabricated), Fabricated Steel, SPS & Drop Arm etc. | — | — | — | 95,496 | |
| — | 12.00 | — | — | ||
| 100% extra for Erection of Galvanised traction Mast,TTC, Portal, Special type portal (Rolled orFabricated), Fabricated Steel, SPS & Drop Arm etc. under PB working | — | — | — | 95,496 | |
| — | 12.00 | — | — | ||
| 50% extra for Erection of Galvanised traction Mast,TTC, Portal, Special type portal (Rolled orFabricated), Fabricated Steel, SPS & Drop Arm etc. under night PB working | — | — | — | 47,748 | |
| — | 20.00 | — | — | ||
| Supply of Single bracket assembly for conventional OHE. | — | — | — | 4,15,240 | |
| — | 20.00 | — | — | ||
| Fabrication & Erection of Single bracket assembly for conventional OHE | — | — | — | 19,640 | |
| — | 20.00 | — | — | ||
| 100% extra for Fabrication & Erection of Single bracket assembly for conventional OHE under PB working | — | — | — | 19,640 | |
| — | 20.00 | — | — | ||
| 50% extra for Fabrication & Erection of Single bracket assembly for conventional OHE under night PB working | — | — | — | 9,820 | |
| — | 1.00 | — | — | ||
| Supply of Extra items for additional fittings at a Turnout/Diamond crossing or overlap (extra of assorted components). | — | — | — | 3,151 | |
| — | 1.00 | — | — | ||
| Erection of Extra items for additional fittings at a Turnout/Diamond crossing or overlap (extra of assorted components) | — | — | — | 856 | |
| — | 1.00 | — | — | ||
| 100% extra for Erection of Extra items for additional fittings at a Turnout/ Diamond crossing or overlap (extra of assorted components) under PB working | — | — | — | 856 | |
| — | 1.00 | — | — | ||
| 50% extra for Erection of Extra items for additional fittings at a Turnout/Diamond crossing or overlap (extra of assorted components) under night PB working | — | — | — | 428 | |
| — | 2.00 | — | — | ||
| Supply of Guy Rod assembly Including Mast Anchor/Guy Rod fittings. | — | — | — | 20,692 | |
| — | 2.00 | — | — | ||
| Erection Guy Rod assembly Including Mast Anchor/Guy Rod fittings | — | — | — | 2,322 | |
| — | 2.00 | — | — | ||
| 100% extra for Erection Guy Rod assembly Including Mast Anchor/Guy Rod fittings under PB working | — | — | — | 2,322 | |
| — | 2.00 | — | — | ||
| 50% extra for Erection Guy Rod assembly Including Mast Anchor/Guy Rod fittings under night PB working | — | — | — | 1,161 | |
| — | 1.00 | — | — | ||
| Supply of Regulating Equipment 3 pulley type with Counter Weight assembly & guide tube for conventional type OHE | — | — | — | 1,03,870 | |
| — | 1.00 | — | — | ||
| Erection of Regulating Equipment 3 pulley type with Counter Weight assembly & guide tube for conventional type OHE | — | — | — | 3,428 | |
| — | 1.00 | — | — | ||
| 100% extra for Erection of Regulating Equipment 3 pulley type with Counter Weight assembly & guide tube for conventional type OHE under PB working | — | — | — | 3,428 | |
| — | 1.00 | — | — | ||
| 50% extra for Erection of Regulating Equipment 3 pulley type with Counter Weight assembly & guide tube for conventional type OHE under night PB working | — | — | — | 1,714 | |
| — | 1.00 | — | — | ||
| Supply of section insulator assembly for conventional OHE | — | — | — | 45,837 | |
| — | 1.00 | — | — | ||
| Erection of section insulator assembly for conventional OHE | — | — | — | 3,610 | |
| — | 1.00 | — | — | ||
| 100% extra for Erection of section insulator assembly for conventional OHE under PB working | — | — | — | 3,610 | |
| — | 1.00 | — | — | ||
| 50% extra for Erection of section insulator assembly for conventional OHE under night PB working | — | — | — | 1,805 | |
| — | 1.00 | — | — | ||
| Supply of Termination of single conductor of OHE (Component ). | — | — | — | 9,273 | |
| — | 1.00 | — | — | ||
| Erection of Termination of single conductor of OHE with Component | — | — | — | 864 | |
| — | 1.00 | — | — | ||
| 100% extra for Erection of Termination of single conductor of OHE with Component under PB working | — | — | — | 864 | |
| — | 1.00 | — | — | ||
| 50% extra for Erection of Termination of single conductor of OHE with Component under night PB working | — | — | — | 432 | |
| — | 1.00 | — | — | ||
| Supply of Termination of Double conductor of OHE(Component ) | — | — | — | 10,431 | |
| — | 1.00 | — | — | ||
| Erection of Termination of Double conductor of OHE with Component | — | — | — | 972 | |
| — | 1.00 | — | — | ||
| 100% extra for Erection of Termination of Double conductor of OHE with Component under PB working | — | — | — | 972 | |
| — | 1.00 | — | — | ||
| 50% extra for Erection of Termination of Double conductor of OHE with Component under night PB working | — | — | — | 486 | |
| — | 1.00 | — | — | ||
| Supply of Component of Anticreep of cadmium copper wire | — | — | — | 12,152 | |
| — | 1.00 | — | — | ||
| Erection of cadmium copper wire Anticreep with Component | — | — | — | 4,429 | |
| — | 1.00 | — | — | ||
| 100% extra for Erection of cadmium copper wire Anticreep with Component under PB working | — | — | — | 4,429 | |
| — | 1.00 | — | — | ||
| 50% extra for Erection of cadmium copper wire Anticreep with Component under night PB working | — | — | — | 2,214.5 | |
| — | 3.00 | — | — | ||
| Supply of Component of Solid core cut-in insulator. | — | — | — | 5,451 | |
| — | 3.00 | — | — | ||
| Erection of Component of Solid core cut-in insulator. | — | — | — | 3,138 | |
| — | 3.00 | — | — | ||
| Extra 100% for Erection of Solid core cut-in insulator with Component complete Under Power Block Working | — | — | — | 3,138 | |
| — | 3.00 | — | — | ||
| Extra 50% for Erection of Solid core cut-in insulator with Component complete Under night Power Block Working | — | — | — | 1,569 | |
| — | 25.00 | — | — | ||
| Supply of Structure bond (including GI Bolt with Nut, Check-nut, Plain washers and spring washer) | — | — | — | 19,500 | |
| — | 25.00 | — | — | ||
| Erection of Structure bond | — | — | — | 3,600 | |
| — | 10.00 | — | — | ||
| Supply of Longitudinal Bond (including GI Bolt with Nut, Check-nut, Plain washers and spring washer) | — | — | — | 5,340 | |
| — | 10.00 | — | — | ||
| Erection Longitudinal Bond (C bond for cross Over & Glued joint) | — | — | — | 1,140 | |
| — | 10.00 | — | — | ||
| Supply of Transverse/ Special Bond /Z-Bond (including GI Bolt with Nut, Check-nut, Plain washers and spring washer) | — | — | — | 13,260 | |
| — | 10.00 | — | — | ||
| Erection of Transverse/ Special Bond | — | — | — | 3,330 | |
| — | 1.00 | — | — | ||
| Supply of structure bond for platform of approx. 8 meter length | — | — | — | 1,849 | |
| — | 1.00 | — | — | ||
| Erection of structure bonds on platform including drilling of holes instructure and rail including cutting of platform surface upto depth of 100 mm placing of bond and making surface with PCC Erection of structure bonds on platform including drilling of holes in structure and rail including cutting of platform surface upto depth of 100 mm placing of bond and making good surface with PCC. | — | — | — | 4,165 | |
| — | 5.00 | — | — | ||
| Suply of Number Plate Retro Reflective type (Mast/Structure) | — | — | — | 3,550 | |
| — | 5.00 | — | — | ||
| Erection of Number Plate Retro Reflective type (Mast/Structure) | — | — | — | 535 | |
| — | 25.00 | — | — | ||
| Supply of stay arm porcelain Insulator (CD-1050 mm) | — | — | — | 1,48,500 | |
| — | 25.00 | — | — | ||
| Supply of bracket porcelain Insulator (CD-1050 mm) | — | — | — | 1,45,375 | |
| — | 3.00 | — | — | ||
| Supply of 9 T porcelain Insulator (CD-1050 mm) | — | — | — | 20,238 | |
| — | 1.00 | — | — | ||
| Supply of Core insulator of section insulator | — | — | — | 6,749 | |
| — | 50.00 | — | — | ||
| Supply of Large Span wire (130sqmm) | — | — | — | 54,100 | |
| — | 50.00 | — | — | ||
| Erection of Large Span wire (130sqmm) | — | — | — | 3,050 | |
| — | 50.00 | — | — | ||
| 100% Extra for erection of Large Span wire (130sqmm) complete Under Power Block Working | — | — | — | 3,050 | |
| — | 50.00 | — | — | ||
| 50% Extra for erection of Large Span wire (130sqmm) complete Under night Power Block Working | — | — | — | 1,525 | |
| — | 250.00 | — | — | ||
| Supply of Dropper wire (5mm) | — | — | — | 47,000 | |
| — | 40.00 | — | — | ||
| Supply of Dropper wire (7mm) | — | — | — | 11,880 | |
| — | 20.00 | — | — | ||
| Supply of Annealed copper Small jumper wire (50 sqmm 19/1.8 mm) | — | — | — | 9,580 | |
| — | 5.00 | — | — | ||
| Supply of Components of Copper jumper (C Jumper & Anti Theft) | — | — | — | 16,380 | |
| — | 5.00 | — | — | ||
| Erection of Copper jumper (C Jumper & Anti Theft) with Components | — | — | — | 845 | |
| — | 5.00 | — | — | ||
| 100% extra for Erection of Copper jumper (C Jumper & Anti Theft) with Components under PB working | — | — | — | 845 | |
| — | 5.00 | — | — | ||
| 50% extra for Erection of Copper jumper (C Jumper & Anti Theft) with Components under night PB working | — | — | — | 422.5 | |
| — | 20.00 | — | — | ||
| Transfer of Equipment from one Mast/Support to another | — | — | — | 68,100 | |
| — | 20.00 | — | — | ||
| 100% extra for Transfer of Equipment from one Mast/Support to another under PB working | — | — | — | 68,100 | |
| — | 20.00 | — | — | ||
| 50% extra for Transfer of Equipment from one Mast/Support to another under night PB working | — | — | — | 34,050 | |
| — | 1.00 | — | — | ||
| Supply of Splicing & Extension of OHE | — | — | — | 4,358 | |
| — | 1.00 | — | — | ||
| Erection of Splicing & Extension of OHE | — | — | — | 6,296 | |
| — | 1.00 | — | — | ||
| 100% extra for Erection of Splicing & Extension of OHE under PB working | — | — | — | 6,296 | |
| — | 1.00 | — | — | ||
| 50% extra for Erection of Splicing & Extension of OHE under night PB working | — | — | — | 3,148 | |
| Each Span | 2.00 | — | — | ||
| Re-droppering of spans including making profilingand adjustment of height & adjustment of encumbrancei ncluding removal of kink. | — | — | — | 3,426 | |
| Each Span | 2.00 | — | — | ||
| 100% extra for Re-droppering of spans including making profilingand adjustment of height & adjustment of encumbrancei ncluding removal of kink under PB | — | — | — | 3,426 | |
| Each Span | 2.00 | — | — | ||
| 50% extra for Re-droppering of spans including making profilingand adjustment of height & adjustment of encumbrancei ncluding removal of kink under night PB | — | — | — | 1,713 | |
| — | 500.00 | — | — | ||
| Supply of Anti bird disc for prevention of bird fault as per maintenance instruction No. TI/MI/0059-Rev.2 or latest | — | — | — | 5,19,000 | |
| — | 500.00 | — | — | ||
| Erection of Anti bird disc for prevention of bird fault as per maintenance instruction No. TI/MI/0059-Rev.2 or latest | — | — | — | 64,500 | |
| — | 500.00 | — | — | ||
| 100% extra for Erec of Anti bird disc for prevention of bird fault as per maintenance instruction No. TI/MI/0059-Rev.2 or latest under PB | — | — | — | 64,500 | |
| — | 500.00 | — | — | ||
| 50% extra for Erection of Anti bird disc for prevention of bird fault as per maintenance instruction No. TI/MI/0059-Rev.2 or latest under night PB | — | — | — | 32,250 | |
| — | 10.00 | — | — | ||
| Drilling of holes on rails | — | — | — | 820 | |
| — | 12.00 | — | — | ||
| Disconnection/Reconnection of missing/opened/ existing traction bond. | — | — | — | 828 | |
| Each Span | 25.00 | — | — | ||
| Adjustment of existing OHE & Tower wagon checking. | — | — | — | 19,875 | |
| Each Span | 25.00 | — | — | ||
| 100% extra for Adjustment of existing OHE & Tower wagon checking under PB working | — | — | — | 19,875 | |
| Each Span | 25.00 | — | — | ||
| 50% extra for Adjustment of existing OHE & Tower wagon checking under night PB working | — | — | — | 9,937.5 | |
| — | 1000.00 | — | — | ||
| Trimming of tree branches to maintain a minimum clearance of 05 to 06 metres from OHE (01 Big branch consisting of 5 small branch) | — | — | — | 82,000 | |
| — | 10.00 | — | — | ||
| 100% extra for Trimming of tree branches to maintain a minimum clearance of 05 to 06 metres from OHE (01 Big branch consisting of 5 small branch) under PB working | — | — | — | 820 | |
| — | 10.00 | — | — | ||
| 50% extra for Trimming of tree branches to maintain a minimum clearance of 05 to 06 metres from OHE (01 Big branch consisting of 5 small branch) under night PB working | — | — | — | 410 | |
| — | 20.00 | — | — | ||
| Dismantling of Mast/Structure upright | — | — | — | 80,200 | |
| — | 20.00 | — | — | ||
| 100% extra for Dismantling of Mast/Structure upright under PB working | — | — | — | 80,200 | |
| — | 20.00 | — | — | ||
| 50% extra for Dismantling of Mast/Structure upright under night PB working | — | — | — | 40,100 | |
| — | 20.00 | — | — | ||
| Dismantling of Cantilever | — | — | — | 17,540 | |
| — | 20.00 | — | — | ||
| 100% extra for Dismantling of Cantilever under PB working | — | — | — | 17,540 | |
| — | 20.00 | — | — | ||
| 50% extra for Dismantling of Cantilever under night PB working | — | — | — | 8,770 | |
| — | 1.00 | — | — | ||
| Dismantling of Section insulator | — | — | — | 3,339 | |
| — | 1.00 | — | — | ||
| 100% extra for Dismantling of Section insulator under PB | — | — | — | 3,339 | |
| — | 1.00 | — | — | ||
| 50% extra for Dismantling of Section insulator under night PB | — | — | — | 1,669.5 | |
| — | 2.00 | — | — | ||
| Dismantling of Guy rod | — | — | — | 2,046 | |
| — | 2.00 | — | — | ||
| 100% extra for Dismantling of Guy rod under PB working | — | — | — | 2,046 | |
| — | 2.00 | — | — | ||
| 50% extra for Dismantling of Guy rod under night PB working | — | — | — | 1,023 | |
| — | 1.00 | — | — | ||
| Dismantling of Anticreep | — | — | — | 4,915 | |
| — | 1.00 | — | — | ||
| 100% extra for Dismantling of Anticreep under PB | — | — | — | 4,915 | |
| — | 1.00 | — | — | ||
| 50% extra for Dismantling of Anticreep under night PB | — | — | — | 2,457.5 | |
| — | 1.00 | — | — | ||
| Dismantling of Regulating Equipment assembly with counter & guide tube | — | — | — | 4,759 | |
| — | 1.00 | — | — | ||
| 100% extra for Dismantling of Regulating Equipment assembly with counter & guide tube under PB | — | — | — | 4,759 | |
| — | 1.00 | — | — | ||
| 50% extra for Dismantling under night PB | — | — | — | 2,379.5 | |
| — | 0.10 | — | — | ||
| Dismantling of small steel parts | — | — | — | 495.4 | |
| — | 0.10 | — | — | ||
| 100% extra for Dismantling of small steel parts under PB working | — | — | — | 495.4 | |
| — | 0.10 | — | — | ||
| 50% extra for Dismantling of small steel parts under night PB working | — | — | — | 247.7 | |
| — | 1.00 | — | — | ||
| Dismantling of foundation etc. | — | — | — | 2,406 | |
| — | 10.00 | — | — | ||
| Dismantling of Structure Bond | — | — | — | 670 | |
| — | 1.00 | — | — | ||
| Supply of Single Earth Electrode. | — | — | — | 3,221 | |
| — | 1.00 | — | — | ||
| Erection of Single Earth Electrode. | — | — | — | 2,285 | |
| — | 0.50 | — | — | ||
| Preparation & Supply of GAD, Section Diagram, LOP & CSD | — | — | — | 4,343.5 | |
| — | 0.50 | — | — | ||
| Preparation & supply of SED & As erected Drawing | — | — | — | 4,088.5 | |
| — | 2.00 | — | — | ||
| Warning board caution live wire drg. No. ETI/OHE/P-7540, specification no. ETI/OHE/33(2/73) or latest | — | — | — | 2,526 | |
| — | 2.00 | — | — | ||
| Caution plate 25kV A.C. as per RDSO drg. No ETI/OHE/P-7532, specification ETI/OHE/33(273)or latest | — | — | — | 1,874 | |
| — | 2.00 | — | — | ||
| Dead section caution boards ( power block working limit) drg. No. ETI/OHE/P-7574, specification No. ETI/OHE/33 (2/73)or latest | — | — | — | 2,716 | |
| — | 2.00 | — | — | ||
| Dead section caution boards (Caution unwire turnout) drg. No. ETI/OHE/P-7573, specification No. ETI/OHE/33 (2/73)or latest | — | — | — | 4,930 | |
| — | 2.00 | — | — | ||
| Dead section caution boards (Electric engine STOP) drg. No. ETI/OHE/P-7572, specification No. ETI/OHE/33 (2/73)or latest | — | — | — | 5,054 | |
| — | 2.00 | — | — | ||
| Danger plate in level crossing gate to electrified section for WB drg. No.ETI/C/0069, specification no ETI/OHE/33(2/73)or latest | — | — | — | 5,540 | |
| — | 2.00 | — | — | ||
| General Caution notice for staff drg. No. RE/33/496, specification no. ETI/OHE/33 or latest | — | — | — | 1,038 | |
| — | 2.00 | — | — | ||
| General caution notice for entrence to Rly. Stn. No.RE/33/P-7551, specification No.ET/OHE/33(273) or latest | — | — | — | 1,176 | |
| — | 2.00 | — | — | ||
| General cautionnotice No.ET/OHE/33(273) or latest | — | — | — | 1,262 | |
| — | — | — | No.RE/33/P-7561,specification | ||
| — | 2.00 | — | — | ||
| Caution Boards for neutral Section of Size 750x450mm for 500 M & 250M. | — | — | — | 2,826 | |
| — | 2.00 | — | — | ||
| Caution Boards for neutral Section of Size 800x400mm for Open DJ and Close DJ. | — | — | — | 2,856 | |
| — | 1.00 | — | — | ||
| Key Box for isolator with lock Key | — | — | — | 1,898 | |
| — | 1.00 | — | — | ||
| Modification to section Diagram board at stations and TPC | — | — | — | 2,801 | |
| — | 1.00 | — | — | ||
| Shock treatment chart laminated | — | — | — | 3,606 | |
| — | 40.00 | — | — | ||
| 40 kv 'Hand gloves rubber', made with suitable insulating rubber, for electrical applications, test potential voltage 40000 V and maximum use 36000 V. length 400 mm, palm size 10 inches as per IS 13774:1993. | — | — | — | 1,65,040 | |
| — | 1.00 | — | — | ||
| supply of earthing discharge rod complete suitable for working voltage of 25KV AC traction, fiber glass body screw type in a suitable carry bag as per RDSO specification no. ETI/OHE/51(9/87) or latest | — | — | — | 12,139 | |
| — | 1.00 | — | — | ||
| First Aid box Supply & Installation | — | — | — | 1,969 | |
| — | 5.00 | — | — | ||
| Supply of Portable light weight tree cutting machine with safety helmet with face shield(ms180). | — | — | — | 2,42,100 | |
| — | 5.00 | — | — | ||
| 2 Stroke Air-cooled Engine Petrol operated Telescopic Pole Pruner, Length 390 centimeter 12 inch Bar length "Make:- STIHL Model :- HT75" or similar | — | — | — | 3,03,850 | |
| — | 2.00 | — | — | ||
| Supply, installation, testing, commssioning of TDMS monitoring system consist with Software update console. | — | — | — | 1,69,396 | |
| — | 5.00 | — | — | ||
| Supply of Operating rod for Drop Out fuse (DO Fuse) switch as per RDSO SPECN. ETI/PSI/14 (1/86) latest. | — | — | — | 53,345 | |
| — | 500.00 | — | — | ||
| Supply of CONTACT WIRE PARALLEL CLAMP SMALL COMPLETE WITH FASTENERS RI NO.1041-2 (MODB) CONFIRMING TO RDSO DRG.NO.ETI/OHE/P/1040-2 MOD E. or latest | — | — | — | 1,08,500 | |
| — | 100.00 | — | — | ||
| Supply of Contact wire parallel clamp (Large) complete with fasteners as per RDSO specification no. ETI/OHE/P/1030-2 REV-D. Accepted Firm's Offer: PARALLEL CLAMP 1030-2 COMPLETE WITH GI FASTENERS BOLTS & NUTS 16X50X38 WITH SPRING WASHER AS PER RDSOS DRG. NO. ETI OHE-P-1030-2 REV D OR LATEST. | — | — | — | 24,100 | |
| — | 100.00 | — | — | ||
| Supply of Parallel clamp (150/160) RI.No.1051-3 with Fasteners as per RDSO Drg. No. ETI/OHE/P/1050-3 Rev-A , Complete set or latest | — | — | — | 30,600 | |
| — | 4600.00 | — | — | ||
| Supply of COPPER SPLIT PIN 2.5X25 MM FOR CATENARY WIRE DROPPER CLIP BOLT AS PER RDSO: SPECIFICATION NO. TI/SPC/OHE/FASTENER/0120 REV-1 (MARCH-2017) OR LATEST | — | — | — | 7,222 | |
| — | 470.00 | — | — | ||
| Supply of Catenary dropper clip as per RDSO Drg. No. ETI/OHE/P/1192, Rev-C with complete fastener. Drg. No. RDSO Drg. No. ETI/OHE/P/1192,Rev-C. RDSO Spec. No. TI/SPC/OHE/Fitngs/s13s-1s/13-REV-1. | — | — | — | 36,190 | |
| — | 10.00 | — | — | ||
| Supply of Come along clamps for Aluminium "Spider" Conductor (20mm2) as per Rly Appv Drg No. POWER/4572 or latest | — | — | — | 31,840 | |
| — | 50.00 | — | — | ||
| LARGE SUSPENSION CLAMP 20 MM COMPLETE WITH ALL ACCESSORIES AND FASTENERS AS PER RDSO DRG NO. ETI/OHE/P/1580 REV.F (SHEET-1) OR LATEST & RDSO SPEC NO. TI/SPC/OHE/FITTINGS/0130 (10/13 )REV.1 OR LATEST | — | — | — | 31,800 | |
| — | 1.00 | — | — | ||
| Supply of Light Wight Section Insulator(LWSI) Assembly as per RDSO Spec No. TI/SPC/OHE/ LWTSI/ 0060 or latest | — | — | — | 4,10,227 |
Tap a document below to read it instantly. You can also download everything as a ZIP if you prefer.
details.html
HTML
nit.pdf
NIT
GCC2022correctionslipno1to10_compressed.pdf GCC correction slip 1 to 10
ATTACHMENT
1 GCC 2022
ATTACHMENT
TenderDocsMicsOHE.pdf
ATTACHMENT
GCC_April-2022_2022_CE-I_CT_GCC-2022_POLICY_27.04.22.pdf
ATTACHMENT
GCC2022correctionslipno1to10_compressed.pdf
ATTACHMENT
Download all tender documents and submit your bid
Disclaimer: TenderKart has made every reasonable effort to ensure that the information on this page is accurate and authentic, however it cannot be held liable for any third-party claims or losses or any damages. TenderKart makes no warranty, expressed or implied, as to the results obtained from the use of this information. If you notice any error or omission, please let us know at .