Loading…
Loading…
| # | Company | Amount | Rank | Status |
|---|---|---|---|---|
| 1 | L1₹27.0 LAccepted-AOC | ₹27.0 L | L1 | Accepted-AOC L1 |
| 2 | L2₹27.0 LRejected-Finance | ₹27.0 L | L2 | Rejected-Finance L2 |
| Sl No | Description | Qty | Unit | M MANIKANDAN CONTRACTOR L2 | SARATHA & CO L1 |
|---|---|---|---|---|---|
| 1.00Name of Work: STRENGTHENING OF THE ROAD FROM KARAIKUDI-THIRUPATHUR MAIN ROAD TO KANTHI-JEEVA MEMORIAL HALL ROAD KM 0/0 - 0/670 | |||||
| 2.00 | Clearing and grubbing Scrub jungle road land including uprooting wild vegetation, grass, bushes, shrubs, saplings and trees of girth upto 300 mm, removal of stumps of such trees cut earlier and disposal of unserviceable materials and stacking of serviceable material to be used or auctioned, upto a lead of 1000 m including removal and disposal of top organic soil not exceeding 150 mm in thickness as per Technical Specification Clause 201. | 723.6 | M2 | 7 ₹5,065.20 | 6 ₹4,341.60 |
| 3.00 | Earthwork excavation in all classes of soils except hard rock requiring blasting and depositing on bank with all leads and lifts as per SS20B including cost of all labour charges, materials, tools, equipments and all incidental charges, removal of other deleterious matter and obstructions, trimming of bottom of excavation back filling, clearing up the site and disposal of all surplus materials etc., complete as per standard specification. For Boxing including conveyance of sut earth away from the site with average lead | 241.2 | M3 | 141 ₹34,009.20 | 140 ₹33,768 |
| 4.00 | Construction of granular sub-base by providing close graded Material, mixing in a mechanical mix plant at OMC, carriage of mixed Material to work site, spreading in uniform layers with motor grader on prepared surface and compacting with vibratory Soil Compactor to achieve the desired density, complete as per clause 401 | 40.5 | M3 | 2,696 ₹1.1 L | 2,695 ₹1.1 L |
| 5.00 | Providing and Laying Gravel Soling to compacted thick including cost & conveyance of gravel from approved sources to work site including labour for spreading, water and compacting by Power roller to achieve the required Proctor density at 100% compaction at optimum moisture content and hire and fuel charges for power roller, water sprinkler and all other incdidental charges such as traffic barricading and providing danger lights etc., complete. | 80.4 | M3 | 753 ₹60,541.20 | 752 ₹60,460.80 |
| 6.00 | Providing and laying spreading and compacting graded stone aggregate to Wet Mix Macadam(WMM) specification including premixing the material with water at OMC in machanical mix plant carriage of mixed material by tipper to site laying in uniform layers 2 | 260.63 | M3 | 2,761 ₹7.2 L | 2,760 ₹7.2 L |
| 7.00 | Providing and laying of prime coat using Emulsion at the rate of 7 Kg per 10.00 square meter over the WMM surface preparatory to another bituminous construction over it. | 2,512.5 | M2 | 86.5 ₹2.2 L | 86.5 ₹2.2 L |
| 8.00 | Providing and laying Tack coat over WMM surface(treated with primer) using 2.5Kg of bitumen emulsion RS-1 for 10sqm for preparatory to another bituminous construction over it including cost of material, labour charges, rentals for machinery, fuel and all other incidental charges etc., | 2,512.5 | M2 | 20 ₹50,250 | 20 ₹50,250 |
| 9.00 | Providing and laying Bituminious concrete to 30mm thick using 0.13cum of 19.00-9.50mm. 0.17cum of 9.5-2.36 and below with 50.3kgs of VG30/VG40 heating the bitumen and aggregates to required temperature and mixing them in required temperature in central hot mix plant 20-30 ton capacity, carrying the mix by tipper trucks to paver site, spreading the mix to uniform thickness of 40mm with mechanical paver to the specified grades and cross sections and consolidated by 8-10 tonnes vibratory/phenumatic roller to the required density etc., including labour for attending to paver to site etc.including hire charges and fuel charges foe 20-30t CMP with bitumen boiler, tipper trucks,paver finisher/9m paver finisher,vibratory/phenumatic roller and all other tools and plants required, including fuel and all other incidental charges etc., complete as per specification using CMP as per clauses 507 of MORTH Part-5 | 62.81 | M3 | 11,725 ₹7.4 L | 11,725 ₹7.4 L |
| 10.00 | Hecta metre stone | 3 | No | 575 ₹1,725 | 574 ₹1,722 |
Tender Value
₹27.4 L
EMD Value
₹27,350
Closing Date
21 Jan 2026, 3:00 pmClosed
BDO
Union Office,Kallal
STRENGTHENING OF THE ROAD FROM KARAIKUDI-THIRUPATHUR MAIN ROAD TO KANTHI-JEEVA MEMORIAL HALL ROAD KM 0/0 - 0/670
2026_RDTN_643934_1
SiravayalRoad
Open Tender
Civil Works - Roads
180 days
KALLAL
Please refer Tender documents.
3 documents required · 3 mandatory
₹0
₹27,350
Yes
25 Feb 2026
14 Jan 2026
21 Jan 2026
14 Jan 2026
21 Jan 2026
14 Jan 2026
Clearing and grubbing Scrub jungle road land including uprooting wild vegetation, grass, bushes, shrubs, saplings and trees of girth upto 300 mm, removal of stumps of such trees cut earlier and disposal of unserviceable materials and stacking of serviceable material to be used or auctioned, upto a lead of 1000 m including removal and disposal of top organic soil not exceeding 150 mm in thickness as per Technical Specification Clause 201.
Earthwork excavation in all classes of soils except hard rock requiring blasting and depositing on bank with all leads and lifts as per SS20B including cost of all labour charges, materials, tools, equipments and all incidental charges, removal of other deleterious matter and obstructions, trimming of bottom of excavation back filling, clearing up the site and disposal of all surplus materials etc., complete as per standard specification. For Boxing including conveyance of sut earth away from the site with average lead
Construction of granular sub-base by providing close graded Material, mixing in a mechanical mix plant at OMC, carriage of mixed Material to work site, spreading in uniform layers with motor grader on prepared surface and compacting with vibratory Soil Compactor to achieve the desired density, complete as per clause 401
Providing and Laying Gravel Soling to compacted thick including cost & conveyance of gravel from approved sources to work site including labour for spreading, water and compacting by Power roller to achieve the required Proctor density at 100% compaction at optimum moisture content and hire and fuel charges for power roller, water sprinkler and all other incdidental charges such as traffic barricading and providing danger lights etc., complete.
Providing and laying spreading and compacting graded stone aggregate to Wet Mix Macadam(WMM) specification including premixing the material with water at OMC in machanical mix plant carriage of mixed material by tipper to site laying in uniform layers 2
Providing and laying of prime coat using Emulsion at the rate of 7 Kg per 10.00 square meter over the WMM surface preparatory to another bituminous construction over it.
Providing and laying Tack coat over WMM surface(treated with primer) using 2.5Kg of bitumen emulsion RS-1 for 10sqm for preparatory to another bituminous construction over it including cost of material, labour charges, rentals for machinery, fuel and all other incidental charges etc.,
Providing and laying Bituminious concrete to 30mm thick using 0.13cum of 19.00-9.50mm. 0.17cum of 9.5-2.36 and below with 50.3kgs of VG30/VG40 heating the bitumen and aggregates to required temperature and mixing them in required temperature in central hot mix plant 20-30 ton capacity, carrying the mix by tipper trucks to paver site, spreading the mix to uniform thickness of 40mm with mechanical paver to the specified grades and cross sections and consolidated by 8-10 tonnes vibratory/phenumatic roller to the required density etc., including labour for attending to paver to site etc.including hire charges and fuel charges foe 20-30t CMP with bitumen boiler, tipper trucks,paver finisher/9m paver finisher,vibratory/phenumatic roller and all other tools and plants required, including fuel and all other incidental charges etc., complete as per specification using CMP as per clauses 507 of MORTH Part-5
Hecta metre stone
Provision for Cautionary Sign Boards
Provision for Mandatory Sign Boards
Road Marking with Hot applied Thermoplastic compound with Reflectorising glass beads on Bituminous surface
Earthwork excavation and depositing on bank with initial lead and list in all classes of soils except hard rock reg. blasting etc., complete as per SS 20B for foundation.
Collection and filling of river sand including cost and conveyance to site and all labour charges for filling water and ramming etc., complete for foundation.
C.C 1:4:8 using 40mm ISS ,HBG metal including cost and conveyance of all materials and all labour charges etc, complete
Supplying and erecting of centering items including cost & conveyance of all materials to site and all labour charges etc., complete.
Cement Concrete 1:3:6 mix using 40mm ISS HBG metal including cost of conveyance of all materials and all labour charges etc., complete for foundation
Collection and supply of Gravel filling in to the Road including cost and conveyance to the siteand all labour charges for filling as per standard specifications
Supply of NP3 pipe including suitabel collars including cost and conveyance at site etc., complete.
GST Amount for providing Service to Government Contract Works for the above Construction Works. { GST Amount is the Total GST Amount for total overall quoted amount above this row in column "BB" for all works in this package}
Please Enable Macros to View BoQ information
stage.html
html • 0.04 MB
tech_eval.pdf
fin_eval.pdf
aoc.pdf
finance_771629.pdf
boq_comp_chart.xlsx
xlsx
Tap a document below to read it instantly. You can also download everything as a ZIP if you prefer.
details.html
html • 0.03 MB
Tendernotice_1.pdf
PDF • 1.44 MB
tENDERNOTICE.pdf
Tender Documents • 1.43 MB
BOQ_771629.xls
BOQ • 0.28 MB
Download all tender documents and submit your bid