Loading…
Loading…
Tender Value
₹28.7 L
EMD Value
₹57,340
Closing Date
17 Aug 2026, 1:00 pmClosed
Executive Officer
Municipal Board Nokha
CONSTRUCTION OF SEWER LINE FROM KANHEYALAL RATHI HOUSE VIA JHALUSINGH HOUSE TO R.K. PURAM COLONY WARD NO. 25 NOKHA
2026_DLB_585471_1
E NIT 03/2026-27 (3)
Open Tender
Civil Works - Roads
Percentage
90 days
Nokha
Please refer Tender documents.
2 documents required · 2 mandatory
₹500
Executive Officer
₹57,340
Yes
10 Aug 2026
10 Aug 2026
18 Aug 2026
10 Aug 2026
17 Aug 2026
10 Aug 2026
This is a percentage-rate BOQ. The schedule below shows estimated quantities and rates. Bidders quote a single percentage above or below the total estimated cost.
| Sl No | Description | Qty | Unit | Est. Rate | Est. Amount |
|---|---|---|---|---|---|
| 1 | Earth work for Sewer line and Manhole in excavation in foundation, trenches manholes, road side chambers etc. including dressing of sides and ramming of bottoms, including getting out the excavated material, refilling after laying pipe/ foundation and disposal of surplus excavated material at a lead upto 50m suitable site as per direction of Engineer for following depths, below natural ground / Road top level including allowances for any additional excavation beyond the drawings (measurement for payment to be as per standard drawings), re-handling of material/earth to complete the task.In all types soils/ saturated soil such as moorum, sand, sandy silt, clay, black cotton soil, kankar, etc.Depth upto 1.5 m | - | Cum | 299 | - |
| 2 | Carriage of Materials by mechanical transport including loading, unloading and stacking ::Sand, bazri,ballast, kankar | 400 | Cum | 203.81 | ₹81,524 |
| 3 | Providing and laying in position cement concrete of specified grade excluding the cost of centring and shuttering - All work upto plinth level :1:5:10 (1 cement : 5 fine/ coarse sand : 10 graded stone aggregate 40 mm nominal size) | 90 | Cum | 4,330 | ₹3,89,700 |
| 4 | Providing and laying in position cement concrete of specified grade excluding the cost of centring and shuttering - All work upto plinth level :1:2:4 (1 cement : 2 coarse sand : 4 graded stone aggregate 20 mm nominal size) | 40 | Cum | 5,510 | ₹2,20,400 |
| 5 | Brick work with FPS bricks of class designation 75 in foundation and plinth in:Cement mortar 1:6 (1 cement : 6 coarse sand) | 90 | Cum | 5,400 | ₹4,86,000 |
| 6 | Cement plastering including T&P, scaffolding, material and complete labour, including cost of water, curing, racking of joints etc. with 20 mm cement plaster of mix : including Providing /mixing of synthetic fibers compulsorily complying with IS 16481:2022 of 06 mm/12 mm length to be mixed @ 0.25% by weight of Cement i.e. 125 gms per 50 kg Cement up to 900 gms per cum of Concrete/ mortar 1:4 (1 cement : 4 fine/ coarse sand) | 350 | Sqm | 315.5 | ₹1,10,425 |
| 7 | Reinforcement for R.C.C. work at all levels including straightening, cutting, bending, placing in position and binding all complete.Cold twisted bars | 3,015 | Kg. | 83.3 | ₹2,51,149.5 |
| 8 | Steel work welded in built up sections/ framed work including cutting, hoisting, fixing in position and applying a priming coat of approved steel primer using structural steel etc. as required In gratings, frames, guard bar, ladder, railings, brackets, gates and similar works | 250 | Kg. | 144.5 | ₹36,125 |
| 9 | Supplying & fixing 560mm dia opening SFRC manhole frame & cover as per IS : 12592-2002 in existing manholes including grouting the frame in PCC M-15 complete in all respect as directed by the
Engineer.HD-20 | 67 | Each | 2,675 | ₹1,79,225 |
| 10 | Providing at site, lowering & laying in trenches, aligning & jointing of RCC pipes NP2 class (with s/s ends IS: 458 - 1988 (amended up to date) marked and manufactured through spun process at all levels with Rubber gaskets (EPDM/SBR) for sewer lines as per IS: 5382 (including cost of Rubber gaskets lubricants) as per drawing, sectional hydro testing of the sewer pipe line (including cost and conveyance of water to site for testing) etc., complete as directed by Engineer. Note : E/w to be measured and paid eparately. Length of pipe shall be measured in between the outer wall of two manholes / Inspection chambers, Pipe in the manhole/inspection chamber’s wall shall deemed to be included in the item of manhole/inspection chamber shall not be payable.300 mm internal diameter | 1,000 | Mtr. | 813 | ₹8,13,000 |
stage.html
html • 0.03 MB
Tap a document below to read it instantly. You can also download everything as a ZIP if you prefer.
details.html
html • 0.03 MB
Tendernotice_1.pdf
PDF • 0.17 MB
Terms.pdf
Tender Documents • 2.38 MB
BOQ_1040141.xls
BOQ • 0.39 MB
Download all tender documents and submit your bid
Disclaimer: TenderKart has made every reasonable effort to ensure that the information on this page is accurate and authentic, however it cannot be held liable for any third-party claims or losses or any damages. TenderKart makes no warranty, expressed or implied, as to the results obtained from the use of this information. If you notice any error or omission, please let us know at .