BLOCK DEVELOPMENT OFFICER VP, SETHUBAVACHATRAM
BLOCK DEVELOPMENT OFFICE, SETHUBAVACHATRAM
Construction of 100000 Litre OHT at Kallivayal habitation in Sarabendrarajanpattinam Panchayat in Thanjavur District under JAL JEEVAN MISSION - 2020 -2021 SAVINGS
2023_RDTN_303866_1
2315/2022/B1/JJM/3
Open Tender
Civil Works - Others
Works
180 days
BLOCK DEVELOPMENT OFFICE, SETHUBAVACHATRAM
Please refer Tender documents.
9 documents required · 9 mandatory
₹0
₹21,000
Yes
8 May 2023
3 May 2023
5 May 2023
3 May 2023
5 May 2023
3 May 2023
Amount
Construction of 100000 Litre OHT at Kallivayal habitation in Sarabendrarajanpattinam Panchayat.
Earth work excavation in all class of Soil except hard rock requiring blasting with intial lead and lift etc. Complete for foundation as per SS 20B. First depth upto 2 m
Earth work excavation in all class of Soil except hard rock requiring blasting with intial lead and lift etc. Complete for foundation as per SS 20B. second depth Above 2.55 m
Supplying and filling with Good Quality M.sand including Cost and conveyance, labour charges etc, Complete.
C.C.(1:4:8) Mix using 40mm ISS & HBG metal including cost & conveyance & Labour charge etc. complete
Cement concrete ( M 30 )1:1.5;3 mix using 20mm ISS metal including cost and conveyance of all materials to site and all labour charges for mixing,laying and curing etc complete for bed blocks for 10 cum
a) For raft below GL ( 1.50- 4.50 ) below GL
a) For raft below GL ( 1.50- 4.50 ) below GL
a) For raft below GL ( 0 to 3.505 m ) below GL
b) For coloumn beam flor slab and side wall from 3.505 -7.50 m GL
b) For coloumn beam flor slab and side wall from (7.35-10.43 m ) m GL
Supplying and and erection of steel centering using mild steel sheets including Cost and conveyance, labour charges etc, Complete.,
a. For coloum footing and GL Brace
b. For brace and middle brace B1
c. For Brace and midddle B2
For Side wall, Hanches and Roof slab sides ( 0 to 3.50 m above GL)
For cylinderical portion sides ( 3.50 m to 4.50 m )
For column head, Ring Beam Sides and Floor slab side ( 6.50m to 7.50m)
Square Column
Below G.L For Outer Column
For Outer Column in 0 to 3.50 m
Square Column
Below G.L For Central Column
For Central Column in 0 to 3.50 m and column inside Tank
Steel - supply , fabrication and placing of reinforcement steel of high yield strength ribbed bars of various diameters and grade conforming reinfore=ced concrete works etc
Exterior Emulsion two coats of approved colour with two coats of including rubbing and labour charges etc.
fabrication , supply delivery and fixing of outside MS ladder of 45 cm wide 50*50*6mm MS Angle for side stepsin 16 mm MS plain rods fixed at 30 mm c/c weltwd and joined etc.
providing and fixing of RCC ccess ladder in RCC 1:1.5:3 mix using 20 mm HBG metal including cost and conveyance etc.
Supplying & fixing of water tight manhole frame and cover of size 0.75mx0.75m over the roof slab of the OHT as directed by the Department Officers.
Supplying & fixing of 65mm dia GI Specials with weld mesh of approved patern as directed by the Department Officers.
Labour charges for fixing of G.I. Pipes & Specials for OHT pipe connections as directed by the Department Officers,
Refiiling with excavated earth (other than sand compying with standard specification for filling in trenches .
Supply of GI Pipes for OHT Connections 100 mm dia
Supply and Delivery 110 mm Ø GI threaded coupler
Supply and Delivery of 100mm Ø GI Tee
Supply and Delivery 100mm Ø GI Elbow
Supply and Delivery of 100mm Ø GI coupling
Supply and Delivery of 100mm Ø GI Flange Set
Supply and Delivery 100mm Ø GM Gate valve
Supply and Delivery of 100 mm x 80 mm GI Reducer
provision for soak pit arrangement etc, complete
provision for arrangement platform etc, complete .
GST Amount for providing Service to Government Contract Works for the above Construction Works. { GST Amount is the Total GST Amount for total overall quoted amount above this row in column "BB" for all works in this package}
S SATHIYARAJA
stage.html
html • 0.03 MB
tech_bid_open.pdf
tech_eval.pdf
fin_bid_open.pdf
boq_comp_chart.xlsx
xlsx
Tap a document below to read it instantly. You can also download everything as a ZIP if you prefer.
details.html
html • 0.04 MB
Download all tender documents and submit your bid
Disclaimer: TenderKart has made every reasonable effort to ensure that the information on this page is accurate and authentic, however it cannot be held liable for any third-party claims or losses or any damages. TenderKart makes no warranty, expressed or implied, as to the results obtained from the use of this information. If you notice any error or omission, please let us know at .