| # | Company | Quoted % | Amount | Rank | Status |
|---|---|---|---|---|---|
| 1 | L1₹25.1 CrAdmitted-Finance | L1 | Admitted-Finance | ||
| 2 | L2₹32.2 Cr+₹7.0 Cr (28.0%)Admitted-Finance | L2 | Admitted-Finance |
Tender Value
₹25.1 Cr
EMD Value
₹50.3 L
Closing Date
7 Aug 2023, 6:00 pmClosed
Office of Chief Engineer Water Resources Division
Office of Chief Engineer Water Resources Division Kota
NECESSARY IRRIGATION WORK IN GAGRIN MEDIUM IRRIGATION PROJECTS TEHSIL PIRAWA DISTRICT JHALAWAR
2023_WRDAS_353087_1
Nit num 12 2023-24
Open Tender
Civil Construction Goods
Percentage
730 days
Office of Chief Engineer Water Resources Division
Please refer Tender documents.
2 documents required · 2 mandatory
₹10,000
AS PER NIT
₹50.3 L
Yes
Water Resources Division ZONE KOTA
17 Aug 2023
24 Jul 2023
8 Aug 2023
24 Jul 2023
7 Aug 2023
24 Jul 2023
28 Jul 2023
This is a percentage-rate BOQ. The schedule below shows estimated quantities and rates. Bidders quote a single percentage above or below the total estimated cost.
| Sl No | Description | Qty | Unit | Est. Rate | Est. Amount |
|---|---|---|---|---|---|
| 1Item Description | |||||
| 1.01 | PLANNING AND DESIGNING
Collection of revenue map and jamabandi of the Area of Interest, scanning revenue map and digitization of khasra boundary and jamabandi.
Rate shall be paid per Ha GCA | 7,500 | Per Ha | 52 | ₹3,90,000 |
| 1.02 | PLANNING AND DESIGNING
Geo-refrencing of digitized khasra map and marking chak and sub chak of required size for micro irrigation and providing chak and sub chak wise GCA, CCA details in excel format. Soft copy with two set of Hard copy shall be provided.
Rate shall be paid per Ha CCA | 4,911 | Per Ha. | 55 | ₹2,70,105 |
| 2.02 | PLANNING AND DESIGNING
Planning of field distribution pipe network up to chak and sub chak level, hydraulic design of pipe network planning and design of outlet arrangement with drawing and Irrigation scheduling up to chak level. Chak Plan showing pipe network is to be provided in soft copy and two set of Hard copy.
Rate shall be paid per Ha CCA | 4,911 | Per Ha | 102 | ₹5,00,922 |
| 3.02 | PLANNING AND DESIGNING
Preparation of l-section of pipe lines as per approved
pipe network and hydraulic design from competent
authority (showing safety valve and control valve
arrangement, filteration system and other accessory if
required). Design and drawing of thrust blocks,
pedestals and valve chamber, are to be provided. All
design, drawing should fulfill the design specification
as per the tender document and IS code / relevant
mannuals.
Rate shall be paid per Ha CCA | 4,911 | Per HA | 133 | ₹6,53,163 |
| 4.02 | PLANNING AND DESIGNING
Irrigation scheduling with timing up to subchak level is
to be preapred as per approved design and revenue
record. Rate shall be paid per Ha CCA | 4,911 | Per HA | 44 | ₹2,16,084 |
| 5.02 | PLANNING AND DESIGNING
Planning and design of Diggie for micro irrigation
system including design of intake/ sump well, pump
house and other ancillary developments to be done in
the campus and providing all hydro- electro
mechanical designs and drawings. | 25 | Each | 85,000 | ₹21,25,000 |
| 6.02 | FOR NEW WORK
Survey work in a grid at defined interval using Total
Station / DGPS instrument and preparation of Block
level plan showing all permanent features/ utilities
including trees, for planning of dam/ canal / water
course / pipe network alignment and superimposing it
on digitalized sajra map and developing contours at
interval desired by Engineer Incharge. Block level
plan is to be submitted in hard copy three set and
soft copy in Auto Cad format, using layer system,
showing all features.
Note:- Khasra map will be provided by Department
In Plain area - Block level to be taken @ 30 meter
grid | 7,500 | Per Ha | 350 | ₹26,25,000 |
| 7.02 | PART A : EARTH WORK IN EXCAVATION
Excavation including loading, unloading, disposal and dressing of excavated earth within initial lead of 50m and lift up to 1.5m including dressing of excavated area and dewatering wherever required complete in all respect
2.Hard / dense soil | 19,279.25 | Cum | 93 | ₹17,92,970.25 |
| 8.02 | PART A : EARTH WORK IN EXCAVATION
Excavation including loading, unloading, disposal and dressing of excavated earth within initial lead of 50m and lift up to 1.5m including dressing of excavated area and dewatering wherever required complete in all respect
3.Hard soil mixed with Kankar / boulders, Morrum | 9,639.75 | Cum | 115 | ₹11,08,571.25 |
stage.html
html • 0.03 MB
tech_eval.pdf
boq_comp_chart.xlsx
xlsx
Tap a document below to read it instantly. You can also download everything as a ZIP if you prefer.
details.html
html • 0.03 MB
Tendernotice_1.pdf
PDF • 4.10 MB
COMB1.pdf
Tender Documents • 6.07 MB
BOQ_627837.xls
BOQ • 0.30 MB
Download all tender documents and submit your bid
Disclaimer: TenderKart has made every reasonable effort to ensure that the information on this page is accurate and authentic, however it cannot be held liable for any third-party claims or losses or any damages. TenderKart makes no warranty, expressed or implied, as to the results obtained from the use of this information. If you notice any error or omission, please let us know at .