Laying and Jointing of RCC UGPL Works, Fixing of ARV, AAV, GV, Construction of Haudies and all other allied works.
2026_DOA_166057_4
DSWC/SAN/2025-2026/19/B
Open Tender
Pipe Laying Works
Percentage
365 days
Sangrur
Please refer tender documents.
3 documents required · 3 mandatory
₹2,000
₹75,000
30 Aug 2026
14 May 2026
21 May 2026
14 May 2026
21 May 2026
14 May 2026
FINANCIAL BID NO.: DSWC/SAN/2025-26/19/B
Rates for Civil Works (Approved by CCS Punjab Chandigarh)
Name of the Firm/Bidder
Phone Number of Bidder Email id of Bidder
Total Estimated Amount of Work Rs.
Quoted by Contractor (As % less of Estimated Amount) Quote (+/-%)
Note: Please quote only figure (upto 2 decimal points) in above blue colour box in minus or plus. Do not put %age sign after this figure. Please check Quoted Rate in Next cell.
Name of Work :- Earth work for excavation of Trenches for laying of Underground pipeline , lowering and jointing of 350 mm Dia RCC Pipes, fixing of AVP , Risers, Construction of Haudies at Village - Cheema (C/o 127250/L Extention), Tehsil:-Sunam, District- Sangrur.
Item of Work Quantity Unit Rate in (Rupees) Total in Rupees
Earth work in Excavation in trenches not exceeding 2 m depth including dressing Bottom & sides of trenches, stacking the excavated Soil Clear from the edge of excavation & subsequent filling around layed pipes in 15 cm layer with compaction including disposal of all surplus soil as directed within a lead of 30 meters. 4470.38 /Cum 93.78 Rupees Ninty Three and Seventy Eight Only
Lowering of R.C.C. Class NP-2 Pipes in to trenches for all depths and laying out the same to correct alignment ,gradients level etc. 3275 /Mtrs 76 Rupee Seventy Six Only
Jointing of class N.P.2 R.C.C pipes in trenches using collar joints jointed with 1:2 1/2 Cement sand mortar including facing trowelling and finishing the joints at the angle of 45 degree with faces of collars keeping joints w.e.f till cured, testing the drain lines or leakage and making good all leakage and defects to the satisfaction site incharge . /Joints 160.5 One Hundred Sixty Rupees And Fifty Paisa Only
Supplying, Lowering and Jointing of class N.P.-3 R.C.C pipes (350mm) in trenches using collar joints jointed with 1:2 1/2 Cement sand mortar including facing trowelling and finishing the joints at the angle of 45 degree with faces of collars keeping joints w.e.f till cured, testing the drain lines or leakage and making good all leakage and defects to the satisfaction site incharge. (Through Rate) 0 /Meter 2000 Two Thousand Rupees And Zero Paisa Only
Cutting reinforcement ,Concrete pipes, chipping & finishing the cut surface to a uniform shape the satisfaction of site incharge (350 mm) 35 /Cut hole 95 Ninety Five Rupees And Zero Paisa Only
Cutting reinforcement ,Concrete pipes, chipping & finishing the cut surface to a uniform shape the satisfaction of site incharge (150 mm) 11 /Cut hole 41 Forty One Rupees And Zero Paisa Only
Fixing of Riser Pipe & Fixing of Alfa Alfa valves with C.C 1:2:4 (350mm) 35 /Riser & Valve 568.16 Five Hundred Sixty Eight Rupees And Sixteen Paisa Only
Fixing of gate valve (350 mm) 6 each 1734.15 One Thousand Seven Hundred Thirty Four Rupees And Fifteen Paisa Only
Fixing of Air vent Pipes with C.C 1:2:4 (150mm) 11 /Air pipe 286.58 Two Hundred Eighty Six Rupees And Fifty Eight Paisa Only
Estimate of Charges for Haudi (1.20 X 1.20 X 3 m)
Earth work in Excavation 8 cum 86 Rupees Ninty Three and Seventy Eight Only
B.B.C 1:8:16 0.6 cum 3980.018 Three Thousand Nine Hundred Eighty Rupees And Two Paisa Only
Plain Cement Concrete 1:2:4 0.14 cum 5058.86 Five Thousand Fifty Eight Rupees And Eighty Six Paisa Only
First Class burnt brick work laid in Cement sand mortar in 1:4 in foundation and plinth 4.75 cum 4569.15 Four Thousand Five Hundred Sixty Nine Rupees And Fifteen Paisa Only
12.5 mm thick cement plaster work 1:4 15.32 cum 205.25 Two Hundred Five Rupees And Twenty Five Paisa Only
RCC Slab 1:2:4 0.21 cum 8175.32 Eight Thousand One Hundred Seventy Five Rupees And Thirty Two Paisa Only
Foot rest (Item No. 29.37) 6 No 100 Rupees One Hundred Only
Total Cost for ONE Haudi
Total Cost for 4 Haudis (B)
Cost of Other Items
Providing and Fixing of jaal 0 each 4000 Rupees Four Thousand Only
Sign Board (5' X 3') 1 each 4000 Rupees Four Thousand Only
Nimar for jointing the pipe 120.52 Per kg 60 Rupees Sixty Only
Provision for Carriage of Pipe for lead upto 2 Km (Subjected to actual site condition, given as per actual measurements provided by the site incharge or the Santioned amount in tender whichever is less) as per CSR 5.2 (13 b,c,d) of 2013 286.84 per tonnes 172.94 Rupees One Hundred Seventy Two and Ninty Four paise only
Name of Work :- Earth work for excavation of Trenches for laying of Underground pipeline , lowering and jointing of 600 mm Dia RCC Pipes, fixing of AVP , Risers, Construction of Haudies at Village -Jharon (C/o 40505/L Extention), Tehsil:-Sunam, District- Sangrur.
Item of Work Quantity Unit Rate in (Rupees) Total in Rupees
Earth work in Excavation in trenches not exceeding 2 m depth including dressing Bottom & sides of trenches, stacking the excavated Soil Clear from the edge of excavation & subsequent filling around layed pipes in 15 cm layer with compaction including disposal of all surplus soil as directed within a lead of 30 meters. 2592 /Cum 93.78 Rupees Ninty Three and Seventy Eight Only
Lowering of R.C.C. Class NP-2 Pipes in to trenches for all depths and laying out the same to correct alignment ,gradients level etc. 1350 /Mtrs 74 Rupee Seventy Six Only
Jointing of class N.P.2 R.C.C pipes in trenches using collar joints jointed with 1:2 1/2 Cement sand mortar including facing trowelling and finishing the joints at the angle of 45 degree with faces of collars keeping joints w.e.f till cured, testing the drain lines or leakage and making good all leakage and defects to the satisfaction site incharge . /Joints 332.268 Three Hundred Thirty Two Rupees And Twenty Seven Paisa Only
Supplying, Lowering and Jointing of class N.P.-3 R.C.C pipes (600mm) in trenches using collar joints jointed with 1:2 1/2 Cement sand mortar including facing trowelling and finishing the joints at the angle of 45 degree with faces of collars keeping joints w.e.f till cured, testing the drain lines or leakage and making good all leakage and defects to the satisfaction site incharge. (Through Rate) 0 /Meter 2000 Two Thousand Rupees And Zero Paisa Only
Cutting reinforcement ,Concrete pipes, chipping & finishing the cut surface to a uniform shape the satisfaction of site incharge (600 mm) 13 /Cut hole 150 One Hundred Fifty Rupees And Zero Paisa Only
Cutting reinforcement ,Concrete pipes, chipping & finishing the cut surface to a uniform shape the satisfaction of site incharge (150 mm) 5 /Cut hole 41 Forty One Rupees And Zero Paisa Only
Fixing of Riser Pipe & Fixing of Alfa Alfa valves with C.C 1:2:4 (600mm) 13 /Riser & Valve 950.62 Nine Hundred Fifty Rupees And Sixty Two Paisa Only
Fixing of gate valve (600 mm) 4 each 2750.8 Two Thousand Seven Hundred Fifty Rupees And Eighty Paisa Only
Fixing of Air vent Pipes with C.C 1:2:4 (150mm) 5 /Air pipe 286.275 Two Hundred Eighty Six Rupees And Twenty Eight Paisa Only
Estimate of Charges for Haudi (1.20 X 1.20 X 3 m)
Earth work in Excavation 8 cum 86 Rupees Ninty Three and Seventy Eight Only
B.B.C 1:8:16 0.6 cum 3980.018 Three Thousand Nine Hundred Eighty Rupees And Two Paisa Only
Plain Cement Concrete 1:2:4 0.14 cum 5058.86 Five Thousand Fifty Eight Rupees And Eighty Six Paisa Only
First Class burnt brick work laid in Cement sand mortar in 1:4 in foundation and plinth 4.75 cum 4550.15 Four Thousand Five Hundred Fifty Rupees And Fifteen Paisa Only
12.5 mm thick cement plaster work 1:4 15.32 cum 204.15 Two Hundred Four Rupees And Fifteen Paisa Only
RCC Slab 1:2:4 0.21 cum 8175.32 Eight Thousand One Hundred Seventy Five Rupees And Thirty Two Paisa Only
Foot rest (Item No. 29.37) 6 No 100 Rupees One Hundred Only
Total Cost for ONE Haudi
Total Cost for 3 Haudis (B)
Cost of Other Items C
Providing and Fixing of jaal 1 each 4000 Rupees Four Thousand Only
Sign Board (5' X 3') 1 each 4000 Rupees Four Thousand Only
Nimar for jointing the pipe 184.149 Per kg 60 Rupees Sixty Only
Provision for Carriage of Pipe for lead upto 2 Km (Subjected to actual site condition, given as per actual measurements provided by the site incharge or the Santioned amount in tender whichever is less) as per CSR 5.2 (13 b,c,d) of 2013 273.5 per tonnes 209.86 Two Hundred Nine Rupees And Eighty Six Paisa Only
A Name of Work :- Earth work for excavation of Trenches for laying of Underground pipeline , lowering and jointing of 600 mm Dia RCC Pipes, fixing of AVP , Risers, Construction of Haudies at Village - DUGGAN (C/o 55900/L), Tehsil and District- Sangrur.
Item of Work Quantity Unit Rate in (Rupees) Total in Rupees
Earth work in Excavation in trenches not exceeding 2 m depth including dressing Bottom & sides of trenches, stacking the excavated Soil Clear from the edge of excavation & subsequent filling around layed pipes in 15 cm layer with compaction including disposal of all surplus soil as directed within a lead of 30 meters. 6048 /Cum 93.78 Rupees Ninty Three and Seventy Eight Only
Lowering of R.C.C. Class NP-2 Pipes in to trenches for all depths and laying out the same to correct alignment ,gradients level etc. 3150 /Mtrs 74 Rupee Seventy Four Only
Jointing of class N.P.2 R.C.C pipes in trenches using collar joints jointed with 1:2 1/2 Cement sand mortar including facing trowelling and finishing the joints at the angle of 45 degree with faces of collars keeping joints w.e.f till cured, testing the drain lines or leakage and making good all leakage and defects to the satisfaction site incharge . 1260 /Joints 332.17 Rupees Three Hundred Thirty Two and Seventeen Paise Only
Cutting reinforcement ,Concrete pipes, chipping & finishing the cut surface to a uniform shape the satisfaction of site incharge (600 mm) 36 /Cut hole 150 Rupees One Hundred Fifty Only
Cutting reinforcement ,Concrete pipes, chipping & finishing the cut surface to a uniform shape the satisfaction of site incharge (150 mm) 14 /Cut hole 41 Rupees Forty One Only
Fixing of Riser Pipe & Fixing of Alfa Alfa valves with C.C 1:2:4 (600mm) 36 /Riser & Valve 949.98 Rupees Nine Hundred Fourt Nine and Ninety Eight Paise Only
Fixing of Air vent Pipes with C.C 1:2:4 (150mm) 14 /Air pipe 286.08 Rupees Two Hundred Eighty Six and Eight Paise Only
Estimate of Charges for Haudi (1.20 X 1.20 X 3 m)
Earth work in Excavation 8 cum 93.78 Rupees Ninty Three and Seventy Eight Only
B.B.C 1:8:16 0.6 cum 3857.74 Rupees Three Thousand Eight Hundred Fifty Seven and Seventy Four Paise Only
Plain Cement Concrete 1:2:4 0.14 cum 5070.77 Rupees Five Thousand Seventy and Seventy Seven Paise Only
First Class burnt brick work laid in Cement sand mortar in 1:4 in foundation and plinth 4.75 cum 4559.42 Rupees Four Thousand Five Hundred Fifty Nine and Fourty Two Paise Only
12.5 mm thick cement plaster work 1:4 15.32 cum 201.57 Rupees Two Hundred One and Fifty Seven Paise Only
RCC Slab 1:2:4 0.21 cum 8170.23 Rupees Eight Thousand One Hundred Seventy and Twenty Three Paise Only
Foot rest (Item No. 29.37) 6 No 100 Rupees One Hundred Only
Total Cost for Three Haudi
Total Cost for One Haudis (B)
Cost of Other Items
Providing and Fixing of jaal 0 each 4000 Rupees Four Thousand Only 0
Sign Board (5' X 3') 0 each 4000 Rupees Four Thousand Only 0
Fixing of gate valve (600 mm) 8 each 2750.16 Rupees Two Thousand Seven Hundred Fifty and Sixteen Paise Only
Nimar for jointing the pipe 429.66 Per kg 60 Rupees Sixty Only
Provision for Carriage of Pipe for lead upto 2 Km (Subjected to actual site condition, given as per actual measurements provided by the site incharge or the Santioned amount in tender whichever is less) as per CSR 5.2 (13 b,c,d) of 2013 639 per tonnes 209.86 Rupees Two Hundred Nine and Eighty Six paise only
A Name of Work :- Earth work for excavation of Trenches for laying of Underground pipeline , lowering and jointing of 400 mm Dia RCC Pipes, fixing of AVP , Risers, Construction of Haudies at Village - Kunran (C/o 56640/R), Tehsil and District- Sangrur.
Item of Work Quantity Unit Rate in (Rupees) Total in Rupees
Earth work in Excavation in trenches not exceeding 2 m depth including dressing Bottom & sides of trenches, stacking the excavated Soil Clear from the edge of excavation & subsequent filling around layed pipes in 15 cm layer with compaction including disposal of all surplus soil as directed within a lead of 30 meters. 1744.88 /Cum 93.78 Rupees Ninty Three and Seventy Eight Only
Lowering of R.C.C. Class NP-2 Pipes in to trenches for all depths and laying out the same to correct alignment ,gradients level etc. 1175 /Mtrs 71 Rupee Seventy One Only
Jointing of class N.P.2 R.C.C pipes in trenches using collar joints jointed with 1:2 1/2 Cement sand mortar including facing trowelling and finishing the joints at the angle of 45 degree with faces of collars keeping joints w.e.f till cured, testing the drain lines or leakage and making good all leakage and defects to the satisfaction site incharge . 470 /Joints 207.68 Rupees Two Hundred Seven and Sixty Eight Paise Only
Cutting reinforcement ,Concrete pipes, chipping & finishing the cut surface to a uniform shape the satisfaction of site incharge (400 mm) 12 /Cut hole 105 Rupees One Hundred Five Only
Cutting reinforcement ,Concrete pipes, chipping & finishing the cut surface to a uniform shape the satisfaction of site incharge (150 mm) 5 /Cut hole 41 Rupees Forty One Only
Fixing of Riser Pipe & Fixing of Alfa Alfa valves with C.C 1:2:4 (400mm) 12 /Riser & Valve 702.36 Rupees Seven Hundred Two and Thirty Six Paise Only
Fixing of Air vent Pipes with C.C 1:2:4 (150mm) 5 /Air pipe 285.75 Rupees Two Hundred Eighty Five and Seventy Five Paise Only
Estimate of Charges for Haudi (1.20 X 1.20 X 3 m)
Earth work in Excavation 8 cum 93.78 Rupees Ninty Three and Seventy Eight Only
B.B.C 1:8:16 0.6 cum 3855.45 Rupees Three Thousand Eight Hundred Fifty Five and Fourty Five Paise Only
Plain Cement Concrete 1:2:4 0.14 cum 5064.54 Rupees Five Thousand Sixty Four and Fifty Four Paise Only
First Class burnt brick work laid in Cement sand mortar in 1:4 in foundation and plinth 4.75 cum 5038.27 Rupees Five Thousand Thirty Eight and Twenty Seven Paise Only
12.5 mm thick cement plaster work 1:4 15.32 cum 201.5 Rupees Two Hundred One and Fifty Paise Only
RCC Slab 1:2:4 0.21 cum 8164.54 Rupees Eight Thousand One Hundred Sixty Four and Fifty Four Paise Only
Foot rest (Item No. 29.37) 6 No 100 Rupees One Hundred Only
Total Cost for ONE Haudi
Total Cost for One Haudis (B) 33106
Cost of Other Items
Providing and Fixing of jaal 0 each 4000 Rupees Four Thousand Only 0
Sign Board (5' X 3') 0 each 4000 Rupees Four Thousand Only 0
Fixing of gate valve (400 mm) 1 each 2047.36 Rupees Two Thousand Fourty Seven and Thirty Six Paise Only
Nimar for jointing the pipe 64.86 Per kg 60 Rupees Sixty Only
Provision for Carriage of Pipe for lead upto 2 Km (Subjected to actual site condition, given as per actual measurements provided by the site incharge or the Santioned amount in tender whichever is less) as per CSR 5.2 (13 b,c,d) of 2013 116.144 per tonnes 172.94 Rupees One Hundred Seventy Two and Ninty Four paise only
Grand Total (A+B+C+D)
stage.html
html • 0.04 MB
tech_bid_open.pdf
tech_eval.pdf
fin_bid_open.pdf
fin_eval.pdf
aoc.pdf
Tap a document below to read it instantly. You can also download everything as a ZIP if you prefer.
details.html
html • 0.03 MB
Tendernotice_1.pdf
PDF • 0.52 MB
NITUGPL252619B.pdf
Tender Documents • 0.50 MB
DNITUGPL252619B.pdf
Tender Documents • 1.16 MB
FBUGPL252619B.xls
Additional Documents • 0.16 MB
Download all tender documents and submit your bid
Disclaimer: TenderKart has made every reasonable effort to ensure that the information on this page is accurate and authentic, however it cannot be held liable for any third-party claims or losses or any damages. TenderKart makes no warranty, expressed or implied, as to the results obtained from the use of this information. If you notice any error or omission, please let us know at .