Tender Value
₹1.9 Cr
EMD Value
₹2.5 L
Closing Date
17 Apr 2025, 3:00 pmClosed
Open tender for Conducting feasibility study Investigation, Detailed Survey with Total Station/DCPS, marking of approval alignment, Soil investigation, Preparation of GAD and submission of DPR for Construction of ROB/RUB under Asansol Division.
GSU-ASN-2024-05
GSU-ASN-2024-05
Open
Works - General
6 Months
Paschim Bardhaman, West Bengal
₹0
₹2.5 L
25 Mar 2025
25 Mar 2025
A-Non Schedule Items
B-USSOR-2021 Items
Item Breakup - A-Non Schedule Items
Detailed Investigation, Survey with Total stationof the level Each crossings along with the existing roadnetwork and propose different possiblealignments for construction of ROB/RUB incoordination with railway Departent officials. a)Submission of site plan with all existing siteparticulars and all Bearing details etc., as perrequirement for getting alignment approvals. b)Preparation of three proposed New Alignments inDifferent colors for getting of Alignment approvalin co-ordination with railway department officials.c) Submission of Longitudinal section of existingroad and for New proposed alignment also.
Once Approval is accorded for the proposedAlignment and for Each Longitudinal section ofROB/RUB by the Railways& state Government, thefollowing details are to be submitted. a) L.S forsite clearance such as jungle clearance, levellingetc., for marking of Approved Alignment on Site.b) Marking of Approved Alignment on site at 25M.Intervals either side. c) After marking Alignmenton site, Preparation of Land Plan Schedules,getting of approvals for the same from theRevenue department and then to be submitted toRailway Department for Approvals. ER-CAO-C-HQ-GATI SHAKTI/EASTERN RLY
After getting approvals for land plan of ROB/RUBschedules Each preparation of estimates for theeffecting structural details like ResidentialBuildings/Sheds/Shops/Industries/Govt.Structuresetc. to be submitted to Revenue department andapprovals to be accorded from concerndepartment for the same and then approvedstructural estimates to be submitted to RailwayDepartment.
After getting Soil Classification Report (SoilInvestigation is not a Each Part), the following detailsare to be submitted. a) Preparation of GAD forBridge Proper and approaches, approvals to beaccorded in coordination with State governmentand Railway department. After getting approval ofGAD from State governmetn the same to besubmitted. b) After approval of GAD, Finalisationof designs and structural drawings for theapproaches on both sides of the railway proper which is with the scope of Railway department. c)For the above submitted components approvals tobe obtained from the concern departments andthe same are to be submitted 5 copies to Railwaydepartment.
Conducting a dronebased aerial survey for the generation of Each orthophotosas per Railway Guidelines (Letter no.2015/Track- 1/24(1)/18/1/ dated09.10.2017 and as per thealignment plan given by Railwayson the Google earth to providealignment plan in kml file format.Deliverable: 1. Raw images (jpgformat) (2cm GSD) 2. File scaledand geopositioned orthophototiles in jpg & sid compressedformat of 2cm resolution andresampled at 5cm GSD. 3. Finalscaled and geopositioned orthotiles in jpg and Sid compressedformat of 2cm resolution andresampled at 5cm GSD.4. Finalscaled and geopositionedorthomosaic in JPG & Sid formatfor each 5km. 5. Map filecompatible to CAD/GIS in SHPformat duly linked with attributesof assets. 6. Quality controlreport for positional accuracyassessment coordinates to bepicked for atleast 5 well definedassets in 1km lengthb fromgoogle and same to be measuredon the orthophoto coordinates comparsion. The differencebetween these values should be greater than equal to 3m. 7. Thecentre line, piers, railway landboundary are to be shown ongoogle earth. (alignment file indwg format and coordinates willbe provided by Railways. Note: 1.This item is complimentary itemto LiDAR survey for generation ofortho photos. 2. This itemincludes prepration oforthophotos for yards also fallingin the corridor of 100m. Seperatepayment will be made for biggeryards vide relevant item of theBOQ for generation oforthophotos over and above thisitem.3. The details are to becollected for a corridor of 100mon the finalized alignment. i.e.50m on either side.StagePayment: 1. On completion ofdrone flying and submission ofdata in the relevant format -20%. 2. On submission andapproval of orthophotos andother deliverables - 60%. 3. Onsubmission of DPR to Railwayboard and approval by zonalRailways - 20%.
"Finding utility service locations such as and Electric, Telephone Each Cables, Water supply, Sewer pipes etc, within the proposed ROB/RUB locations both in Railway and state government areas as per approved concept plan duly collecting the information from the concerned Departments and location by conformation procedures such as trenching and digging suitable pitsor any other latest methods if required and developing fairly accurate location sketches with dimensions and preparation of alternate route plans for shifting the utilities for execution of ROB/RUB work and as directed by the Engineer-in-Charge including the cost of all materials,tools plantand labouretc., complete. (UNIT: EACHROB/RUB) "
Preparation of complete booklet of DPR with all the above Each details in five copies along with soft copies of all the work as directed by Engineer-in-charge including the cost of printing ,binding and all materials, tools plant, transportation and labour etc,complete .(UNIT:EACH ROB/RUB)" Total 13150888.40
Item Breakup - B-USSOR-2021 Items
1940.01 levels Drilling of NX size borehole (75mm dia.) in all types of hard rock and collection of rock core samples from boreholes and preserving in boxes.
130.80 soil from bore holes, including provision of air tight containers for packing and, labeling incl. transporting the samples to laboratory. Piston sampler shall be used for extracting undisturbed samples where necessary. Samples shall be collected as per IS:2720.
144.18 from bore holes, including provision of air tight containers for packing, labeling and transporting the samples to laboratory. Samples shall be collected as per IS:2720.
751.44 approximate1.5m intervals in bore holes, as directed by the Engineer in charge Conducting laboratory Tests on collected soil samples as per relevant IS code
Each 100.00 Conducting Laboratory tests on collected ROCK SAMPLES as per relevant IS code
Download all tender documents and submit your bid
Disclaimer: TenderKart has made every reasonable effort to ensure that the information on this page is accurate and authentic, however it cannot be held liable for any third-party claims or losses or any damages. TenderKart makes no warranty, expressed or implied, as to the results obtained from the use of this information. If you notice any error or omission, please let us know at .