Loading…
Tenderkart now works inside Claude and ChatGPT: search and analyse tenders right from your chat
Loading…
Tender ID
Eligibility, documents, scope and key termsEligibility, required documents, scope of work and key terms of this tender, in one click.
| # | Company | Amount | Rank | Status |
|---|---|---|---|---|
| 1 | L1₹7.1 LAccepted-Finance | L1 | Accepted-Finance Rate quoted is lowest | |
| 2 | L2₹8.0 L+₹87,150 (12.2%)Accepted-Finance | L2 | Accepted-Finance Rate quoted is second lowest | |
| 3 | L3₹8.4 L+₹1.3 L (17.7%)Accepted-Finance | L3 | Accepted-Finance Rate quoted is highest |
Tender Value
₹8.1 L
EMD Value
₹9,000
Closing Date
16 Jul 2022, 4:00 pmClosed
Eligibility, documents, scope and key termsEligibility, required documents, scope of work and key terms of this tender, in one click.
Superintending Engineer
SE ETC Sultanpur 400KV S/S Campus Payagipur Sultanpur
ERECTION, TESTING and COMMISSIONING OF 160MVA 220/132KV TRANSFORMER (BBL MAKE) INCLUDING DISMANTLING and SHIFTING OF 100MVA 220/132 KV (BHEL MAKE) TRANSFORMER AND OTHER ASSOCIATED WORKS AT 220KV SUB STATION NEW TANDA UNDER ETD, AYODHYA.
2022_UPTCL_712803_1
S.T. T.No. 22/ETCS/2022-23
Open Tender
Electrical Works
Item Wise
30 days
Sultanpur
Please refer Tender documents.
2 documents required · 2 mandatory
₹1,062
SE ETC Sultanpur
₹9,000
19 Jul 2022
5 Jul 2022
18 Jul 2022
5 Jul 2022
16 Jul 2022
5 Jul 2022
180 days
Amount
Following Works are to be carried out for installation, erection, testing & commissioning of 160 MVA 220 / 132 KV T/F (BBL make) including ,Dismantling & Shifting of 100 MVA 220/132 KV (BHEL MAKE) T/F and other associated works at 220 K.V. S/S New Tanda, Ambedkar Nagar with all cost of men & CFM Operator, misc. consumables, T&P, Crane, Centrifuging Machine, etc. to complete the job satisfactorily :
Draining of complete oil from conservator, radiator and pipe lines, from 100 MVA Transformer at 220 KV S/S New Tanda into 209 Litre drums and again fill in main tank after shifting of T/F. Remaining oil storage at proper safe place as directed by engineer in charge.
Dismantling of 100 MVA T/F and accessories removing the Radiator, Conservator Tank, A Frame, Header, Bushing, Pipe line, Pump, Cooling Fan including packing of HV/LV bushing and shifting and Stacking.
Dismantling of mulsifire pipe lines, Q.B Detector, Spray nozzles of 100MVA Transformer including its shifting and Stacking.
Shifting of 100 MVA T/F main tank from plinth to near 20 Mtrs.
Additional Shifting of T/F Tank upto 50 Meter distance (1 Job. for every 5 Meter)
Dismantling of RTCC Panel of 100 MVA T/F storage at proper safe place as directed by engineer in charge.
Dismantling & re erection of 132 KV LA upon Structure and proper tightening
Shifting of Main Tank of above 160 MVA T/F upto 20 Meter distance from unloading place towards Plinth including turning of the T/F Tank, as required alongwith all associated accessories at 220 K.V. S/S New Tanda, with all due care of safety & precautions, with all cost of men, T&P and other associated works required to complete the job satisfactorily.
Additional Shifting of T/F Tank upto 30 Meter distance (1 Job. for every 5 Meter)
Complete Erection of the 160 MVA 220 / 132 KV T/F including its Bushings, Headers, Radiators, Conservator Tank, Turrets, Oil Pipe Lines, Buchholz Relay, Motor Drive Mechanism of OLTC, Cooling Fans, Oil Pump etc. complete in all respect to complete the job satisfactorily as per technical specifications.
Safe Carriage of 20 KL Transformer Oil Tank for Centrifuging of the Transformer Oil from other Sub Stations including Loading & Unloading (approx. distance 30 Km).
Transformer Oil preparation before filling into Transformer including transfer of fresh Transformer Oil from 209 Ltr. Oil Drums into 20 KL Tanks then dehydration of the Transformer Oil by Ultra High Vacuum Oil Filtration Plant after connecting the Centrifuging Pipes between Oil Tanker & Oil Filtration Plant including taking the BDV Values of Oil periodically till the required value is achieved and then Filling & Topping up of the Transformer Oil in Main Tank, Radiator, Conservator Tank etc. with all cost of Centrifuging Machine, CFM Operator, Lubricants etc.
Dehydration of 160 MVA T/F by centrifuging of the complete T/F Oil duly filled in T/F using Ultra High Vacuum Oil Filtration Plant after connecting the Centrifuging Pipes between T/F Tank & Oil Filtration Plant including taking the BDV Values of Oil and Meggering of T/F Bushings periodically till the required values are achieved including Oil in Radiators, OLTC & Conservator.
Complete Earthing of the 160 MVA T/F using 50 x 6 mm / 75 x 10 mm size M.S. Flats as per standard practice as detailed below :
Earthing of Main Tank of the Transformer, RTCC Panel, Marshalling Box, Drive Mechanism of the Cooling Fans etc. and its connection with already laid Earthmat as per standard practice.
Making of Delta for Neutral Earthing (HV & IV) by due fabrication of 3 No. 3.5 Meter long Electrodes of 36 / 40 mm dia. M.S. Round Bar, its piercing under the ground at equal distance of 1 Meter at 700 mm depth by digging of earth and connecting all the 3 No. Electrodes with 75 mm x 10 mm size M.S. Flat & connecting with existing Earthmat and taking out Riser by due cutting, bending, welding etc. as per Technical Specifications. M.S. Round Bar / Flat shall be provided by Department. (1 Job for each Delta for Earthing)
Erection of RTCC Panel of 160 MVA T/F in control Room including its earthing as per standard practice.
New Jumpering of the 160 MVA Transformer with associated Terminal Connector & PG Clamps etc. to connect the HV & LV Bushings with 220 K.V. & 132 K.V. Jack Bus Bar / CTs by fabricating new Jumper using 'Moose' / 'Zebra' Conductor as per requirement.
Termination with proper ferruling as per drawing of above laid cables in between Turrets, WTI, OTI, Bucholz Relays PRV, Coolling Fans, Pumps, OLTC, Marshalling Box, RTCC Panel etc. including laying of cables for 160 MVA Transformer mountings upto Marshelling Box.
Splicing of Fibre Optical cable in FO junction box of C&R Panel for proper communication of Scada including hardware required for job.
Laying of following size control cable in trenches from C&R panel to Marshalling box /RTCC panel as per cable shedule alongwith sadding at avery 750 mm. distance with MS saddles.
2CX2.5 Sq.mm.
4CX2.5 Sq.mm.
Conducting test by arranging appropriate equipment for following testing- 1-. WRM 2- Tan Delta 3- SFRA
Conducting testing by arranging appropriate equipment for following testing- DGA,BDV,PPM by approved Lab.
Omurmila Constructions
Meena Elect & Engg. Works
tech_bid_open.pdf
tech_eval.pdf
fin_bid_open.pdf
boq_comp_chart.xlsx
xlsx
fin_eval.pdf
Download all tender documents and submit your bid
Disclaimer: TenderKart has made every reasonable effort to ensure that the information on this page is accurate and authentic, however it cannot be held liable for any third-party claims or losses or any damages. TenderKart makes no warranty, expressed or implied, as to the results obtained from the use of this information. If you notice any error or omission, please let us know at .