| # | Company | Amount | Rank | Status |
|---|---|---|---|---|
| 1 | L1₹16.9 LAccepted-AOC | L1 | Accepted-AOC Tender has Quoted Less than the Estimate rate | |
| 2 | Rejected-Technical | - | Rejected-Technical Tender Reject |
| Sl No | Description | Qty | Unit | SHANMUGHA CONSTRUCTION L1 | RAJENDRAN A L2 |
|---|---|---|---|---|---|
| 1.00Construction of Anganwadi building in MGR Nagar at Arunkundram Panchayat at Thiruporur Panchayat Union in Chengalpattu District for the Year 2025-26 having Package No 3/2025-26 scheme of MLA CDS | |||||
| 2.00 | Earth work excavation for foundation in all soils and sub soils to full depth etc | 41.91 | Cum | 246 ₹10,309.86 Lowest | 300 ₹12,573 |
| 3.00 | Filling with Msand including cost and Conveyance of all charges etc. | 5.91 | Cum | 1,493 ₹8,823.63 Lowest | 1,500 ₹8,865 |
| 4.00 | CC 1:4:8 mix using 40mm ISS HBG Metal including all cost and conveyance etc.complete. | 11.69 | Cum | 5,057 ₹59,116.33 Lowest | 5,057 ₹59,116.33 Lowest |
| 5.00 | RCC 1:1.5:3 mix using (One cement two sand and four hard bronken granite stone) using 20mm gauge hard broken granite stone jelly for foundation including cost and conveyance of all materials to site and all labour charges at site including curing etc comp | 8.28 | Cum | 8,860 ₹73,360.8 Lowest | 8,860 ₹73,360.8 Lowest |
| 6.00 | RCC 1:1.5:3 mix using (One cement two sand and four hard bronken granite stone) using 20mm gauge hard broken granite stone jelly for foundation including cost and conveyance of all materials to site and all labour charges at site including curing etc comp above base | 11.69 | Cum | 8,991 ₹1,05,104.79 Lowest | 8,991 ₹1,05,104.79 Lowest |
| 7.00 | Supplying and centering of sides and sofits includign supports and strutting upto base | 41.13 | Sqm | 516 ₹21,223.08 Lowest | 516 ₹21,223.08 Lowest |
| 8.00 | Supplying and centering of sides and sofits includign supports and strutting Above base | 73.15 | Sqm | 1,033 ₹75,563.95 Lowest | 1,033 ₹75,563.95 Lowest |
| 9.00 | Supplying and centering of sides and sofits includign supports and strutting Above base | 55.9 | Sqm | 1,033 ₹57,744.7 Lowest | 1,033 ₹57,744.7 Lowest |
| 10.00 | Supplying and fabrication of steel including cost and conveyance of all labour charges ' | 3 | MT | 89,957 ₹2,69,871 Lowest | 89,957 ₹2,69,871 Lowest |
Tender Value
₹17.3 L
EMD Value
₹18,000
Closing Date
13 Aug 2025, 3:00 pmClosed
Block Developement Officer BP
Block Developement Office Thiruporur
Construction of Anganwadi Building in MGR Nagar in Arunkundram Panchayat Thiruporur Panchayat Union in Chengalpattu District for the Year 2025- 2026 having Package No . 3/2025 - 2026
2025_RDTN_585611_1
R.C. No 1306/2025/A2 Dt 21.07.2025
Open Tender
Civil Works - Buildings
Item Rate
Arunkundram
Please refer Tender documents.
2 documents required · 2 mandatory
₹0
₹18,000
Yes
Block Developement Office Thiruporur
26 Aug 2025
25 Jul 2025
13 Aug 2025
25 Jul 2025
13 Aug 2025
25 Jul 2025
29 Jul 2025
Amount
Construction of Anganwadi building in MGR Nagar at Arunkundram Panchayat at Thiruporur Panchayat Union in Chengalpattu District for the Year 2025-26 having Package No 3/2025-26 scheme of MLA CDS
Earth work excavation for foundation in all soils and sub soils to full depth etc
Filling with Msand including cost and Conveyance of all charges etc.
CC 1:4:8 mix using 40mm ISS HBG Metal including all cost and conveyance etc.complete.
RCC 1:1.5:3 mix using (One cement two sand and four hard bronken granite stone) using 20mm gauge hard broken granite stone jelly for foundation including cost and conveyance of all materials to site and all labour charges at site including curing etc comp
RCC 1:1.5:3 mix using (One cement two sand and four hard bronken granite stone) using 20mm gauge hard broken granite stone jelly for foundation including cost and conveyance of all materials to site and all labour charges at site including curing etc comp above base
Supplying and centering of sides and sofits includign supports and strutting upto base
Supplying and centering of sides and sofits includign supports and strutting Above base
Supplying and centering of sides and sofits includign supports and strutting Above base
Supplying and fabrication of steel including cost and conveyance of all labour charges '
Brick work in cm 1:5 for super structure usign stock brick including all cost and labour charges etc.complete . Complying with standard specification etc.
Brick work in cm 1:5 for super structure usign stock brick including all cost and labour charges etc.complete . Complying with standard specification etc. above base
Floor finishing with granolithic flooring in cc 1:2:4 mix using 10 -12mm chips includign all charges
Paving the floor iwht scratch proof ceramic tiles including cost and conveyance of all labour charges
Paving the floor with pre polished concrete anti skid tiles of 20mm thick approved quality and color laid in
Dadooing of walls with glazed tiles of of any color and laid in cm 1:2 10mm thick and pointing with white cement
Refilling the basement with excavated earth other than sand complying the standard specification
Brick helly lime concrete using 20mm brick jelly with slacked lime in the ratio of 32:12.5 including all charges
Finishing the top of roof with one course of pressed tiles
Ceiling plastering with cm 1:3 mix using 10mm thick including all charges
Plastering with cm 1:5 mix using 10mm thick including all charges
Distermbering two coats with approved distember including all labour charges
Exterior emulsion of wall two coat plastic emulsion Paint including cost and conveyance of all materials to site and all labour charges etc complete
Towards cost and supply of new steel Door of size (0.9x2.10m)
Towards cost and supply of new steel Door of size (0.75 x1.80m)
Towards cost and supply of new steel Door of size (1.10x1.20m)
Towards cost and supply of new steel Window of size (1.2x1.30m)
Towards cost and supply of new steel Ventilator of size (0.90x0.45m)
Towards cost and supply of RCC jolly (0.9x0.45)
Painting two coats over new iron works using ready mixed paint enamel paint
Labour charges for fixing the door including all labour charges
Labour charges for fixing the steel window including all charges
Supply and fixing of cuddapah slab 20-30mm thick including all labour charges
Supply and fixing of indian type water closet including all charges
Supply and fixing of European water closet including all charges
Supply and fixing of PVC rain water down fall pipe 110mm dia
Compoune wall Earth work excavation for foundation in all soils and sub soils to full depth etc
Filling with Msand including cost and Conveyance of all charges etc.
CC 1:4:8 mix using 40mm ISS HBG Metal including all cost and conveyance etc.complete.
RCC 1:1.5:3 mix using (One cement two sand and four hard bronken granite stone) using 20mm gauge hard broken granite stone jelly for foundation including cost and conveyance of all materials to site and all labour charges at site including curing etc comp
RCC 1:1.5:3 mix using (One cement two sand and four hard bronken granite stone) using 20mm gauge hard broken granite stone jelly for foundation including cost and conveyance of all materials to site and all labour charges at site including curing etc comp above base
Supplying and centering of sides and sofits includign supports and strutting upto base
Supplying and centering of sides and sofits includign supports and strutting Above base
Supplying and fabrication of steel including cost and conveyance of all labour charges '
Brick work in cm 1:5 for super structure usign stock brick including all cost and labour charges etc.complete . Complying with standard specification etc.
Plastering with cm 1:5 mix using 10mm thick including all charges
Distermbering two coats with approved distember including all labour charges
Wiring with 2x2.5 sqm pvc unsheathed using 650v grade Light point/ Fan point
Wiring with 2x2.5 sqm pvc unsheathed using 650v grade plug point
Supply and run of 2 of 1.5 sq.mm PVC insulated SC unshethed copper conductor of 1100 V grade
Supply and run of 2 of 1.5 sq.mm PVC insulated SC unshethed copper conductor of 1100 V grade in 25mm Dia GI pipe
Supply and fixing of WT Bulk head fitting
Supply and fixing of CFL fitting
Supply and fixing of single box type 4-40'W flourescent tube light fitting with copper choke and condencer with TW round block on wall or ceiling
Supply and fixing of 1200mm Ceiling fan complete fan complete with stepped electronic 300w reqular
pply and fixing of 16amps DPIC switch of 500V with fuse and neutral side handle on suitable TW box PWD
Supply and fixing of TNEB meter board
Provision for EB depost charges
water supply arrangements Supply and delivery of 25mm UPVC pipe
Supply and delivery and fixing of 500 lit capacity tank
Supply and delivery of 25mm GM gate valve
Supply and delivery of cross nail
GST Amount for providing Service to Government Contract Works for the above Construction Works. {GST Amount is the Total GST Amount for total overall quoted amount above this row in column "BB" for all works in this package}
RAJENDRAN A (BID ID -1427901)
stage.html
html • 0.04 MB
tech_eval.pdf
fin_eval.pdf
aoc.pdf
finance_699595.pdf
boq_comp_chart.xlsx
xlsx
Tap a document below to read it instantly. You can also download everything as a ZIP if you prefer.
details.html
html • 0.04 MB
Download all tender documents and submit your bid
Disclaimer: TenderKart has made every reasonable effort to ensure that the information on this page is accurate and authentic, however it cannot be held liable for any third-party claims or losses or any damages. TenderKart makes no warranty, expressed or implied, as to the results obtained from the use of this information. If you notice any error or omission, please let us know at .