Loading…
Loading…
| # | Company | Amount | Rank | Status |
|---|---|---|---|---|
| 1 | L1₹18.6 LAccepted-AOC | ₹18.6 L | L1 | Accepted-AOC Apprved |
| 2 | L2₹18.6 LRejected-AOC | ₹18.6 L | L2 | Rejected-AOC Rejected |
| Sl No | Description | Qty | Unit | N.S.Parthipan L1 | P R Ramaraj L2 |
|---|---|---|---|---|---|
| 1.01 | Renovation of School Building @ P.U.Middle School in Lakshmipuram at Lakshmipuram Panchayat (East Side Entrance Building) :- Dismantling Mangalore Tiles including removal away from site for vestage materials including all labour charges etc. completed | 152.5 | Sqm | 29.78 ₹4,541.45 Lowest | 29.87 ₹4,555.18 |
| 1.02 | Cost and Supply of PUF Roof Panel Sheet of 30mm thick including all Charges | 152.5 | Sqm | 2,530 ₹3,85,825 Lowest | 2,537.59 ₹3,86,982.48 |
| 1.03 | Painting Two coat over old wall surface with approved quality of Oil bound Distember with colourmover one coat of white cement for priming coat for the base including preparation of old colour /white washing surface and all matierla cost labour cost etc. 10m2 | 124.29 | Sqm | 150.42 ₹18,695.7 Lowest | 150.87 ₹18,751.63 |
| 1.04 | Painting Two coat over old wall surface with approved quality plastic emulsion of cement paint with colour over one coat of white cement for priming coat for the base including preparation of old colour/White washing surface and all magterials cost labour cost etc. 10m2 | 157.4 | Sqm | 267.42 ₹42,091.91 Lowest | 268.22 ₹42,217.83 |
| 1.05 | Painting Two coat over Old iron work with synthetic enamal paint of approved quality and colour including preparation surface and all materials cost labour cost etc. 10m2 ( for structural steel work) | 18.72 | Sqm | 159.23 ₹2,980.79 Lowest | 159.71 ₹2,989.77 |
| 1.06 | Painting Two coat over old wall surface with approved quality of black board painting including preparation of old colour /white washing surface and all matierla cost labour cost etc. 10m2 | 12 | Sqm | 156.84 ₹1,882.08 Lowest | 157.31 ₹1,887.72 |
| 1.07 | Renovation of School Building @ P.U.Middle School in Lakshmipuram at Lakshmipuram Panchayat (North facing West Side Building) :- Dismantling Mangalore Tiles including removal away from site for vestage materials including all labour charges etc. completed | 133.95 | Sqm | 29.78 ₹3,989.03 Lowest | 29.87 ₹4,001.09 |
| 1.08 | Dismantling Gronolithick Floor Concrete including removal away from site for vestage materials including all labour charges etc. Completed | 103.28 | Sqm | 11.06 ₹1,142.28 Lowest | 11.09 ₹1,145.38 |
| 1.09 | Cost and Supply of PUF Roof Panel Sheet of 30mm thick including all Charges | 133.95 | Sqm | 2,530 ₹3,38,893.5 Lowest | 2,537.59 ₹3,39,910.18 |
| 1.10 | Paving the floor with kota stone slab of size 600 x 600 of 18 / 20mm (un-polished) in all floors laid in of cement mortor 1:3 (one cement three M.Sand), 20mm thick and pointed with colour cement neatly including polishing with polishing stone and oxalic acid etc., so as to perfectly smooth and glossy and including hire charges for polishing machine and power consumption charges etc. The kota stone slabs and other materials to be used shall be got approved by the Executive Engineer concerned before use on work, etc., complete as per standard speicification. | 107.11 | Sqm | 168 ₹17,994.48 Lowest | 168.5 ₹18,048.04 |
Tender Value
Refer Docs
EMD Value
₹19,340
Closing Date
20 Feb 2026, 3:00 pmClosed
BLOCK DEVELOPMENT OFFICER (BP) PERIYAKULAM
BLOCK DEVELOPMENT OFFICER (BP) PERIYAKULAM
Renovation of School Building at P.U.Middle School in Lakshmipuram at Lakshmipuram Panchayat (East Side Entrance Building) and Renovation of School Building at P.U.Middle School in Lakshmipuram at Lakshmipuram Panchayat (North facing West Side Buildi
2026_RDTN_658083_1
331/2026/A.4
Open Tender
Civil Works
Works
90 days
PERIYAKULAM
Please refer Tender documents.
6 documents required · 6 mandatory
₹0
₹19,340
28 Feb 2026
14 Feb 2026
20 Feb 2026
14 Feb 2026
20 Feb 2026
14 Feb 2026
| Sl No | Description | Qty | Unit | Est. Rate | Est. Amount |
|---|---|---|---|---|---|
| 1.01 | Renovation of School Building @ P.U.Middle School in Lakshmipuram at Lakshmipuram Panchayat (East Side Entrance Building) :- Dismantling Mangalore Tiles including removal away from site for vestage materials including all labour charges etc. completed | 152.5 | Sqm | - | - |
| 1.02 | Cost and Supply of PUF Roof Panel Sheet of 30mm thick including all Charges | 152.5 | Sqm | - | - |
| 1.03 | Painting Two coat over old wall surface with approved quality of Oil bound Distember with colourmover one coat of white cement for priming coat for the base including preparation of old colour /white washing surface and all matierla cost labour cost etc. 10m2 | 124.29 | Sqm | - | - |
| 1.04 | Painting Two coat over old wall surface with approved quality plastic emulsion of cement paint with colour over one coat of white cement for priming coat for the base including preparation of old colour/White washing surface and all magterials cost labour cost etc. 10m2 | 157.4 | Sqm | - | - |
| 1.05 | Painting Two coat over Old iron work with synthetic enamal paint of approved quality and colour including preparation surface and all materials cost labour cost etc. 10m2 ( for structural steel work) | 18.72 | Sqm | - | - |
| 1.06 | Painting Two coat over old wall surface with approved quality of black board painting including preparation of old colour /white washing surface and all matierla cost labour cost etc. 10m2 | 12 | Sqm | - | - |
| 1.07 | Renovation of School Building @ P.U.Middle School in Lakshmipuram at Lakshmipuram Panchayat (North facing West Side Building) :- Dismantling Mangalore Tiles including removal away from site for vestage materials including all labour charges etc. completed | 133.95 | Sqm | - | - |
| 1.08 | Dismantling Gronolithick Floor Concrete including removal away from site for vestage materials including all labour charges etc. Completed | 103.28 | Sqm | - | - |
| 1.09 | Cost and Supply of PUF Roof Panel Sheet of 30mm thick including all Charges | 133.95 | Sqm | - | - |
| 1.1 | Paving the floor with kota stone slab of size 600 x 600 of 18 / 20mm (un-polished) in all floors laid in of cement mortor 1:3 (one cement three M.Sand), 20mm thick and pointed with colour cement neatly including polishing with polishing stone and oxalic acid etc., so as to perfectly smooth and glossy and including hire charges for polishing machine and power consumption charges etc. The kota stone slabs and other materials to be used shall be got approved by the Executive Engineer concerned before use on work, etc., complete as per standard speicification. | 107.11 | Sqm | - | - |
stage.html
html • 0.04 MB
tech_eval.pdf
fin_bid_open.pdf
boq_comp_chart.xlsx
xlsx
fin_eval.pdf
aoc.pdf
Tap a document below to read it instantly. You can also download everything as a ZIP if you prefer.
details.html
html • 0.03 MB
Tendernotice_1.pdf
PDF • 0.64 MB
Tendernotice_2.pdf
PDF • 0.74 MB
BOQ_789412.xls
BOQ • 0.25 MB
Download all tender documents and submit your bid
Disclaimer: TenderKart has made every reasonable effort to ensure that the information on this page is accurate and authentic, however it cannot be held liable for any third-party claims or losses or any damages. TenderKart makes no warranty, expressed or implied, as to the results obtained from the use of this information. If you notice any error or omission, please let us know at [email protected].