Loading…
Tenderkart now works inside Claude and ChatGPT: search and analyse tenders right from your chat
Loading…
Tender ID
Eligibility, documents, scope and key termsEligibility, required documents, scope of work and key terms of this tender, in one click.
| # | Company | Status |
|---|---|---|
| 1 | Admitted-Finance 7TH FLOOR EASTERN WING CENTENNIAL SQUARE 6A DR AMBEDKAR ROAD KODAMBAKKAM CHENNAI 600024 | CHENNAI | CHENNAI | TAMIL NADU | 600024 | Admitted-Finance |
| 2 | Admitted-Finance TC III TOWER B 2ND FLOOR C WING P O BOX 979 MOUNT POONAMALLEE ROAD MANAPAKKAM CHENNAI 600089 TAMIL NADU INDIA | CHENNAI | CHENNAI | TAMIL NADU | 600089 | Admitted-Finance |
| 3 | Rejected-Technical | Rejected-Technical Technically Rejected on account of not meeting PQC |
Tender Value
Refer Docs
Closing Date
3 Aug 2022, 3:00 pmClosed
Eligibility, documents, scope and key termsEligibility, required documents, scope of work and key terms of this tender, in one click.
Mr. Sushant Deshpande
thyssenkrupp Industrial Soln India Pvt Ltd, Vikhroli, Mumbai
PILING AND GROUND IMPROVEMENT WORKS TENDER FOR NUMALIGARH REFINERY EXPANSION PROJECT
2022_NRL_697703_1
TK-1P25A-MP-RFQ-0021
Open Tender
Construction Works
Works
300 days
Numaligarh Refinery Limited Assam
Please refer Tender documents.
8 documents required · 8 mandatory
₹0
Exempted
6 Sept 2022
29 Jun 2022
4 Aug 2022
29 Jun 2022
3 Aug 2022
21 Jul 2022
29 Jun 2022 - 10 Jul 2022
Amount
Section - A
BORED CAST IN SITU CONCRETE PILES
BORED CAST IN SITU CONCRETE PILES (Refer Section 16.0 of Technical Specifications) Mobilisation of Piling rigs and construction equipments, machineries, inlcuding all necessary accessories, temporary supports, arranging kentledges & properly calibrated instruments & set ups,trucks,cranes, material handling , deputing qualified personnel,skilled and unskilled labour,safety engineer etc. to site of work, conducting the various types of pile load tests,removing shrubs,roots,bushes and other vegetation etc.completely, dewatering during monsoon if necessary, Removing,chipping and disposal of debris,excess soil, clearing the ground of the site, making way for movement of machines for piling and Carting away, stacking and spreading bored/excavated spoildisposal of waste and excess soil rubbish within the refinery complex etc. , augmenting manpower and resources to meet the project schedule complete as per scope of work enclosed in the bid document / as directed by Engineer during the tenure of the Contract, including clean up, following HSE requirment . Rate shall also include various designs of concrete mixes, that may be required from time to time. Quoted rate shall include supply of all material like cemnet , steel etc. complete in all respect to carry out the piling jobs and testing for line items mentioned below related to piling work .
Forming vertical piles by Boring, providing and installing bored cast-in-situ R.C.C. piles using cement concrete of grade M 30 with either Ordinary Portland Cement of Grade-43/Grade-53 or Portland Pozzolana Cement (PPC, fly ash based) confirming to IS: 1489 Part 1 or Portland Pozzolana Cement (PPC, calcined based) confirming to IS: 1489 Part 2 (with minimum cement content of 400 kg/cu.m) including supply and application of Bipolar corrosion inhibiting admixture POLYALK CP293 or equivalent @ 3 kg per cubic meter of concrete, by approved technique through all types of subsoil strata using coarse aggregates of 20 mm and down size to carry a safe working load not less than that specified in the drawing, excluding the cost of steel reinforcement but including the cost of boring with casing and/or bentonite solution for maintaining borehole side, tremie concreting, supply of necessary materials , machnineries and labours and carrying out all ancillary works, disposal of surplus materials and vegetations, including earth/muck, bentonite etc at designated areas for all leads and lifts within refinery premises, shifting of plant and equipment from one pile location to other, all complete as per drawing and direction of Engineer-in-charge. Length of pile up to 20.0 meter plus concreting minimum 600 mm above cut-off level. : 450 mm (uniform) diameter piles. Rate includes all ancillary equipments, materials, tools, tackles , laboiur etc. all complete necessary to install Bored cast-in-situ R.C.C. piles at site, as per Technical specification and demobilisation of the same after completion of job. (Length of pile will be measured from Pile Cut-off level (C.O.L.) to pile tip level).
All above activities for dia, Basic expected length as follows: Diameter of pile = 750 mm. Basic length of pile from C.O.L. = 20 metres.
Extra for supply , using and proper disposal of polymer instead of bentonite as per 16.104 for Diameter of pile 750 mm, length of pile 20M , Grade of Concrete-M30, with minimum cement content of 400 kg/m3)
All activities and scope same as 16.102 but for length of pile beyond 20M but not more than 30 M for 450 mm dia. pile.
All activities and scope same as 16.106 but for 750 mm dia. pile.
Extra for supply , using and proper disposal of polymer instead of bentonite as per 16.108 for Diameter of pile 750 mm, length of pile in excess of 20.0M but not more than 30 M, Grade of Concrete-M30, with minimum cement content of 400 kg/m3)
Empty boring for vertical piles, measured from the working level to plus 600 mm above the cut off level for 450 mm dia. pile.
All activities and scope same as 16.114 but for 750 mm dia. pile.
Providing and laying reinforcement steel in RCC works as per drawing and specifications including preparation and obtaining approval of bar bending schedule, straightening, decoiling, removing milscales and rust, cutting, bending to required shape, binding in position,welding as required , supply of approved type of binding wire etc.High Yield strength Deformed bars (HYSD) produced by the thermo-mechanical treatment process of grade as per IS1786 but with enhanced specified minimum percentage elongation (>14.5%) as per IS13920 for Fe 500D. .
Contractor shall transport surplus earth from Refinery premises and dispose the earth in various locations outside refinery premises as per below SOR item (16.120A and 16.120B) and scope of work of the tender and as directed by NRL/EPCM1 as per site requirement .
Carting away, stacking and spreading bored/excavated spoil mixed with bentonite muck out side the refinery complex / refinery gate for a lead upto 5 KM from Pragati dwar (NREP gate ) / existing Refinery nearest exit gate
Carting away, stacking and spreading bored/excavated spoil mixed with bentonite muck out side the refinery complex / refinery gate for a lead of upto 15 KM from Pragati dwar (NREP gate ) / existing Refinery nearest exit gate
Extending piles above cut off level, if required, including supplying and pouring M-30 concrete with a minimum cement content of 400 Kg/cu.m. of concrete and with water cement ratio (including water contained in the aggregates) not exceeding 0.45 inlcuding all shuttering, vibrating, curing, etc. complete but excluding reinforcement (Any building up of piles upto specified cutoff level if required to be done, due to any reason other than design change shall be at piling CONTRACTOR's cost) for 450 MM DIA. PILE.
All activities and scope same as 16.121 but for 750 mm dia. pile.
LOAD TESTING ON PILES : A. INITIAL LOAD TESTS
Carrying out initial cyclic vertical load test on single vertical test pile as per IS-2911 with loading equal to two and half times the proposed safe bearing loads including necessary arrangements such as jacks, measuring devices, structural frame work for platform, kentledge , excavation upto cut off level and backfilling all complete as required. Providing and installing test piles shall be measured and paid separately for 450 mm dia. bored cast-in-situ piles. Note :The necessary preparatory work, making of pile head, finishing pile head by breaking off the concrete above the cutoff level , supply & erection of kentledge of suitable magnitude, labour, excavation, back filling, compaction etc., removal of load along with all preparatory works and measuring equipment after execution of test, all tools and tackles required, analyzing the results, making the report and submitting the records and reports, all complete as per specifications and directions of Engineer‐in‐Charge shall be in the scope of contractor.
All activities and scope same as 16.125 but for 750 mm dia. bored cast-in-situ piles.
Carrying out initial lateral load test on single vertical pile as per IS 2911 with loading equal to two and half times the proposed safe bearing loads including all necessary arrangements such as jacks, measuring devices, structural framework for platform, kentledge, excavation upto cut- off level and backfilling all complete as required. Providing and installing test piles shall be measured and paid separately for 450 mm dia. pile.
All activities and scope same as 16.129 but for 750 mm dia. pile.
Carrying out initial pull out load test on vertical test piles as per IS:2911 (Type of loading shall be as per approved loading method) with loading equal to two and half times the proposed safe bearing loads including all activities as mentioned in 16.129 for 450 mm dia. pile.
All activities and scope same as 16.133 but for 750 mm dia. pile.
B. ROUTINE LOAD TESTS
Carrying out routine maintained vertical load test on single vertical working pile as per IS 2911 with loading equal to one and half times the proposed safe bearing loads including all necessary arrangements such as jacks, measuring devices, structural framework for platform, kentledge, excavation upto cut- off level and backfilling all complete as required for 450 mm dia pile.
All activities and scope same as 16.137 but for 750 mm dia. pile.
Carrying out routine maintained lateral load test on vertical piles as per IS:2911 with loading equal to one and half times the proposed safe bearing loads including all activities as mentioned in 16.137. For this test, two working piles shall be used and jacked apart. Both piles shall be considered as test piles. The lateral deflection of both the piles shall be recorded. However, testing both these piles shall be considered as one test, for 450 mm dia. piles.
All activities and scope same as 16.141 but for 750 mm dia. pile.
Carrying out routine pull out load test on vertical working piles as per IS:2911 (Type of loading shall be as per maintained loading method) with loading equal to one and half times the proposed safe bearing loads including all activities as mentioned in 16.137 for 450 MM DIA. PILE.
All activities and scope same as 16.145 but for 750 mm dia. pile.
Making preparation and carrying out Pile integrity test (NDT using High sensitive accelerometer or equivalent conforming to specification for all piles through specialist approved agency, in consultation with Owner/Consultant and submitting the report on all the piles as per specification and submitting the report to Owner / Consultant for approval
Chipping of piles up to cut off level as shown on the drawings, ensuring that while chipping , the reinforcement is kept completely intact including cleaning and coating exposed reinforcement with cement wash completely. For 750 mm dia. of pile.
Excavation in ordinary soil including clay black cotton soil, soft & hard murrum, sand, gravel, soil containing small pebbles, rubble, boulders, removable without breaking/blasting, etc. which can be loosened manualy or mechanically operating tackles such as pick shovels, front loader (as defined in IS:1200) etc. for all types of foundations/footings, plinth beams, pilecaps or any other substructure, including shoring, strutting, dewatering and disposal of surplus earth up to a distance of 1000 metre from the nearest edge of excavation area. The rate shall include all tools, tackles, supervision, transport and incidental expense, overhead & profit, etc. as per section 1 of Tech. Specification, up to and including a depth of 2M below existing level. (Mode of measurement shall be as per footprint area of PCC dimensions)
All activities & scope same as in item 16.150.1 but for excavation below 2M and upto 4 M below existing ground level.
All activities & scope same as in item 16.150.1 but for excavation below 4M and upto 6 M below existing ground level. (For shoring required sheet piling to be included in quoted rates)
Dismantling of existing structures or part at all levels and breaking in to small pieces (suitable for backfilling) including all leads and lifts, tools, tackles, compressed air, labour, crane, consumables and disposal within refinery premises as directed by Engineer-in-charge
All type of Concrete, PCC
Removal of existing steel , structural members , pipes,cables etc.. Including cutting and disposal anywhere within refinery premises as directed by Engineer-in-charge
Section B
STONE COLUMNS\ GROUND IMPROVEMENT
Designing & providing all material, tools, tackles and constructing stone columns as specified, and to control settlements, as per design, guidelines, material specifications, construction methods given in Job supply specification.
Mobilisation of adequate number of rigs, tools, tackles, plant, equipment etc. and all accessories required for the construction of the stone columns/ ground improvement as per specifications and demobilising the same after the works are complete.
STONE COLUMNS BELOW SHALLOW FOUNDATION FOR ENHANCEMENT OF NET SBC & LIQUEFACTION MITIGATION
Provide and construct stone columns below bottom of stone sand blanket provided beneath foundation (3.0m below FGL) including all material, labour etc. all complete as per specifications to improve the existing net safe bearing capacity of soil to 14 T/M² limiting the settlement to 25mm (post erection of structures) (to be proven by initial and routine load tests specified in Job Supply specification) for Shallow foundation with liquefaction mitigation of soil layers as per geotechnical report. (Unit of measurement -RM starting from 3m below FGL)
Stone COLUMNS Dia - 900 MM
DESIGN CALCULATIONS Provide design calculations depicting desired net SBC and mitigation of liquefaction & method to achieve the same in line with specification TP-1ZZZA-CV-SPE-0040. Also, provide stone columns layout for item no. 17.1 for EPCM1 approval before start of execution. Contractor has to carry out soil investigation on his own as per design requirement / instructions of EIC, in addition to the existing soil data provided within his quoted rates. (Mode of measurement will be foundation footprint area)
Approval of IIT or NIT or Government College of Engineering for item no. 17.2 before start of execution (This is a Lumpsum Payment to be considered for entire scope of design work)
STONE COLUMNS AROUND CONCRETE PILES FOR LIQUEFACTION MITIGATION
Provide and construct stone columns bottom of foundation (2.5 m below FGL) including all material, labour etc. all complete as per specifications between and around 750mm dia. concrete piles with liquefaction mitigation of soil layers as per geotechnical report. (Unit of measurement -RM starting from 3m below FGL)
Stone COLUMNS Dia - 700 MM
Stone COLUMNS Dia - 900 MM
DESIGN CALCULATIONS Provide design calculations depicting desired increase in N-value in order to mitigate soil liquefaction below all the units (Corresponding piling layouts provided by EPCM1) & method to achieve that N-value in line with specification TP-1ZZZA-CV-SPE-0040.Also provide stone columns layout between and around concrete piles for item no. 17.3 for EPCM1 approval before start of execution. (Mode of measurement will be foundation footprint area)
Approval of IIT or NIT or Government College of Engineering for item no. 17.4 before start of execution (This is a Lumpsum Payment to be considered for entire scope of design work)
To carry out specified no. of initial load tests on single columns (at 1.5 times design load as per clause 3.5 of IS15284 part 1. Contributory area for Design load should be calculated in line with clause 7.4 of IS15284 part 1) at specified locations as given by the consultant/client as per Job Supply specifications with necessary kentledge etc. complete in all respects and making a report thereof to confirm achievement of net SBC as mentioned in item 17.1
To carry out vertical plate initial load tests on ground within a group of three adjacent stone columns (at 1.5 times design load as per clause 3.5 of IS15284 part 1. Contributory area for Design load should be calculated in line with clause 7.4 of IS15284 part 1) at specified locations as given by the consultant/client as per Job Supply spec.to confirm achievement of net SBC as mentioned in item 17.1
To carry out specified no. of routine load tests on single columns(at 1.1 times design load as per clause 3.6 of IS15284 part 1. Contributory area for Design load should be calculated in line with clause 7.4 of IS15284 part 1) at specified locations as given by the consultant/client as per Job Supply specifications with necessary kentledge etc. complete in all respects and making a report thereof to confirm achievement of net SBC targeted for item 17.1
To carry out vertical plate routine load tests on ground within a group of three adjacent stone columns(at 1.1 times design load as per clause 3.6 of IS15284 part 1. Contributory area for Design load should be calculated in line with clause 7.4 of IS15284 part 1) at specified locations as given by the consultant/client as per Job Supply spec. and making a report thereof to confirm achievement of net SBC targeted for item 17.1
Conducting Electric Static cone penetration test (ECPT) conforming to ASTM D5778-20 for minimum 10M depth to specify N-Value at specified depths to confirm improvement in N-value to nullify liquifaction patential.
Stone Sand Blanket (Applicable only below shallow foundation with SBC improvement) The stone sand blanket shall be laid over the top of the stone columns for minimum 500mm thickness or as per the governing design criteria and will be compacted to a relative dry density of 85 percent. Compaction shall be carried out with rollers or by any other suitable mechanical equipment. Stone / Sand shall be laid in layers of 150mm and compacted to achieve desired compaction. The Stone Sand Blanket shall be constructed with mixture of 75 mm and down stone aggregates and well graded medium to coarse sand of Fineness Modulus not less than 2.2 mixed in the ratio of 2:1 (2 Stone Aggregates: 1 sand).
COMPACTION GROUTING\ GROUND IMPROVEMENT
Designing & providing all material, tools, tackles and carrying out compaction grouting as specified, and to control settlements, as per design, guidelines, material specifications, construction methods given in Job supply specification.
Mobilisation of adequate number of rigs, tools, tackles, plant, equipment etc. and all accessories required for the execution of the compaction grouting as per specifications and demobilising the same after the works are complete.
COMPACTION GROUTING AROUND CONCRETE PILES FOR LIQUEFACTION MITIGATION
All above activities as per 17.3 & Provide and execute compaction grouting of minimum length of 12.00M below bottom of foundation (2.5 m below FGL) including all material, labour etc. all complete as per specifications between and around 750mm dia/600 mm dia concrete piles with liquefaction mitigation of soil layers as per geotechnical report. (Unit of measurement -Pilecap foot print area. Contractor to refer preliminary foundation plan drawings )
DESIGN CALCULATIONS Provide design calculations depicting desired increase in N-value in order to mitigate soil liquefaction below all the units (Corresponding piling layouts provided by EPCM1) & method to achieve that N-value in line with specification TP-1ZZZA-CV-SPE-0039.Also provide compaction grouting pipes layout between and around concrete piles for item no. 18.1 for EPCM1 approval before start of execution. (Mode of measurement will be foundation footprint area)
Approval of IIT or NIT or Government College of Engineering for item no. 18.2 before start of execution (This is a Lumpsum Payment to be considered for entire scope of design work)
Conducting Electric Static cone penetration test (ECPT) conforming to ASTM D5778-20 for minimum 10M depth to specify N-Value for piled area for item 18.1 as per reuirements given in IS13094:1992 clause 9.2 at specified depths to confirm improvement in N-value to nullify get the desired net SBC.
LandT GeoStructure Private Limited
stage.html
html • 0.03 MB
tech_eval.pdf
boq_comp_chart.xlsx
xlsx
Tap a document below to read it instantly. You can also download everything as a ZIP if you prefer.
details.html
html • 0.03 MB
Download all tender documents and submit your bid
Disclaimer: TenderKart has made every reasonable effort to ensure that the information on this page is accurate and authentic, however it cannot be held liable for any third-party claims or losses or any damages. TenderKart makes no warranty, expressed or implied, as to the results obtained from the use of this information. If you notice any error or omission, please let us know at .