| # | Company | Amount | Rank | Status |
|---|---|---|---|---|
| 1 | L1₹9.0 LAccepted-Finance | L1 | Accepted-Finance Lowest Rate | |
| 2 | L2₹10.0 L+₹99,141.24 (11.0%)Rejected-Finance | L2 | Rejected-Finance Higher Rate |
Tender Value
Refer Docs
EMD Value
₹10,000
Closing Date
20 Sept 2023, 2:30 pmClosed
SE SEDC Salem
office of the SE SEDC Salem
Wortks contract for Shevapet Sub division
2023_EB_367991_1
WC 031/2023-24 Dt.01.09.2023
Open Tender
Electrical and Maintenance Works
Works
365 days
Salem West
Please refer Tender documents.
2 documents required · 2 mandatory
₹0
₹10,000
19 Oct 2023
8 Sept 2023
21 Sept 2023
8 Sept 2023
20 Sept 2023
8 Sept 2023
Amount
Excavation of Pole/Stay pits
Excavation of pole pit up to 27”(8.0m) pole
Stay bit 4.5” to 5” depth
Excavation of pole pit up to 9.14 mtr pole
Hard Rock requires without blasting
Medium rock and debse medium rock reqires blasting
Erection of poles.
RCC poles/Metal pole up to 8.00m (27’)
RCC poles/Metal pole up to 9.14.m(30’) (300 kg)
Erection of stay set complete
Fixing of line materials
HT V Cross arms / Channel Cross arms / Guarding Cross arm 3 1/2, 4 1/2
LT 3 Phase cross arm
LT single Phase cross arm
HT / LT TI Fitting
Fixing of HT Pin Insulators (11/22 KV)
Fixing of HT 11KV stain disc
Fixing of HT 22KV stain disc
Fixing of LT Pin Insulators
Fixing of LT Shackle
Fixing of Knob
Labour charges for alteration of Back clamps/ Stay clamps to suit for the works
Earthing of poles
Paving and Stringing of conductor
ACSR 7/4.09mm Raccoon conductor
7/3.35mm ACSR 7/3.15mm AAAC (Per wire per span)
7/2.59mm ACSR & 7/2.50mm AAAC (Per wire per span)
Structure Erection
Erection of Transformer structure complete in all respects with wiring Earthing, fixing of open type fuse units, HT/LT/LAS and jumpering 3 Nos, Earth pits with tubes including painting of metal parts, structure poles, fixing of top channel seating channel, belting angle including concreting (Except erection of transformer)
Erection of single pole structure
Erection of DP Structure with AB switch, Top channel, Cross Bracing, Earthing, Painting, Providing stay and concreting.
Transporting of Poles
Transport of Poles/Materials/Conductors and other materials (excluding loading and unloading charges) below 8 kms (Plains)
Above 8 Kms. For additional Km.
Transporting of poles from road side to pole pit including loading and unloading of poles by using JCB or manual upto 100m.
Transporting of poles from road side to pole pit including loading and unloading of poles by using JCB or manual beyond 100m.
Loading & Unloading of Poles.
Loading of poles upto 27"
Loading of poles upto 30"
Loading of Metal poles (All sizes)
Unloading of poles upto 27"
Unloading of poles upto 30"
Unloading of Metal poles (All sizes)
Loading of materials
Un-Loading of materials
Services Connections.
Releasing of Single phase service wire and refixing.
Releasing of Three phase service wire and refixing.
Erection of street light including fixure fitting
Dismantling of Line Materials
Dismantling of transformer structure set
Dismantling of Single pole transformer structure set
Dismantling of DP Structure with AB switch, Top channel, Cross Bracing, Earthing, Painting, Providing stay and concreting.
Dismantling of pole (9.0m and above).
Dismantling of pole (7.5m and 8.0mtr).
Dismantling of pole & pole pit and loading unloading of grills(9.0mtr & above)
Dismantling of pole & pole pit and loading unloading of grills(7.5mtr & 8mtr)
Dismantling of HT pin Insulator
Dismantling of HT/LT TI Fitting
Dismantling of 11 KV Strain Disc
Dismantling of 22 KV Strain Disc
Dismantling of LT 3 Phase X arm
Dismantling of Tapping X arm, HT V Cross arms/ Channel Cross arms / Guarding cross arm
Dismantling of 1 PH X arm
Dismantling of Alu Knob
Dismantling of LT pin Insulator
Dismantling of LT Shackle Insulator
Dismantling of Stay set complete
Dismantling of ACSR 7/4.09mm
Dismantling of ACSR 7/3.35mm
Dismantling of ACSR 7/2.59mm & 7/2.11mm ACSR conductor
Loading or unloading of transformer above 100 and upto 200 KVA
Loading or unloading of transformer above 200 KVA.
Erection of New Transformer all capacities (with Jumpering)
Erection of HT metering set
Replacement of failed transformers all capacities.
Dismantling of transformer structure set
Re-stringing of ACSR 7/3.35mm
Re-stringing of ACSR 7/2.59mm
Dismantling of street light including fixture fitting
Tree cutting
Releasing of grills from RCC Poles
Concreting of Poles
Mass concreting including Materials (Cement + River sand/ M.Sand and Blue metals and watering)
Sleeve concreting including cost of Materials and labour 375mm x 375mm x 50mm.
Stay concreting including cost of Materials and labour 375mm x 375mm x 50mm.
Painting
Painting of metal poles including cross arms (Excluding cost of paint)
Numbering of pole with paint with base painting
Painting of RCC/PSC poles (Colour washing)
Painting of Transformer (Double coat)
Painting of HT metering set and box
Lathe works
Drilling of hole in channel only 3/4" & 1"
Cutting of channel
Cutting of RSJ poles
Miscellaneous Works.
Providing LT bus bar arrangement in DT structure loc.
Erection of New 10' Earth pipe replacing the corroded earth pipe and renewal of earthing including burying looping and binding.
G.S.T. @18% should be Entered by the Bidder
S P M ENGINEERING ENTERPRISES
stage.html
html • 0.04 MB
tech_bid_open.pdf
tech_eval.pdf
fin_bid_open.pdf
boq_comp_chart.xlsx
xlsx
fin_eval.pdf
Tap a document below to read it instantly. You can also download everything as a ZIP if you prefer.
details.html
html • 0.03 MB
Download all tender documents and submit your bid
Disclaimer: TenderKart has made every reasonable effort to ensure that the information on this page is accurate and authentic, however it cannot be held liable for any third-party claims or losses or any damages. TenderKart makes no warranty, expressed or implied, as to the results obtained from the use of this information. If you notice any error or omission, please let us know at .