Tender ID
Tender Value
₹133.6 Cr
EMD Value
₹2.7 Cr
Closing Date
2 Jun 2026, 12:30 pmClosed
Yes (up to 3 members)
No
Two Packet System
Normal Tender
Yes
24/04/2026 15:30
Lowest to Highest
90 days
Expenditure
Capital (Works)
PROJECTBSB
14 conditions · 2 needing a document upload
The tenderer must have minimum average annual contractual turnover of 'V/N' or 'V' whichever is less; where V= Advertised value of the tender in crores of Rupees. N= Number of years prescribed for completion of work for which bids have been invited. The average annual contractual turnover shall be calculated as an average of "total contractual payments" in the previous three financial years, as per the audited balance sheet. However, in case balance sheet of the previous year is yet to be prepared/ audited, the audited balance sheet of the fourth previous year shall be considered for calculating average annual contractual turnover. The tenderers shall submit requisite information as per Annexure-VIB of GCC 2022, along with copies of Audited Balance Sheets duly certified by the Chartered Accountant/ Certificate from Chartered Accountant duly supported by Audited Balance Sheet, and as per tender document.
a.The tenderer must have successfully completed or substantially completed any one of the following categories of work(s) during last 07 (seven) years, ending last day of month previous to the one in which tender is invited: i.Three similar works each costing not less than the amount equal to 30% of advertised value of the tender, OR ii.Two similar works each costing not less than the amount equal to 40% of advertised value of the tender, OR iii.One similar work costing not less than the amount equal to 60% of advertised value of the tender. b. In case of tenders for composite works (e.g. works involving more than one distinct component, such as Civil Engineering works, S&T works, Electrical works, OHE works etc. and in the case of major bridges - substructure, superstructure etc.) (Not Applicable for this Tender), tenderer must have successfully completed or substantially completed any one of the following categories of work(s) during last 07 (seven) years, ending last day of month previous to the one in which tender is invited: i.Three similar works each costing not less than the amount equal to 30% of advertised value of each component of tender, OR ii.Two similar works each costing not less than the amount equal to 40% of advertised value of each component of tender, OR iii.One similar work each costing not less than the amount equal to 60% of advertised value of each component of tender. Note for b: Separate completed works of minimum required values shall also be considered for fulfillment of technical eligibility criteria for different components, and as per tender document.
Defination of Similar Work :- Any work of MACLS with Electronic Interlocking or Panel Interlocking or Route relay Interlocking (Indoor or both Indoor and Outdoor) on any passenger carrying system.
60 conditions · 13 needing a document upload
Please enter the percentage of local content in the material being offered. Please enter 0 for fully imported items, and 100 for fully indigenous items. The definition and calculation of local content shall be in accordance with the Make in India policy as incorporated in the tender conditions.
Tenderer(s) on award of contract will have to enter into agreement with Railway in format of above mentioned original tender documents. Tenderer(s) shall not have any right/claim to insist on signing of contract agreements in format on which tender document were forwarded by him on e-tendering website.
If during process of tender finalization, it is detected that tenderer has submitted tender documents after making any changes / additions / deletions in the tender documents on e- tendering website, then, the earnest money deposited by the tenderer shall be forfeited by the Railway. Further, if after award of contract, it is detected that tenderer has submitted tender documents after making any changes/additions/deletions in the tender documents etendering website then Railway will take action to remove the contract from the work in terms of clause 62 of GCC 2022 and initiate such further legal action against contractor as it considered necessary.
False/Incomplete statement: Any statement/declaration made by the Tenderer, if proved wrong or false or incomplete or such as to withhold any information relevant to the award of the tender, at any stage of the tender or in the event of his tender having been accepted at any stage of the contract, shall tender his/their tender(s)/contractors) liable to be cancelled/rescinded, in addition to the following: (i) If such statement is found at the stage of tender his total earnest money shall be forfeited. (ii) In case such a statement is found at the contract stage rights available to the Railways under clause 62 of the GCC-2022 shall be applicable.
Design, Programming, Installation, Supply, Testing and Commissioning of Electronic Interlocking (EI) System Conforming to RDSO Specification No. RDSO/SPN/192/2019 or Latest (With Latest Amendment if any) as per SIP along with Indoor & Outdoor Work Including Part Supply of Materials at (SANR,CC,GB,BALR, DEOS, NRA, BHTR , BTK ,MW, ZRDE, PCK,DDA , CW,EM, DDP, and KPS ) (Centralized Type) Stations and Siwan Jn. & CHPG Station (Distributed 1+2 Type) in between GKC-CHPG Sections, Automatic Block Signaling work in CPR Jn-CI-CHPG Block Section and work for OFC cables GKC - BTT and CPR Jn-CI-CHPG Sections in Varanasi Division of N.E. Railway
NER_SnT_Proj_BSB_01_2026
NER_SnT_Proj_BSB_01_2026
Open
Works - General
18 Months
Gorakhpur, Uttar Pradesh
₹0
₹2.7 Cr
10 Apr 2026
10 Apr 2026
19 May 2026
24 Apr 2026
2 items across 1 schedule · ₹98,49,840 total
| # | Description | Unit | Qty | Rate | Amount |
|---|---|---|---|---|---|
| 1 | Execution | Square Foot | 14350.00 | 135.18 | 19,39,833 |
| 2 | Supply | Square Foot | 14350.00 | 551.22 | 79,10,007 |
| Schedule total | ₹98,49,840 | ||||
Tap a document below to read it instantly. You can also download everything as a ZIP if you prefer.
details.html
HTML
nit.pdf
NIT
GCC2022.pdf
ATTACHMENT
ACS1to11_compressed.pdf
ATTACHMENT
DrawingIRSEM.pdf
ATTACHMENT
TenderDocument.pdf
ATTACHMENT
CorrigendumofTenderDocument.pdf
CORRIGENDUM
Download all tender documents and submit your bid
Disclaimer: TenderKart has made every reasonable effort to ensure that the information on this page is accurate and authentic, however it cannot be held liable for any third-party claims or losses or any damages. TenderKart makes no warranty, expressed or implied, as to the results obtained from the use of this information. If you notice any error or omission, please let us know at .