| # | Company | Amount | Rank | Status |
|---|---|---|---|---|
| 1 | L-1₹8.2 CrAccepted-AOC | ₹8.2 Cr Quoted ₹8.7 Cr | L-1 | Accepted-AOC L-1 Bidder |
| 2 | L-2₹8.7 Cr+₹3.4 L (0.39%)Rejected-Finance | ₹8.7 Cr+₹3.4 L (0.39%) | L-2 | Rejected-Finance L-2 Bidder |
| 3 | L-3₹9.0 Cr+₹25.3 L (2.90%)Rejected-Finance | ₹9.0 Cr+₹25.3 L (2.90%) | L-3 | Rejected-Finance L-3 Bidder |
Tender Value
₹8.0 Cr
EMD Value
₹8 L
Closing Date
2 Nov 2020, 12:00 pmClosed
SE, ETC, Varanasi
Bhikaripur, DLW, Varanasi
CONSTRUCTION OF 132 KV SAHUPURI(220)-SARNATH LILO LINE AT ALAIPUR UNDER ELECTRICITY TRANSMISSION DIVISION-I, VARANASI.
2020_UPTCL_517578_1
E Tender No. 37/2020-21/ETC/VNS
Open Tender
Electrical Works
Item Wise
150 days
132 KV SAHUPURI(220)-SARNATH LILO LINE AT ALAIPUR
Fee/EMD/PAN/GST Registration and experience for execution of work as per specification
2 documents required · 2 mandatory
₹11,800
SE, ETC, Varanasi
₹8 L
16 Nov 2021
3 Oct 2020
3 Nov 2020
3 Oct 2020
2 Nov 2020
26 Oct 2020
Amount
Part-I-Supply of Materials for conventional lattice Tower
Fabrication, galvanizing, inspection and supply of DC towers including stubs, extension and stub setting template , gantry structure as drawing and BOM.
Hot dip galvanized , Hexagon round hexagon head transmission tower Bolts/Nuts/Washers for above structures as per BOM.
Tower Accessories for lattice towers
Number plate
Danger Plate
Phase plate in set of red, blue and yellow for tension towers
Bird Gaurds
Pipe type earthing material for towers
Insulators
70 KN Porcelain Insulator
120 KN Porecelain Insulators
Hardware suitable for ACSR PANTHER Conductor
Single tension fittings
Double suspension fittings
Double tension fittings
Conductor Accessories suitable for ACSR PANTHER Conductor
Vibration dampers
Mid span joints
Repair sleeves
PA Rod
OPGW(Including Monopole portion of line)
24 Fiber(DWSM) OPGW Fiber optic cable
Supply and installation of Hardware set for 24 fiber(DWSM) OPGW
Joint Boxes(24 fibers)
FODP 48 Fiber
Fiber optics approach cable for 24 fiber
Supply and installation of hardware set for 24 fibers (DWSM,G652D Fiber-optics approach cable.
Par-II- WORK required for conventional tower
Survey including preparation of schedule of materials, marking of locations (Route length ), GPS Survey of line with co- ordinates of each tower(The length of line shall be authenticated by GPS Survey).
Check Survey
Cost of excavation of 132 KV tower foundation pits including all earth work , backfilling , leveling etc.
Setting of stubs including all foundation work but the cost of concreting and excavation (Rate per location) for following 132 KV DC towers.
Cost of concreting for all types of tower foundation including the cost of cement, dewatering, shoring and shuttering, forming curing but excluding cost of reinforcement bars.
1:2:4 concreting
1:3:6 concreting
Cost of Reinforcement bars in RCC foundation including cost of steel reinforcement bars with cutting, bending, placing, binding etc.
Erection of Superstructure of 132 KV DA, DB, DC Towers and Anchor tower and their extensions wherever required including all work above ground level excluding hoisting of insulators, hardware & accessories , but including fitting of danger number, phase plates, bird guard and fixing & punching.
Tack welding of all the bolts up to the height of one section of the tower or 5 meter from ground level whichever is higher with three tacks at 1200 seperation of minimum 10 mm thickness with 10 mm/ 12 mm electrode & application of Zinc rich Aluminium paint on the affected surface including cost of all material including tack welding of River Crossing toweer & Anchor towers.
Laying, stringing, tensioning, clamping, jointing etc of ACSR 'PANTHER' conductor including hoisting of insulators, fitting of all necessary hardware and accessories i.e. fitting Armour rods, vibration dampers etc on all six phases of 132 KV DC lines.
Laying, stringing, tensioning, clamping, joining etc of OPGW and OFAC, termination at S/S ,end to end connectivity and testing etc on 132 KV line.
Grounding work including earth work etc for pipe type grounding including cost of coke & salt.
Design of 132 KV DC Mono Poles & Embedded type monopoles with extension nuts, bolts, washers & ladders etc. and its foundations(design of poles & its foundations duly approved from any of the Govt. approved test lab i.e. CPRI/IIT Mumbai, Delhi, Roorkee. The final diameter of all the monopoles should be less than 2000mm so as to fit the monopoles on the divider of Road. a- PB (2-20 degree) (Approximate height of Bottom X- arm 21 Mtr.) b- PD (60-90 degree) (Approximate height of Bottom X- arm 21 Mtr) with extra cross arms for cable termintion. c- PD (20-50 degree) (Approximate height of Bottom X- arm 21 Mtr.) d- PC (15-30 degree) (Approximate height of Bottom X- arm 27 Mtr.) e- PD (0-20 degree) (Approximate height of Bottom X- arm 36 Mtr.)for Railway Over Bridge Crossing.
Fabrication, galvanizing,Inspection & supply of 132 KV DC mono poles with extension nuts, bolts, washers & ladders etc as per design at FOR at 132 KV Alaipur site.
PB (2-20 degree) (Approximate height of Bottom X- arm 21 Mtr.)
PD (60-90 degree) (Approximate height of Bottom X- arm 21 Mtr.) with extra cross arm for cable termination.
PD (20-50 degree) (Approximate height of Bottom X- arm 21 Mtr.)
PC (15-30 degree) (Approximate height of Bottom X- arm 27 Mtr.)
PD (0-20 degree) (Approximate height of Bottom X- arm 36 Mtr.)for Railway Over Bridge Crossing.
Tower Accessories
Number Plate
danger Plate
Phase Plate in Set of Red, Blue & Yellow.
Pipe type earthing material
Bird gaurds
Hardware suitable for ACSR PANTHER
Double Tension Fitting
Conductor Accessories Suitable for ACSR PANTHER
Vibration dampers
Composite Silicon- Rubber Insulator string of 120 KN Suitable for 132 KV Tension Fitting
Survey including preparation of schedule of material marking location (Route length) and super impose the GPS coordinates of diverted locations on elevated road plan to get the clearance from building etc before start the work.
Check survey & final peg marking (Route length)
Cost of excavation of 132 KV DC monopole foundation pits including all earth work,back filling and leveling etc.
Cost of pilling upto 10/15 mtr. depth including bulbs upto 600 mm dia. Cost also includes laying of reinforcement & bentonite bags but excludes the cost of reinforcement & concreting.
Cost of setting & alignment of bolts along with sacrificial & normal template (rate per location ) for above 132KV DC monopoles.
Installation of steel reinforcement bars in RCC foundation including cost of steel reinforcement bars with cutting, bending, placing, binding etc.
Cost of concreting for all type (M-20/M-25) of 132 KV DC monopoles, piles & foundation including cost of cement dewatering shorting and shuttering forming and cutting but excluding cost of reinforcement bars.
Erection of Following type of monopoles and there extensions wherever required including all work above ground level.
PB (2-20 degree) (Approximate height of Bottom X- arm 21 Mtr.)
PD (60-90 degree) (Approximate height of Bottom X- arm 21 Mtr.) with extra cross arm for cable termination.
PD (20-50 degree) (Approximate height of Bottom X- arm 21 Mtr.)
PC (15-30 degree) (Approximate height of Bottom X- arm 27 Mtr.)
PD (0-20 degree) (Approximate height of Bottom X- arm 36 Mtr.)for Railway Over Bridge Crossing.
Tack welding of all the bolts at Base Plate of Monopole.
Laying, stringing, tensioning, clamping, jointing etc complete with ACSR 'PANTHER' conductor DC including hoisting of insulators, fitting of all six phases with necessary hardware & accessories etc.
Laying, stringing, tensioning, clamping, joining etc complete with ground wire including hoisting of all necessary hardware & accessories for 01 No. OPGW
Ground work including earth material for pipe type earthing.
Construction of Machan/Providing Crane / Hydra to fit the conductor during stringing work smooth running of traffic on roads for all the locations.(At Three locations)
Providing barricades for avioding any accident during the period of excavation to backfilling of soil & during erection.
Dismantling of Dividers/ pedestral area at locations for the work & making good after completion of work.
Shifting of Soil from work site to under construction substation premises for filling land with the help of Tractor/loading vehicle.(Note: Carraige from one evacution site to under construction substation premises is one job.)
ASHUTOSH ENTERPRISES
KUMAR TRADING COMPANY
tech_bid_open.pdf
tech_eval.pdf
fin_bid_open.pdf
boq_comp_chart.xlsx
xlsx
fin_eval.pdf
aoc.pdf
Download all tender documents and submit your bid
Disclaimer: TenderKart has made every reasonable effort to ensure that the information on this page is accurate and authentic, however it cannot be held liable for any third-party claims or losses or any damages. TenderKart makes no warranty, expressed or implied, as to the results obtained from the use of this information. If you notice any error or omission, please let us know at .