Tender Value
₹45.1 Cr
EMD Value
₹90.3 L
Closing Date
27 Jul 2026, 3:00 pm
Design, Supply, Erection, Testing & Commissioning for upgradation of existing 1x25kV Electric Traction System into 2x25kV Electric Traction System Chunar- Chopan Section of Prayagraj Division of North Central Railway.
PRYJPU2627T01
PRYJPU2627T01
Open
24 Months
Prayagraj, Uttar Pradesh
₹0
₹90.3 L
4 Jul 2026
4 Jul 2026
13 Jul 2026
A2-Schedule-01 Section-2(a) (Concrete) 94610743.89 Below/P
A4-Schedule-01 Section-4(a)(other Non Ferrous) 46968732.71 Below/P
A5-Schedule-01 Section-5(Insulators) 16725338.98 Below/P
A6-Schedule-01 Section-6 Extra Under Power Block 13182013.00 Below/P
A7-Schedule-02 Section -7 Non-schedule items 19532270.00 Below/P
A8-Schedule-03 Section -8 Non-schedule items (AEC and BEC) 26362300.00 Below/P
Item Breakup - A1-Schedule-01 Section-1 (General)
1 (a) Preparation of designs and drawings Kilometre for overhead equipment and verification of purchaser's pegging plan. (Kilometer = Track kilometer)
5a (i) Supply without insulator and erection Each of mounting arrangements for span wire. (Materials)
5a (i) Supply without insulator and erection Each of mounting arrangements for span wire. (Erection)
8a (xii) Marking/painting of temperature & Each 'Y'- Measurement of OHE mast at BWA locations
8b (i) Supply without insulator and erection Each of material for termination of Single conductor of Over head equipment or terminating wire. (Materials)
8b (i) Supply without insulator and erection Each of material for termination of Single conductor of Over head equipment or terminating wire. (Erection) CEE-PROJECT-ELECTRICAL/NORTH CENTRAL RLY
8b (iii) Supply without Insulator and Each erection of material for termination of all aluminum 25KV Feeder / return conductor (Single SPIDER). (Materials)
8b (iii) Supply without Insulator and Each erection of material for termination of all aluminum 25KV Feeder / return conductor (Single SPIDER). (Erection)
8b (ix) Supply without insulator and Set erection of materials for termination of copper cross feeder with gantries. (Materials)
8b (ix) Supply without insulator and Set erection of materials for termination of copper cross feeder with gantries. (Erection)
11a (i) Supply without Insulator and Each erection of cut-in (9Tonne) Insulator (Materials)
11a (i) Supply without Insulator and Each erection of cut-in (9Tonne) Insulator (Erection)
11a (ii) Supply without Insulator and Each erection of a suspension (9 Tonne) Insulator (Materials)
11a (ii) Supply without Insulator and Each erection of a suspension (9 Tonne) Insulator (Erection)
11(b) Supply without Insulator and erection Each of 25 kV Post Insulator (Materials)
11(b) Supply without Insulator and erection Each of 25 kV Post Insulator (Erection)
31(a) Transfer of equipment from one mast Each or support to another. (Material)
31(a) Transfer of equipment from one mast Each or support to another. (Erection)
31(b) Provision of an additional bracket Each assembly/ assemblies on a mast or support.
31(d) Dismantling of overhead equipment.
31(e) Dismantling Conductor
31(f) Splicing & extension of an anchored Each overhead equipment.
31(gz) Dismantling of a Section Insulator Each Assembly (Materials)
31(gz) Dismantling of a Section Insulator Each Assembly (Erection)
31(i) Dismantling of an Isolator
31(j) Dismantling Insulator. Total 5157884.00
Item Breakup - A2-Schedule-01 Section-2(a) (Concrete)
2(a) Concrete for foundation and plinth (i) In cum hard soil (Materials)
2(a) Concrete for foundation and plinth (i) In cum hard soil (Erection)
2(a) Concrete for foundation and plinth (ii) cum In rocky soil (Materials)
2(a) Concrete for foundation and plinth (ii) cum In rocky soil (Erection) CEE-PROJECT-ELECTRICAL/NORTH CENTRAL RLY
2(b) Concrete for foundation and plinth - In cum other than hard soil and rock (Materials)
2(b) Concrete for foundation and plinth - In cum other than hard soil and rock (Erection)
2 ( c z ) Reinforced concrete for foundation cum and plinth in other than hard soil & rock (Grade M-20) (Materials)
2(cz) Reinforced concrete for foundation cum and plinth in other than hard soil & rock (Grade M-20) (Erection) Total 27303900.00
Item Breakup - A3-Schedule-01 Section-3(Ferrous)
3(a)(ii) Supply of traction masts, main MT masts of switching stations, Booster transformer station, fabricated from Rolled mild steel joist (RSJ) of size 203mm x 152 mm x 52.0 Kg/m and galvanised in lengths 9.5 m or 8.5 m long.
3(a)(ii) Erection of traction masts, main MT masts of switching stations, Booster transformer station, fabricated from Rolled mild steel joist (RSJ) of size 203mm x 152 mm x 52.0 Kg/m and galvanised in lengths 9.5 m or 8.5 m long.
3(b)(i) Supply of fabricated and galvanised MT structures (O,N & R type portals) with all necessary components other than masts.
3(b)(i) Erection of fabricated and galvanised MT structures (O,N & R type portals) with all necessary components other than masts.
3(b)(ii) Supply of Structure steel (traction MT masts) fabricated and galvanised of all Type : B-Series Mast.
3(b)(ii) Erection of Structure steel (traction MT masts) fabricated and galvanised of all Type : B-Series Mast.
3(b)(iii) Supply of special fabricated and MT galvanised steel structures other than Portals & traction- Masts not covered under items 3(b)(i) & 3(b)(ii).
3(b)(iii) Erection of special fabricated and MT galvanised steel structures other than Portals & traction- Masts not covered under items 3(b)(i) & 3(b)(ii)
3(c)Supply only of fabricated steel other MT than masts
3(e)(i)Supply of a Guy Rod Assembly
3(e)(i)Erection of a Guy Rod Assembly
4(a)(i) Supply without insulator of Single Each bracket assembly.
4(a)(i) Erection of Single bracket assembly. Each
4(a)(ii) Extra on 4 (a)(i) for supporting two Each OHEs. (Materials)
4(a)(ii) Extra on 4 (a)(i) for supporting two Each OHEs.(Erection)
8(a)(v) Supply of Regulating Equipment (3- Each Pulley type) with counter weight assembly for conventional/ composite OHE.
8(a)(v) Erection of Regulating Equipment (3- Each Pulley type) with counter weight assembly for conventional/ composite OHE. CEE-PROJECT-ELECTRICAL/NORTH CENTRAL RLY
9(a) Supply without Insulator of anticreep Each with galvanized steel wire
9(a) Erection of anticreep with galvanized Each steel wire.
16(a)(i) Supply of a structure bond.
16(a)(i) Erection of a structure bond.
16(b) Supply of a longitudinal bond
16(b) Erection of a longitudinal bond
16(c) Supply of a transverse and special Each bond.
16(c) Erection of a transverse and special Each bond.
17(a) Supply of a single earth electrode.
17(a) Erection of a single earth electrode.
3(g)Supply of steel reinforcement for RCC Total 78997410.00
Item Breakup - A4-Schedule-01 Section-4(a)(other Non Ferrous)
6(az) Supply of Over Head equipment only
6(az) Erection of Over Head equipment only Kilometre
7(d) Supply of all aluminium 25KV Feeder/ Kilometre Return conductor (Single Spider)
7(d) Manual Erection of all aluminium 25KV Kilometre Feeder/ Return conductor (Single Spider)
7(e) Supply of copper cross feeder wires Kilometre (37/2.25 mm HDBC) across the track at SP/SSP/FP/BT locations
7(e) Erection of copper cross feeder wires Kilometre (37/2.25 mm HDBC) across the track at SP/SSP/FP/BT locations
12(d) Erection of a Ceramic/beaded Glass Each Fibre type (PTFE) Short Neutral section assembly
15(a)(ii) Supply of small copper jumpers
15(a)(ii) Erection of small copper jumpers
15(b) Supply of an aluminum jumper.
15(b) Erection of an aluminum jumper.
15(e) Supply of materials of Large copper Each jumper 160 Sq. mm between cross feeder and OHE
15(e) Erection of Large copper jumper 160 Each Sq. mm between cross feeder and OHE
26(a)(ii) Supply of Solid copper bus-bars Metre 18mm
26(a)(ii) Erection of Solid copper bus-bars Metre 18mm
26(c)(i) Supply of solid copper bus-bar Each connectors: Bus terminal (6310)
26(c)(i) Erection of solid copper bus-bar Each connectors: Bus terminal (6310)
26(c)(ii) Supply of solid copper bus-bar Each connectors: Bus splice (6320)
6(c)(ii) Erection of solid copper bus-bar Each connectors: Bus splice (6320) Total 14935364.00
Item Breakup - A5-Schedule-01 Section-5(Insulators)
4(ax) Supply of Insulators for item 4(a)(i) & Each 4(a)(iii) :- 4(ax)(i) Stay Arm Porcelain (CD- 1050 mm)
4(ax) Supply of Insulators for item 4(a)(i) & Each 4(a)(iii) :- 4(ax)(iv) Bracket Porcelain (CD- 1050 mm)
8(bx) Supply of 9-Tonne insulators for item Each 8(b)(i), (ii), (iii), (vi), (vii), (viii) & (ix) :- 8(bx) (i) Porcelain (CD-1050 mm)
9(ax) Supply of 9-Tonne insulators for item Each 9(a), (b), (c), (d) & (e) :- 9(ax)(i) Porcelain (CD-1050 mm)
11(ax) Supply of 9-Tonne Insulator for item Each 11(a)(i) & 11(a)(ii) :- 11(ax)(i) Porcelain (CD- 1050 mm)
11(ax) Supply of 9-Tonne Insulator for item Each 11(a)(i) & 11(a)(ii) :- 11(bx) Supply of 25 kV Post Insulator for Item 11(b) Total 7026567.65
Item Breakup - A6-Schedule-01 Section-6 Extra Under Power Block
5a(i) Erection of mounting arrangements for Each span wire
8(b)(i) Erection of material for termination Each of Single conductor of Over head equipment or terminating wire.
8(b)(iii) Erection of material for termination Each of all aluminium 25KV Feeder / return conductor (Single SPIDER)
8(b)(ix) termination of copper cross feeder with gantries
11(a)(i) Erection of cut-in (9Tonne) Insulator Each
11(a)(ii) Erection of a suspension (9 Tonne) Each Insulator
11(b) Erection of 25 kV Post Insulator
31(b) Provision of an additional bracket Each assembly/ assemblies on a mast or support.
31(d) Dismantling of overhead equipment.
31(e) Dismantling Conductor
31(f) Splicing & extension of an anchored Each overhead equipment.
31(gz) Dismantling of a Section Insulator Each Assembly
31(i)Dismantling of an Isolator
31(j)Dismantling Insulator.
3(a)(ii) Erection of traction masts, main MT masts of switching stations, Booster transformer station, fabricated from Rolled mild steel joist (RSJ) of size 203mm x 152 mm x 52.0 Kg/m and galvanised in lengths 9.5 m or 8.5 m long.
3(b)(i) Erection of fabricated and galvanised MT structures (O,N & R type portals) with all necessary components other than masts.
3(b)(ii) Erection of Structure steel (traction MT masts) fabricated and galvanised of all Type : B-Series Mast. CEE-PROJECT-ELECTRICAL/NORTH CENTRAL RLY
3(b)(iii) Erection of special fabricated and MT galvanised steel structures other than Portals & traction- Masts not covered under items 3(b)(i) & 3(b)(ii)
4(a)(i) Erection of Single bracket assembly. Each
4(a)(ii) Extra on 4 (a)(i) for supporting two Each OHEs.
9(a) Erection of anticreep with galvanized Each steel wire.
6(az) Erection of Over Head equipment only Kilometre
7(d) Erection of all aluminium 25KV Feeder/ Kilometre Return conductor (Single Spider)
12(d) Erection of a Ceramic/beaded Glass Each Fibre type (PTFE) Short Neutral section assembly
Dismantling of a Ceramic/beaded Glass Each Fibre type (PTFE) Short Neutral section assembly
15(a)(ii) Erection of small copper jumpers
26(a)(ii) Erection of Solid copper bus-bars Metre 18mm.:
Erection of 160 sq.mm copper jumpers
Erection of dropper wire including cost of Each making droppers as per schedule (including Span A-Dropper).
Dismantling of dropper wire on existing Each OHE Span
8(a)(v) Erection of Regulating Equipment (3- Each Pulley type) with counter weight assembly for conventional/ composite OHE. Total 13182013.00
Item Breakup - A7-Schedule-02 Section -7 Non-schedule items
Handling/leading loading, unloading and MT-Km transportation of all type of Rly's supply materials & released materials.
Supply and Erection of Retro- reflective Square Number Plate as RDSO drawing & Foot specification.
Supply of 5mm/7mm solid round copper Kg dropper wire as per dropper schedule including contact and catenary dropper clip with nut and bolts as per spc.
Supply of 160 sq.mm copper jumpers
Erection of 160 sq.mm copper jumpers
Supply of 55KV DP Isolator complete with Set SPS.
Erection of 55KV DP Isolator complete with Set SPS.
Provision of Hiring of Non-AC multi utility Kilometre 30000.00 4wheeler diesel driven, Vehicle moto, Tata Sumo (Victa), Innova or similar with commercial registration including driver, fuel, crew and Maintenance site supervisor and Toll Tax charge etc. (kilometer=per kilometer)
Modification in TWR/sectioning diagram at Square various stations Foot
Erection of dropper wire including cost of Each making droppers asper schedule. Span CEE-PROJECT-ELECTRICAL/NORTH CENTRAL RLY
Dismantling of dropper wire on existing Each OHE Span
Dismantling of PTFE
Monthly charges for one crane operator for Per full time operation of one BFR crane Month including monthly charges for watch & ward for one crane
Erection /Laying of 25 kV Feeder cable Metre (Railway will supply the cable)
Supply of Feeder Cable Terminating kit
Erection of Feeder Cable Terminating kit
Supply of Straight Through jointing Kit
Erection of Straight Through jointing Kit
Supply of Route Markers
Supply of Warning Tape
HDPE Pipe for crossing 200 mm Dia PN6 Metre PE80
Formation of Trench less Road crossing with Metre HDPE pipe for Feeder Cable
Miscellaneous items required for successful Lumpsum commissioning not covered under any schedule
Provision erection/dismantling of Portal/TTC Total 19532270.00
Item Breakup - A8-Schedule-03 Section -8 Non-schedule items (AEC and BEC)
Supply of BEC 20mm dia galvanised steel Kilometre c o n d u c t o r ) with necessary accessories fitting and fasteners as per RDSO specification
Erection and laying of BEC (20mm dia Kilometre galvanised steel conductor) with necessary accessories fitting and fasteners as per RDSO specification
Supply of Arial Earth Conductor (12.24 mm Kilometre dia ACSR raccoon) with required fitting on mast/portal/TTC as per RDSO specification.
Erection of Arial Earth Conductor (12.24 Kilometre mm dia ACSR raccoon) with required fitting on mast/portal/TTC as per RDSO specification. Total 26362300.00
Tap a document below to read it instantly. You can also download everything as a ZIP if you prefer.
details.html
HTML
nit.pdf
NIT
TenderDocumentPart-II.pdf
ATTACHMENT
TenderDocumentPart-I.pdf
ATTACHMENT
BrandsofmaterialsintendersofDSR-CPWD.pdf
ATTACHMENT
RB instructions regarding eBG
ATTACHMENT
ContractorMBGuidelines.pdf
ATTACHMENT
PCECircularforFoundationworksnearTrack.pdf
ATTACHMENT
CorrectionSlip1-10.pdf
ATTACHMENT
System of verification of credentials
ATTACHMENT
GCCApril2022.pdf
ATTACHMENT
Annexure-VIB.pdf
ATTACHMENT
Annexure-VA.pdf
ATTACHMENT
GCCACS11_compressed.pdf
ATTACHMENT
2023_09_05RBCE_CE-I-CTSystemofVerificationofTendererCredentials.pdf
ATTACHMENT
2026_06_16Acceptanceofe-BankGuaranteee-BGinWorksContractsandPGMS_PMS_PSSAGC.pdf
ATTACHMENT
Download all tender documents and submit your bid