Eligibility, documents, scope and key termsEligibility, required documents, scope of work and key terms of this tender, in one click.
| # | Company | Status |
|---|---|---|
| 1 | Admitted-Fee/PreQual/Technical/Finance | Admitted-Fee/PreQual/Technical/Finance |
| 2 | Admitted-Fee/PreQual/Technical/Finance | Admitted-Fee/PreQual/Technical/Finance |
Tender Value
₹22.9 L
EMD Value
₹23,000
Closing Date
27 Jan 2023, 3:00 pmClosed
Eligibility, documents, scope and key termsEligibility, required documents, scope of work and key terms of this tender, in one click.
Block development office
Block development office puzhal union
Vilangadupakkam Village 3 works Kulam CC road Fancing
2022_RDTN_270265_7
2358/2022/A7
Open Tender
Civil Works
Works
90 days
puzhal
Please refer Tender documents.
3 documents required · 3 mandatory
₹0
₹23,000
Yes
Block development office
27 Jan 2023
21 Jan 2023
27 Jan 2023
21 Jan 2023
27 Jan 2023
21 Jan 2023
21 Jan 2023
Amount
1.IMPROVEMENT OF MALLIMA NAGAR KULAM IN VILENKADUPAKKAM PANCHAYAT (MAIN POND, BABY POND, REVETMENT, STEPS, INLET) IN PUZHAL PANCHAYAT UNION
Pond Earthwork
Clearing the Light jungle with uprooting and disposing of the same as directed by the Engineer in charge of the works as per technical (A8)
Earth Work in all soils expected hard rock requiring blastering and conveying by earth by deploying earth moving machineries and tippers for formation of bund in layes of suitable thickness benching of slopes prior to placement od earth fill breaking clods watering to OMC (Optimum Moidture Content) and compaction of each layer to 95% proctor dendity through deployment of appropriate compaction eqipement (+8-10T Power Roller / Vibtratory Power Roller / Short width +-0.90m with drum) power roller or vibratory power roller / fuel operated or elect operated plade compactor ensuring compaction of dedigned bund section including side slopes" complete as per spectification.
Revertment
Earthwork excavation in all classes of soil and hard rock requiring blasting with initial lead and lift including all labour charges etc complete
Supplying and filling of conveyed earth with a lead of 5Km for filling
Filling with river sand including all charges
Cement Concrete 1:4:8 ( One Cement Five sand and Ten Hard Broken stone) using 40 mm gauge Hard Broken Granite stone jelly for foundation including cost and conveyance of materials to site and labour charges for laying, watering and compacting etc. complete
Supplying and erecting centering shuttering including necessary supports for planeBroken Granite surface in foundation and basement and in all floors for R C C column footing laying, watering column plinth beam, beams, roof slabs, staircase steps, bed blocks, critical pier etc
Cement Concrete 1:3:6 ( One Cement Three sand and Six Hard Broken stone) using 40 mm gauge Hard Broken Granite stone jelly for foundation including cost and conveyance of materials to site and labour charges for laying, watering and compacting etc. complete
Plain Cement Concrete 1:2:4 ( One Cement Two sand and Four Hard Broken stone) using 20 mm gauge Hard Broken Granite stone jelly for foundation including cost and conveyance of materials to site and labour charges for laying, watering and compacting etc. complete
Gravel backing for revetments including all labour charges etc complete
Providing and Laying of Interlocking Concrete (Surface Textured) Block Pavements having thickness 83mm
Fencing for pond
Earthwork excavation in all classes of soil and hard rock requiring blasting with initial lead and lift including all labour charges etc complete
Supplying and filling in foundation and basement with good sand in layers not more 15 cm thick including ramming, watering and compacting etc.complete complying to standard specification
Cement Concrete 1:4:8 ( One Cement Five sand and Ten Hard Broken stone) using 40 mm gauge Hard Broken Granite stone jelly for foundation including cost and conveyance of materials to site and labour charges for laying, watering and compacting etc. complete
Plain Cement Concrete 1:2:4 ( One Cement Two sand and Four Hard Broken stone) using 20 mm gauge Hard Broken Granite stone jelly for foundation including cost and conveyance of materials to site and labour charges for laying, watering and compacting etc. complete
Cost of cement post
Cost of Diamond chain circle 3"X3"
Labour cost of barbed wire tieing
Provision for Stainless Steel Sitting bench of minimum capacity of 3 persons including all labour charges etc
30W LED FITTING &LAMP out door type PAGE NO: 114
2.Providing Cement Concrete Road at Venugopal Street 87 m at Pallikuppam Habitation in Vilangadupakkam Village Panchayat
Earth work excavation and depositing on bank with initial lead and lift in hard stiff clay and hard gravelly soil as per SS20B for narrow foundations. Etc,.complete.
Cement Concrete 1:4:8 ( One Cement Five sand and Ten Hard Broken stone) using 40 mm gauge Hard Broken Granite stone jelly for foundation including cost and conveyance of materials to site and labour charges for laying, watering and compacting etc. complete.
Cement Concrete 1:2:4 (One cement, Two sand, Four Hard Broken stone) using 20 mm guage machine broken hard broken granite stone jelly including cost conveyance and all labour charges etc. complete.
Supply and Errecting for Centering and shuttering for core wall sides including cost and conveyance and materials of labour charges etc,.complete.
Supply and fixing of Bitumen Pad inclouding cost and conveyance and other labour charges
3.Providing Fencing and Green nnet for Horticulture and Moringa Nursery at Dargas in Vilangadupakkam Panchayat
Earthwork excavation in all classes of soil and hard rock requiring blasting with initial lead and lift including all labour charges etc complete
Supplying and filling in foundation and basement with good sand in layers not more 15 cm thick including ramming, watering and compacting etc.complete complying to standard specification
Cement Concrete 1:4:8 ( One Cement Five sand and Ten Hard Broken stone) using 40 mm gauge Hard Broken Granite stone jelly for foundation including cost and conveyance of materials to site and labour charges for laying, watering and compacting etc. complete
Plain Cement Concrete 1:2:4 ( One Cement Two sand and Four Hard Broken stone) using 20 mm gauge Hard Broken Granite stone jelly for foundation including cost and conveyance of materials to site and labour charges for laying, watering and compacting etc. complete
Supply and Delivery and fixing of 50mm x 50mm of 3mm thickness of squre tube including dia Horizontal Hollow pipe including cost and conveyance of all charges
Supply and Delivery and fixing of 30mm x 30mm of 3mm thickness of squre tube including dia Horizontal Hollow pipe including cost and conveyance of all charges
Supply and Delivery and fixing of Green shade Net for Nursery including cost and conveyance of all charges
GST Amount for providing Service to Government Contract Works for the above Construction & Maintenance Works. { GST Amount is the Total GST Amount for overall quoted amount (Both Construction and Maintenance) above this row in column "BB" for all works in this package} (Refer Clause 13.2 & 13.3 of Section 2 of Instruction to Bidders (ITB) of SBD)
M.Mayan
stage.html
html • 0.02 MB
boq_comp_chart.xlsx
xlsx
Tap a document below to read it instantly. You can also download everything as a ZIP if you prefer.
details.html
html • 0.03 MB
Download all tender documents and submit your bid
Disclaimer: TenderKart has made every reasonable effort to ensure that the information on this page is accurate and authentic, however it cannot be held liable for any third-party claims or losses or any damages. TenderKart makes no warranty, expressed or implied, as to the results obtained from the use of this information. If you notice any error or omission, please let us know at .