Tender ID
Eligibility, documents, scope and key termsEligibility, required documents, scope of work and key terms of this tender, in one click.
| # | Company | Status |
|---|---|---|
| 1 | Accepted-Technical | Accepted-Technical correct document |
| 2 | Accepted-Technical | Accepted-Technical correct document |
| 3 | Accepted-Technical 99 100 KAVERI ENCLAVE MODIPURAM ROAD MODINAGAR DISTT GHAZIABAD | MODINAGAR | GHAZIABAD | UTTAR PRADESH | Accepted-Technical correct document |
Tender Value
Refer Docs
EMD Value
₹7.1 L
Closing Date
11 Nov 2026, 5:00 pmClosed
Eligibility, documents, scope and key termsEligibility, required documents, scope of work and key terms of this tender, in one click.
EXECUTIVE OFFICER
NAGAR PANCHAYAT FARIDNAGAR
Nagar Panchayat Faridnagar mein man bazar canara bank se kripal purv sabhasad ki dukan tak RCC naali va CC sadak ka nirman karya
2026_DOLBU_1199426_1
290/NPF/E-Tender/2026-27
Open Tender
Civil Works
Percentage
60 days
NAGAR PANCHAYAT FARIDNAGAR
Please refer Tender documents.
2 documents required · 2 mandatory
₹8,435
EXECUTIVE OFFICER
₹7.1 L
21 Nov 2026
22 Oct 2026
12 Nov 2026
22 Oct 2026
11 Nov 2026
22 Oct 2026
22 Oct 2026 - 11 Nov 2026
120 days
This is a percentage-rate BOQ. The schedule below shows estimated quantities and rates. Bidders quote a single percentage above or below the total estimated cost.
| Sl No | Description | Qty | Unit | Est. Rate | Est. Amount |
|---|---|---|---|---|---|
| 1 | Demolishing cement concrete manually/by mechanical including disposal of materaial with in 50 meters lead as per direction Engineer -in-charge.Nominal concrete 1:4:8 or leaner. | 153.9 | cum | 1,180.78 | ₹1,81,722.04 |
| 2 | Cartagen of ballast kankar coal,grit or sand including loading & unloading but excluding stacking on pakka roads For Brick 1000 nos.reduce by 15% of the above rates and multiply by 2.30time .(4th km), | 153.9 | cum | 165.7 | ₹25,501.23 |
| 3 | Dismantling brick work or ston work in lime or cement mortar and including stacking of materials as distance of 60 meter (200feet). | 31.74 | cum | 600 | ₹19,044 |
| 4 | Construction of subgrade and earthen shoulders with approved material obtained from borrow plts with all lifts and leds, transporthing to site,spreading , grading to required slope and compacted to meet requirement of Table 300.2 with lead upto 1000 m as per Technical specification Clause 3031(With Ordinery Earth in Patri Work)12km. | 561.09 | cum | 348.5 | ₹1,95,539.87 |
| 5 | Providing concrete for plain/reinforced concrete Grade M-10 (1:3:6)in open foundation complete as per drawings and technical specifications clause 802,803,1202&1203 | 38.5 | cum | 6,935.7 | ₹2,67,024.45 |
| 6 | Supplying, fitting and placing with MS bar reinforcement (Fe-415) in substructrue complete as per drawing and technical specification Clauses 1002,1005,1010, & 1202, including bending for proper and necessary completion of the work. | 65.44 | qtl | 7,099 | ₹4,64,558.56 |
| 7 | Plain/reinforcedcementconcorete (Grade M20)in substructure complete as per drawing and technical specification Clauses 802, 804, 805, 806, 807, 1202 and 1204 | 92.61 | cum | 7,888.6 | ₹7,30,563.25 |
| 8 | Construction of granular sub-base by providing well graded material, spreading in uniform layers with motor grader on prepared surface, mixing by mix in place method with rotavator at OMC, and compacting with vibratory roller to achieve the desired density, complete as per clause 401 | 307.8 | cum | 3,661.4 | ₹11,26,978.92 |
| 9 | Construction of un-reinforced plain cement concrete pavement, thickness as per design, over a prepared sub base, with 43 rade cement or any other type as per Clause 1501.2.2 M 30(Grade), coarse and fine aggregates conforming to IS:383, maximum size of coarse aggregate not exceeding 25 mm, mixed in a concrete ixer of not less than 0.2 cum capacity and appropriate weigh batcher using approved mix design, laid in approved fixed side formwork (steel channel, laying and fixing of 125 micron thick polythene film, wedges, steel plates including levelling the ork as per drawing), spreading the concrete with shovels, rakes, ted using needle, screed and plate vibrators and finished in inuous operation luding provision of contraction and construction joints, applying debonding strips, primer, sealant, near roaches to bridge/culvert and construction joints, admixtures as roved, curing of concrete slabs for 14- days,using curing compound re specified) and water finishing to lines and grade as per drawing and finished with Power Trowel Cum Floter-Trimix Flooring
Machine | 384.75 | cum | 7,908.8 | ₹30,42,910.8 |
| 10 | Supply and fixing of granite stone for inauguration | 1 | job | 5,000 | ₹5,000 |
stage.html
html • 0.02 MB
tech_bid_open.pdf
tech_eval.pdf
Tap a document below to read it instantly. You can also download everything as a ZIP if you prefer.
details.html
html • 0.03 MB
Tendernotice_1.pdf
PDF • 5.72 MB
BOQ_2268129.xls
BOQ • 0.27 MB
Download all tender documents and submit your bid
Disclaimer: TenderKart has made every reasonable effort to ensure that the information on this page is accurate and authentic, however it cannot be held liable for any third-party claims or losses or any damages. TenderKart makes no warranty, expressed or implied, as to the results obtained from the use of this information. If you notice any error or omission, please let us know at .