| # | Company | Amount | Rank | Status |
|---|---|---|---|---|
| 1 | L1₹1.0 CrAdmitted-Finance | ₹1.0 Cr | L1 | Admitted-Finance |
| 2 | L2₹1.0 Cr+₹4,863.47 (0.05%)Admitted-Finance | ₹1.0 Cr+₹4,863.47 (0.05%) | L2 | Admitted-Finance |
| 3 | Not Admitted-Fee/PreQual/Technical | - | - | Not Admitted-Fee/PreQual/Technical EMD Not Furnished |
| Sl No | Description | Qty | Unit | KAMALAM L1 | Arumugam P V L2 |
|---|---|---|---|---|---|
| 1.00Upgradation of the poosapadi to Thenponparaappai road km0/0-3/230 | |||||
| 1.01 | Clearing the scrub jungles including all labour charges for all labour charges etc complete.km 0/0-3/230 | 5,102.16 | Sqm | - | - |
| 1.02Earthwork excavation and deposting on bank eith an intial lead and lift in hard gravelly soil as per SS 20B for foundationkm km 0/0-1/6 | |||||
| 1.03 | Km0//0-3/230 | 1,447.49 | Cum | - | - |
| 1.04laying US Gravel including cost and conveyance and stacking at site to departmental gauge for taking pre measurements by departmental officers and including labour charges for spreading the gravel as per standard specificiation etc complete | |||||
| 1.05 | Km 0/997-1/0 | 372.83 | Cum | - | - |
| 1.06 | Km 1/0-2/0 | 373.91 | Cum | - | - |
| 1.07 | Km 2/0-3/0 | 366.98 | Cum | - | - |
| 1.08 | Km 3/0-3/230 | 13.88 | Cum | - | - |
| 1.09Providing and laying 75mm compacted thick WBM Gr.IIusing 1 cum of 63 mm to 26.50 mm IRC HBG metal and 0.24 cum of Gravel for blindage for 10sqm. Of 75mm compacted thick (the blindage material shall have PI value less than 6%) including cost and conveyance of all materials from approved quarry to worksite and stacking to departmental gauge for pre-measurement as directed by the departmental officers including labour for spreading metal and gravel hand packing to camber and grade lines blinding with required quantity of gravel forming edge bunds watering with all leads for good water slurrying rolling and consolidation by power roller and finishing has per MOST 404 (III revision) including hire and fuel charges for power roller and water sprinkler and all other tools and plants employed therefor and all other incidental charges etc., complete for top layer. | |||||
Tender Value
₹1.1 Cr
EMD Value
₹1.0 L
Closing Date
25 Nov 2019, 3:00 pmClosed
Project Director
DRDA, VPM
VPM/TNRRIS/DP/054
2019_RDTN_143614_1
VPM/TNRRIS/DP/054
Open Tender
Civil Works
Works
180 days
Viluppuram District
Please refer Tender documents.
3 documents required · 3 mandatory
₹0
₹1.0 L
Yes
9 Jan 2020
5 Nov 2019
25 Nov 2019
5 Nov 2019
25 Nov 2019
12 Nov 2019
Amount
Upgradation of the poosapadi to Thenponparaappai road km0/0-3/230
Clearing the scrub jungles including all labour charges for all labour charges etc complete.km 0/0-3/230
Earthwork excavation and deposting on bank eith an intial lead and lift in hard gravelly soil as per SS 20B for foundationkm km 0/0-1/6
laying US Gravel including cost and conveyance and stacking at site to departmental gauge for taking pre measurements by departmental officers and including labour charges for spreading the gravel as per standard specificiation etc complete
Providing and laying 75mm compacted thick WBM Gr.IIusing 1 cum of 63 mm to 26.50 mm IRC HBG metal and 0.24 cum of Gravel for blindage for 10sqm. Of 75mm compacted thick (the blindage material shall have PI value less than 6%) including cost and conveyance of all materials from approved quarry to worksite and stacking to departmental gauge for pre-measurement as directed by the departmental officers including labour for spreading metal and gravel hand packing to camber and grade lines blinding with required quantity of gravel forming edge bunds watering with all leads for good water slurrying rolling and consolidation by power roller and finishing has per MOST 404 (III revision) including hire and fuel charges for power roller and water sprinkler and all other tools and plants employed therefor and all other incidental charges etc., complete for top layer.
Providing and laying 75mm compacted thick WBM Gr.IIIusing 1 cum of 63 mm to 26.50 mm IRC HBG metal and 0.24 cum of Gravel for blindage for 10sqm. Of 75mm compacted thick (the blindage material shall have PI value less than 6%) including cost and conveyance of all materials from approved quarry to worksite and stacking to departmental gauge for pre-measurement as directed by the departmental officers including labour for spreading metal and gravel hand packing to camber and grade lines blinding with required quantity of gravel forming edge bunds watering with all leads for good water slurrying rolling and consolidation by power roller and finishing has per MOST 404 (III revision) including hire and fuel charges for power roller and water sprinkler and all other tools and plants employed therefor and all other incidental charges etc., complete for top layer.
Applying tack coat over WBM surface using 4 kg of bituminous emulsion per 10 sqm including cost and conveyance of bituminous emulsion which will be supplied by deptly at section store and cost of which will be recovered at the rates as per special condittion appended including labour charges for preparing the surface for laying tack coat and for applying required quantity of bituminous emulsion by mechanical sprayer including hire and fuel charges for all tools and plants employed etc, complete as per clause 503 of MOST specification
Providing and laying Premix carpet with seal coat type 'A' for 20 mm consolidated thickness 0.18cum of 13.20 mm and 0.09 cum of 11.20 mm with 14.60 kg of 60/70 grade bitumen for pre mixing for 10 sqm for premix carpet and 0.09 cum of 6.70 mm IRC size HBG metal
Construction of 1.50m span RCC slab culvert @ch320m
Earthwork excavation and deposting on bank eith an intial lead and lift in hard gravelly soil as per SS 20B for foundation
sand filling with clean dry river sand including cost and conveyance of all materials to site and all labour charges for mixing ,laying and conslidaed etc complete
Cement concrete 1:4:8 using 40mm ISS HBG metal including all labour charges for mixing concrete watering and laying the concrete in layers not more than 15cm thick compacting etc complete complying with standard specificiation
Cost and supply and errecting centering including conveyance and all labour charges complete complying with standard specification
Below Sill
Above Sill
Cement concrete 1:3:6 using 40mm ISS HBG metal including all labour charges for mixing concrete watering and laying the concrete in layers not more than 15cm thick compacting etc complete complying with standard specificiation
Cement concrete 1:2:4 using 40mm ISS HBG metal including all labour charges for mixing concrete watering and laying the concrete in layers not more than 15cm thick compacting etc complete complying with standard specificiation for bed block
Supplying and fabrication of steel including cost and conveyance of steel to site and all labour charges for straightening ,cutting to length ,bending to shape and tying in position and forming grills for all R.C.C works
Reinforce cement concrete 1:11/2:3 mix using 20mm ISS metal including cost and conveyance of all materilas to site and all labour charges for mixing ,laying,and curing etc., complete for 10cum
Provision for bituman pads
Provision for Wheep holes
Construction of 1.50m span RCC slab culvert @ch1600m
Earthwork excavation and deposting on bank eith an intial lead and lift in hard gravelly soil as per SS 20B for foundation
sand filling with clean dry river sand including cost and conveyance of all materials to site and all labour charges for mixing ,laying and conslidaed etc complete
Cement concrete 1:4:8 using 40mm ISS HBG metal including all labour charges for mixing concrete watering and laying the concrete in layers not more than 15cm thick compacting etc complete complying with standard specificiation
Cost and supply and errecting centering including conveyance and all labour charges complete complying with standard specification
Below Sill
Above Sill
Cement concrete 1:3:6 using 40mm ISS HBG metal including all labour charges for mixing concrete watering and laying the concrete in layers not more than 15cm thick compacting etc complete complying with standard specificiation
Cement concrete 1:2:4 using 40mm ISS HBG metal including all labour charges for mixing concrete watering and laying the concrete in layers not more than 15cm thick compacting etc complete complying with standard specificiation for bed block
Supplying and fabrication of steel including cost and conveyance of steel to site and all labour charges for straightening ,cutting to length ,bending to shape and tying in position and forming grills for all R.C.C works
Reinforce cement concrete 1:11/2:3 mix using 20mm ISS metal including cost and conveyance of all materilas to site and all labour charges for mixing ,laying,and curing etc., complete for 10cum
Provision for bituman pads
Provision for Wheep holes
Provision for the Name board
Provision for thesign board
Provsion of Photo graph charges
Provision for HM stone
Provision for kM stone
GST Amount for providing Service to Government Contract Works for the above Construction Works. { GST Amount is the Total GST Amount for total overall quoted amount above this row in column "BB" for all works in this package}
Arumugam P V
stage.html
html • 0.03 MB
tech_eval.pdf
boq_comp_chart.xlsx
xlsx
Tap a document below to read it instantly. You can also download everything as a ZIP if you prefer.
details.html
html • 0.03 MB
Tendernotice_1.pdf
PDF • 0.28 MB
BOQ_172256.xls
BOQ • 0.31 MB
54.pdf
Tender Documents • 0.95 MB
Download all tender documents and submit your bid
Disclaimer: TenderKart has made every reasonable effort to ensure that the information on this page is accurate and authentic, however it cannot be held liable for any third-party claims or losses or any damages. TenderKart makes no warranty, expressed or implied, as to the results obtained from the use of this information. If you notice any error or omission, please let us know at .