| # | Company | Amount | Rank | Status |
|---|---|---|---|---|
| 1 | L1₹71.2 LAdmitted-Finance TUTICORIN | TUTICORIN | TAMIL NADU | 626202 | ₹71.2 L | L1 | Admitted-Finance |
| 2 | L2₹81.3 L+₹10.0 L (14.0%)Admitted-Finance | ₹81.3 L+₹10.0 L (14.0%) | L2 | Admitted-Finance |
| 3 | Rejected-Technical | - | - | Rejected-Technical Technically not qualified. |
| Sl No | Description | Qty | Unit | Ramesh Enterprises L1 | PEARL ENTERPRISES L2 |
|---|---|---|---|---|---|
| 1.00 | Painting of structural members, pipelines, Pressure Vessels and overhead structures in Utility & SWRO section. The work includes Surface preparation and applying two coat of primer, two coats of Aliphatic Polyurethane paint on structures, pipelines, Pressure vessels and chequered plates with DFT not less than 120micron and two coat of primer, two coats of heat resistance paint on Boiler surface with DFT not less than 120micron. The scope of work includes the supply of PU paint(Aliphatic), heat resistant paint, primer, thinner, cleaning materials, tools, tackles and manpower for completing the job as required and directed by
the Engineer in- charge. The rate shall include cost of material, consumable, labour, and other
expenditure involved for finished item. | 3,750 | Sq.Mtr. | 320 ₹12,00,000 Lowest | 600 ₹22,50,000 |
| 2.00 | Erection & de-erection of scaffolding at various locations of Zirconium Complex as per engineer in charge direction for painting work with supply of required scaffolding pipes, clamps, safety platform grills etc as per IS:4014(Part 1&2)-1967 | 4,617 | Sq.Mtr. | 150 ₹6,92,550 Lowest | 600 ₹27,70,200 |
| 3.00 | Replacement of Damaged Metallic Structures, channels and I beams at Utility and SWRO section as per engineer in charge which involves work at height. The work is inclusive of all consumables, welding, Gas cutting and Fabrication work along with manpower and PPE's. The list of structures to be supplied and replaced in indicated in Annexure B. | 3,700 | kg | 133 ₹4,92,100 Lowest | 600 ₹22,20,000 |
| 4.00 | Floor Painting of areas in Utility &SWRO section over concrete / Floor. The work is inclusive of removal of debris, scaling. Water, moisture, oil, grease any other contaminants on floor which
includes surface preparation by scrapping mechanical surface grinding / buffing, washing, cleaning, drying, filling of epoxy mortar to holes, inclusive of primer, paint, thinner etc with all
necessary equipments, labours complete as per the Technical Specifications and as directed by the Engineer- In- Charge. | 1,580 | Sq.Mtr. | 3,000 ₹47,40,000 | 560 ₹8,84,800 Lowest |
Tender Value
₹91 L
EMD Value
₹1.8 L
Closing Date
9 Jul 2026, 2:00 pmClosed
GENERAL MANAGER
Zirconium Complex, Pazhayakayal, Tuticorin.
Painting of structural members, Pipelines, Floor paint, Overhead Support Structures and Pressure Vessels in Utility and SWRO, Zirconium Complex, Pazhayakayal - Tuticorin-628152
2026_NFC_912972_1
ZC/NFC/UTY/2026/65
Open Tender
Job Works
Item Rate
365 days
ZIRCONIUM COMPLEX, PAZHAYAKAYAL
Please refer Tender documents.
8 documents required · 8 mandatory
₹0
₹1.8 L
Yes
13 Aug 2026
17 Jun 2026
10 Jul 2026
19 Jun 2026
9 Jul 2026
19 Jun 2026
| Sl No | Description | Qty | Unit | Est. Rate | Est. Amount |
|---|---|---|---|---|---|
| 1 | Painting of structural members, pipelines, Pressure Vessels and overhead structures in Utility & SWRO section. The work includes Surface preparation and applying two coat of primer, two coats of Aliphatic Polyurethane paint on structures, pipelines, Pressure vessels and chequered plates with DFT not less than 120micron and two coat of primer, two coats of heat resistance paint on Boiler surface with DFT not less than 120micron. The scope of work includes the supply of PU paint(Aliphatic), heat resistant paint, primer, thinner, cleaning materials, tools, tackles and manpower for completing the job as required and directed by
the Engineer in- charge. The rate shall include cost of material, consumable, labour, and other
expenditure involved for finished item. | 3,750 | Sq.Mtr. | - | - |
| 2 | Erection & de-erection of scaffolding at various locations of Zirconium Complex as per engineer in charge direction for painting work with supply of required scaffolding pipes, clamps, safety platform grills etc as per IS:4014(Part 1&2)-1967 | 4,617 | Sq.Mtr. | - | - |
| 3 | Replacement of Damaged Metallic Structures, channels and I beams at Utility and SWRO section as per engineer in charge which involves work at height. The work is inclusive of all consumables, welding, Gas cutting and Fabrication work along with manpower and PPE's. The list of structures to be supplied and replaced in indicated in Annexure B. | 3,700 | kg | - | - |
| 4 | Floor Painting of areas in Utility &SWRO section over concrete / Floor. The work is inclusive of removal of debris, scaling. Water, moisture, oil, grease any other contaminants on floor which
includes surface preparation by scrapping mechanical surface grinding / buffing, washing, cleaning, drying, filling of epoxy mortar to holes, inclusive of primer, paint, thinner etc with all
necessary equipments, labours complete as per the Technical Specifications and as directed by the Engineer- In- Charge. | 1,580 | Sq.Mtr. | - | - |
stage.html
html • 0.03 MB
tech_eval.pdf
boq_comp_chart.xlsx
xlsx
Tap a document below to read it instantly. You can also download everything as a ZIP if you prefer.
details.html
html • 0.03 MB
Tendernotice_1.pdf
PDF • 13.51 MB
AtoH.xls
Tender Documents • 0.09 MB
BOQ_959476.xls
BOQ • 0.25 MB
Corrigendum.pdf
PDF • 0.69 MB
Download all tender documents and submit your bid
Disclaimer: TenderKart has made every reasonable effort to ensure that the information on this page is accurate and authentic, however it cannot be held liable for any third-party claims or losses or any damages. TenderKart makes no warranty, expressed or implied, as to the results obtained from the use of this information. If you notice any error or omission, please let us know at .