| # | Company | Amount | Rank | Status |
|---|---|---|---|---|
| 1 | L1₹8.8 CrAccepted-AOC | ₹8.8 Cr | L1 | Accepted-AOC L1 |
| 2 | L2₹9.0 CrRejected-AOC | ₹9.0 Cr | L2 | Rejected-AOC L2 |
| 3 | L3₹9.1 CrRejected-AOC 142 | ₹9.1 Cr | L3 | Rejected-AOC L3 |
Tender Value
₹11.3 Cr
EMD Value
₹22.6 L
Closing Date
5 Feb 2020, 1:00 pmClosed
Superintending Engineer
Superintending Engineer, Rapti Nahar Nirman Mandal-2 Basti U.P.
Construction of P.R.B. at km. 45.738 of Campiearganj Branch.
2020_UPIDC_428229_2
11/SE/2019-20
Open Tender
Civil Works
120 days
Maharajganj
Please refer Tender documents.
2 documents required · 2 mandatory
₹2,354
ONLINE
₹22.6 L
S. E., Rapti Nahar Nirman Mandal-2 Basti U.P.
18 May 2020
29 Jan 2020
5 Feb 2020
29 Jan 2020
5 Feb 2020
29 Jan 2020
30 Jan 2020
Amount
E/W in excavation of foundation in all type of soil including initial lead up to 30m & lift up to 1.50m and its proper disposal and back filling as per direction by engineer in charge required for proper complection of work including cost of all T&P,Labour etc.
Laying C.C, A-40, M-10 in foundation of toe wall of protection work with cement (OPC 43 Grade),coarse sand of F.M not less then 2.00 and hard stone ballast (20-40mm size) including lead up 60m lift up to 3m mechanical mixing & machinal vibration but excluding of centering and shuttering required for proper completion of work includind cost of all material, T&P,Labour etc.
Laying C.C, A-40, M-15 in foundation below raft, protection work wing wall and approach slab with cement (OPC 43 Grade),coarse sand of F.M not less then 2.00 and hard stone ballast (20-40mm size) including lead up 60m lift up to 3m mechanical mixing & machinal vibration but excluding of centering and shuttering required for proper completion of work includind cost of all material, T&P,Labour etc.
Laying R.C.C, A-20, M-15 with cement (OPC-43 Grade)coarse sand of F.M not less than 2.5 and crused hard stone grit of size 4.75 to 20mm, including lead up to 60m lift up to 3m, mechnical mixing & mechnical vibration but excluding cost of centering and shuttering required for proper completion of work including cost of all meterial, T&P, Labour etc.
Laying R.C.C, A-20, M-20 with cement (OPC-43 Grade)coarse sand of F.M not less than 2.5 and crused hard stone grit of size 4.75 to 20mm, including lead up to 60m lift up to 3m, mechnical mixing & mechnical vibration but excluding cost of centering and shuttering required for proper completion of work including cost of all meterial, T&P, Labour etc.
Laying R.C.C, A-20, M-30 with cement (OPC-43 Grade)coarse sand of F.M not less than 2.5 and crused hard stone grit of size 4.75 to 20mm, including lead up to 60m lift up to 3m, mechnical mixing & mechnical vibration but excluding cost of centering and shuttering required for proper completion of work including cost of all meterial, T&P, Labour etc.
Laying R.C.C/C.C., A-10, M-30 with cement (OPC-43 Grade)coarse sand of F.M not less than 2.5 and crused hard stone grit of size 4.75 to 10mm, including lead up to 60m lift up to 3m, mechnical mixing & mechnical vibration but excluding cost of centering and shuttering required for proper completion of work including cost of all meterial, T&P, Labour etc.
Laying R.C.C., A-20, M-35 with cement (OPC-43 Grade)coarse sand of F.M not less than 2.5 and crused hard stone grit of size 4.75 to 20mm, including lead up to 60m lift up to 3m, mechnical mixing & mechnical vibration but excluding cost of centering and shuttering required for proper completion of work including cost of all meterial, T&P, Labour etc.
Centering & Shuttering for C.C & R.C.C work with all lead & lift reqired for proper completion of work including cost of all material and scafolading labour, T&P etc
Cutting bending binding and placing TMT steel bar for reinforcement with cost of binding wirw with required for proper compltion of work including cost of all material, labour, T&P etc
S/F Draiange spout pipe 100mm dia in R.C.C slab for proper complition of work including cost of all material, labour, T&P etc
Laying and fixing PVC joint 40mm thick as specied location in different postion required for proper comletion of work including cost of all material, labour, T&P etc.
Laying and fixing joint filler bord 20mm thick as specied location in different postion required for proper comletion of work including cost of all material, labour, T&P etc.
S/F 150 mm dia M.S. heavy hollow pipe & MS Flat for railing including cost of fabrication, welding and necessary tools required for proper completion of work
E/W in making Diversion in all type of soil including lead up to 30.00 lift up to 1.50m with manual compation and dressing required for proper compection of work including cost of all T&P, labour etc.
P/L base material of size 45-63 mm stone ballast including consolidation in 200mm thickness , prepration of sub base , spreading ballast, making medihs to retain OMC and cost of all carriage of material, labour T&P etc
P/L base material of size 22.4-53 mm stone ballast including consolidation in 225mm thickness , prepration of sub base , spreading ballast, making medihs to retain OMC and cost of all carriage of material, labour T&P etc
P/L Prime coat with bitumin emulsion over WBM surface on prepared surface of granular base including cleaning of road surface and spraying primer for proper completion of work and including wages of fire man and tar boiler man
P/L Tack coat with bitumin emulsion over Prime coated surface on prepared surface of granular base including cleaning of road surface and spraying primer for proper completion of work and including wages of fire man and tar boiler man.
providing laying & rolling 20 mm thick premix carpet composed of 13.2 mm to 6.7 mm aggregate including mixing in suitable plant and bitumen emulsion including cost of all carriage of material, labour T&P etc
P/L seal coat sealing voids in a bituminous surface ith crused stone chips of 6.7 mm size laid to the specified levels including cost of all carriage of material, labour T&P etc
IInd Class Brick work for Barriar in 1:6 C.M. with coarse sand including all lead & lift and cost of all material, labour, T&P etc
E/W in making canal section U/S and D/S of VRB/DRB i/c cost of all lead lift , drassing and mannual campaction etc.
Dewatering with all cost of power/POL machines,pump well,paint system & operator etc with assembling and dismantling of equipment required for complection of work, labour, T&P etc.
Carriage and laying stone boulder (weight 40 to 60 kg) and minimum diamension of 200 mm for canal inner slope protection and apron in Campierganj Branch required for proper completion of work including cost of all material, T&P,Labour etc.
S/F Elastometic bearing
Dismantling of 2nd class brick barriar including cost of all T&P,Labour etc.
E/W in Removing diversion in all type of soil including lead up to 30m and lift up to 1.5 m with cost of all T&P,Labour etc.
Pucca road cutting of diversion including all lead lift labour t&p etc
P/L filter media with granular crushed stone grit of size 45-63 of thickness not less than 600 mm including cost all material labour t&p etc
P/L 100 mm dia AC pipe for weep holes including cost of all material labour t&p etc
P/L 150 mm dia PVC pipe for carrying OFC cable etc ncluding cost of all material labour t&p etc
P/F 75X75X10 mm angle iron frame for Expansion Joints & supporting PVC pipe for carrying OFC cable etc
Vijai Construction (India) Pvt. Ltd.
M/S SHIV SHAKTI CONSTRUCTION
tech_bid_open.pdf
tech_eval.pdf
fin_bid_open.pdf
boq_comp_chart.xlsx
xlsx
fin_eval.pdf
aoc.pdf
Download all tender documents and submit your bid