Loading…
Loading…
| # | Company | Amount | Rank | Status |
|---|---|---|---|---|
| 1 | L1₹1.7 LAccepted-AOC 00 00 RAIPUR POST JAITIPUR NAWABGANJ UNNAO UTTAR PRADESH 209831 | UNNAO | UTTAR PRADESH | 209831 | L1 | Accepted-AOC AWARD OF WORK TO L1 BIDDER AND REJECT L2 BIDDER DUE TO NOT L1 BIDDER | |
| 2 | Rejected-Technical BINA ROAD PARASI P O KAKRI DISTT SONBHADRA UP | SONBHADRA | UP | - | Rejected-Technical NOT L1 BIDDER |
Tender Value
₹3.3 L
EMD Value
₹4,200
Closing Date
2 Apr 2024, 11:00 amClosed
GENERAL MANAGER EXCAVATION, NCL KHADIA PROJECT
NCL KHADIA PROJECT, SHAKTINAGAR, SONBHADRA, U.P.
Repairing / fabrication of 04 nos. 30 KW, 05 nos. 22 KW, 03 nos. 7.5 KW blower motors of 20/90 Dragline of Khadia Project.
2024_NCL_305545_1
KHD/G.M. (Excv)/E-Tender/23-24/1245
Open Tender
Excavation Department Work
Item Rate
90 days
NCL KHADIA PROJECT, SHAKTINAGAR
Please refer Tender documents.
6 documents required · 6 mandatory
₹4,200
31 May 2024
18 Mar 2024
3 Apr 2024
18 Mar 2024
2 Apr 2024
19 Mar 2024
18 Mar 2024 - 22 Mar 2024
Amount
Labour Charges for repairing of 30 KW blower motors including contractor's profit.
Material involved for 04 nos. 30 KW blower motors.
Cost of super enameled copper wire 18 swg (ISI mark) including less cost of scrap wire.
Cost of Nomex paper.
Cost of Mica paper.
Cost of Glass coated cloth.
Cost of Cotton tape 1"
Cost of Glass coated sleeve.
Cost of Glass coated wire.
Cost of Copper lug.
Cost of Insulating varnish.
Cost of Thinner.
Cost of Wedge.
Labour Charges for repairing of 22 KW blower motors including contractor's profit.
Material involved for 05 nos. 22 KW blower motors.
Cost of super enameled copper wire 18 swg (ISI mark) including less cost of scrap wire.
Cost of Nomex paper.
Cost of Mica paper.
Cost of Glass coated cloth.
Cost of Cotton tape 1"
Cost of Glass coated sleeve.
Cost of Glass coated wire.
Cost of Copper lug.
Cost of Insulating varnish.
Cost of Thinner.
Cost of Wedge.
Labour Charges for repairing of 7.5 KW blower motors including contractor's profit.
Material involved for 03 nos. 7.5 KW blower motors.
Cost of super enameled copper wire 18 swg (ISI mark) including less cost of scrap wire.
Cost of Nomex paper.
Cost of Mica paper.
Cost of Glass coated cloth.
Cost of Cotton tape 1"
Cost of Glass coated sleeve.
Cost of Glass coated wire.
Cost of Copper lug.
Cost of Insulating varnish.
Cost of Thinner.
Cost of Wedge.
Total impact of GST for the purpose of CTC
CHANDRA MOTOR REWINDING WORKS
tech_eval.pdf
fin_eval.pdf
aoc.pdf
finance_316592.pdf
boq_comp_chart.xlsx
xlsx
Download all tender documents and submit your bid
Disclaimer: TenderKart has made every reasonable effort to ensure that the information on this page is accurate and authentic, however it cannot be held liable for any third-party claims or losses or any damages. TenderKart makes no warranty, expressed or implied, as to the results obtained from the use of this information. If you notice any error or omission, please let us know at .