| # | Company | Amount | Rank | Status |
|---|---|---|---|---|
| 1 | L1₹8.9 LAccepted-AOC | L1 | Accepted-AOC L1 is quoted less than tender value | |
| 2 | L2₹9.1 L+₹13,588.20 (1.52%)Rejected-AOC | L2 | Rejected-AOC L2 is quoted greater than tender value |
Tender Value
Refer Docs
EMD Value
₹18,000
Closing Date
20 Dec 2024, 3:00 pmClosed
THE BLOCK DEVELOPMENT OFFICER
THE BLOCK DEVELOPMENT OFFICE, PERNAMBUT
Vellore District Construction of Ceremony Shed at Pogalure in Pogalure Panchayat of Pernambut Block General Fund 2024-25 Package No 01
2024_RDTN_510116_1
A3/811/2023
Open Tender
Civil Works
Item Rate
180 days
THE BLOCK DEVELOPMENT OFFICE, PERNAMBUT
Please refer Tender documents.
5 documents required · 5 mandatory
₹0
₹18,000
10 Feb 2025
11 Dec 2024
20 Dec 2024
11 Dec 2024
20 Dec 2024
11 Dec 2024
Amount
Vellore District Construction of Ceremony Shed at Pogalure in Pogalure Panchayat of Pernambut Block General Fund 2024-25 Package No 01
Earthwork excavation and depositing on bank with initial lead and lift in all clauses of soil including cost of labour etc complete SS20B
Collection and supply of gritty gravel from appd quarry including cost and conveyance of all materials to site including all labour charges for filling etc.complete,
P.C.C 1:4:8 mix using 40mm ISS HBG metal including cost and conveyance of all etc.. Complete
Plain Cement Concrete 1:2:4 (one cement, two M.Sand and four hard broken stone jelly) using 20mm jelly for wearing coat including laying, compacting, finishing and curing, etc., complete as per standard specificatins and as directed by the departmental officers.
Brickwork with cm 1:5 using country bricks including cost and conveyance labour charges etc complete.
Supplying and erecting centering shuttering including necessary supports for plane
Below Ground Level
Above Ground Level
Supplying, fabrication and placing in position mils steel or ribbed for all reinforced cement concrete works as per the design given including cost of steel and binding wire in all floors etc., complete complying with standared specification.
R.C.C. 1:1.5:3 mix using 20mm ISS HBG metal including cost and conveyance etc., complete
Weathring Course with Brick Jelly Concrete with 20mm Brick Jelly with pure slacked lime are RCC roof slab in the pooposion 32:12:5 finish with CM1:4 20 mm thick
Finshed with one course of pressed tiles of size 23x23x2cm with cement mortar 1:3 mix and pointed with the same oiled mortar including cost and conveyance of all materials to site and all labour charges etc complete.
Plastering in 1:3, 10mm thick including cost and conveyance of all etc.. Complete
Plastering in 1:5, 12mm thick including cost and conveyance of all etc.. Complete
Paving the floor with best quality Vertified Tiles of size 600 x 600 x 8mm of approved colour, shade and quality laid in cement mortar 1:3 (one cement and three crushed stone M.Sand) 20mm thick in all floors and the top pointed with the white cement mixed same colour pigments etc., complete complying with standard specification. (The make and brand of the tiles should be got approved by Executive Engineer before use on works)
Supplying and painting the walls with two coats of oil bound distemper over one coat of water based cement primer including cost for distemper, primer, cleaning and scrapping the walls, rendering the walls smooth with necessary putty, brushes, scaffolding arrangements, labour charges, etc., as per standard specification. (The colour and shade of the distemper shall be got approved by the Executive Engineer before use of work).
Painting two coats of newly plastered wall surface with ready mixed plastic emulsion paint of first class quality and of approved colour over a priming coat including thorough scrapping, clean removal of dirt, and including necessary plaster of paris putty, wherever required etc., complete complying with standard specification.
Cost of 25mm PVC Pipe 10KSC
Cost of 25mm PVC Bend
Cost of 25mm PVC Tee
Cost of 20mm PVC Tape
Provision for 1000 litre HDPE Tank
Provision for Grill Gate
Letering and Painting for Citizen Information Board
GST Amount for providing service to Government contract works for the above construction works. { GST amount is the Total GST amount for total overall quoted amount above this row in column "BB" for all works in this package}
Rajivghandhi (BID ID -1213145)
stage.html
html • 0.04 MB
tech_eval.pdf
fin_eval.pdf
aoc.pdf
finance_606671.pdf
boq_comp_chart.xlsx
xlsx
Tap a document below to read it instantly. You can also download everything as a ZIP if you prefer.
details.html
html • 0.03 MB
Download all tender documents and submit your bid
Disclaimer: TenderKart has made every reasonable effort to ensure that the information on this page is accurate and authentic, however it cannot be held liable for any third-party claims or losses or any damages. TenderKart makes no warranty, expressed or implied, as to the results obtained from the use of this information. If you notice any error or omission, please let us know at .