Executive Engineer ID Ompora
Executive Engineer ID Ompora
Construction of lining wall cum RCC channel on Peer Nari dara M/o Sonmai canal near the land of Abdul Rashid Mir at Nuchgam
2026_IFC_314589_9
enit2of072026
Open Tender
Civil Works
15 days
Budgam
Please refer Tender documents.
6 documents required · 6 mandatory
₹200
Chief Engineer Kmr I and FC Deptt.
₹7,200
Yes
4 Jul 2026
4 Jul 2026
25 Jul 2026
4 Jul 2026
24 Jul 2026
4 Jul 2026
This is a percentage-rate BOQ. The schedule below shows estimated quantities and rates. Bidders quote a single percentage above or below the total estimated cost.
| Sl No | Description | Qty | Unit | Est. Rate | Est. Amount |
|---|---|---|---|---|---|
| 1 | Earth work in bulk excavation by manual means over areas (exceeding 30 cm in depth, 1.5 m in width as well as 10 m2 on plan) including disposal of excavated earth lead upto 50 meters and lift upto 1.5 m, as directed by Engineer-in-Charge. All kinds of soil : | 24.71 | cum | 592.9 | ₹14,650.56 |
| 2 | Providing and laying in position cement concrete of specified grade including curing but excluding the cost of centring and shuttering. All work upto plinth level with: 1:4:8 (1 cement : 4 coarse sand : 8 graded stone aggregate 40 mm nominal size) | 2.68 | cum | 5,202.9 | ₹13,943.77 |
| 3 | Providing and laying in position cement concrete of specified grade including curing but excluding the cost of centring and shuttering. All work upto plinth level with: 1:3:6 (1 cement : 3 coarse sand : 6 graded stone aggregate 20 mm nominal size) | 16.12 | cum | 5,733.6 | ₹92,425.63 |
| 4 | 12mm Cement plaster of mix: 1 : 4 ( 1 cement : 4 coarse sand) | 28.16 | Sqm | 283.8 | ₹7,991.81 |
| 5 | Centering and shuttering including strutting, propping etc. and removal of form work for:
a) Foundations, footings, bases for columns | 30.91 | sqm | 286.35 | ₹8,851.08 |
| 6 | b) Retaining walls, return walls, walls (any thickness) including attached pilasters buttresses, plinth and string course fillets, kerbs andsteps etc. | 26.88 | sqm | 628.95 | ₹16,906.18 |
| 7 | Providing and laying in position specified grade of reinforced cement concrete including curing but excluding the cost of centering, shuttering, finishing and reinforcement. All works upto plinth level 1:2:4 (1 cement : 2 coarse sand : 4 graded stone aggregate 20 mm nominal size) | 5.62 | cum | 7,104.35 | ₹39,926.45 |
| 8 | Steel reinforcement for R.C.C. work including straightening, cutting, bending, placing in position and binding all complete upto plinth level: Thermo-Mechanically Treated bars of grade Fe-500D or more. | 252.9 | kg | 123.2 | ₹31,157.28 |
| 9 | Filling available excavated earth (excluding rock) in trenches, plinth, sides of foundations etc. in layers not exceeding 20 cm in depth, consolidating each deposited layer by ramming and watering, lead upto 50 m and lift upto 1.5 m. | 1.97 | cum | 218.4 | ₹430.25 |
| 10 | Carriage of Materials from source upto road site by Mechnical transport including cost of loading unloading and stacking.
Cement and Steel avg. lead of 04 km | 6.13 | MT | 163.19 | ₹1,000.35 |
Tap a document below to read it instantly. You can also download everything as a ZIP if you prefer.
details.html
html • 0.03 MB
Tendernotice_1.pdf
PDF • 6.36 MB
BOQ_1018687.xls
BOQ • 0.28 MB
Download all tender documents and submit your bid