| # | Company | Amount | Rank | Status |
|---|---|---|---|---|
| 1 | L1₹63.6 LAccepted-AOC | ₹63.6 L Quoted ₹77.6 L | L1 | Accepted-AOC L1 Bidder AOC issued |
| 2 | L2₹81.1 LRejected-AOC NO 68 D BLOCK 2ND FLOOR S 1 FRONTIER HOMES ALIPH MAJITH NAGAR KELAMBAKKAM CHENGALPATTU DIST CHENNAI 603 103 | CHENGALPATTU | TAMIL NADU | 603103 | ₹81.1 L | L2 | Rejected-AOC L2 Bidder Rejected |
| Sl No | Description | Qty | Unit | Renga Engineering Works India Pvt Ltd L2 | Mani Engineering Works L1 |
|---|---|---|---|---|---|
| 1.00 | I. Material Portion: ISA 110x110x10 | 14.5 | MT | 73,077 ₹12,50,347.47 | 69,930 ₹11,96,502.3 |
| 2.00 | ISA 65 x 65x8 | 3.18 | MT | 68,250 ₹2,56,101.3 | 65,310 ₹2,45,069.24 |
| 3.00 | ISA 50 x50x6 | 0.49 | MT | 68,250 ₹39,462.15 | 65,310 ₹37,762.24 |
| 4.00 | MS Plate 12mm Tk | 2.84 | MT | 92,825 ₹3,11,075.14 | 88,830 ₹2,97,687.1 |
| 5.00 | II.Labour Portion: Dismantling of existing severely corroded/damaged technological structures for BCN-42 A & 42B which involves cutting, leading and removal of damaged portion including crane, hire charges, T&P charges consumables etc. | 10.51 | MT | 12,205 ₹1,51,363.97 | 11,678 ₹1,44,828.22 |
| 6.00 | Utilizing iron & steel structural materials lifting, loading, transporting and unloading in the work spot including all hire charges. | 21.01 | MT | 6,432 ₹1,59,460.86 | 6,155 ₹1,52,593.53 |
| 7.00 | Fabrication of Angle plate for technological structures in BCN-42 A & 42B by marking, cutting & fabrication of utilizing iron & steel structural including crane hire charges, consumables and T&P hire charges. | 21.01 | Opns | 89,385 ₹22,16,015.04 | 85,535 ₹21,20,566.61 |
| 8.00 | Erection of new fabricated material for technological structures in BCN-42 A & 42B by leading, lifting, fixing in the conveyor, providing necessary scaffolding arrangements including consumables and T&P hire charges. | 21.01 | Nos | 99,195 ₹24,59,222.6 | 94,923 ₹23,53,312.03 |
| 9.00 | Cleaning the surface with shot blasting the structures of chennal and plates including cost of shots, hire charges of compressor, scaffolding arrangements including consumables and T&P hire charges. | 483 | M² | 335 ₹1,90,929.9 | 322 ₹1,83,520.68 |
| 10.00 | Labour charges for painting with three coats of paint with a total dry film thickness (DFT) of 190 to 225 Microns ie. Painting with one coat of zinc phosphate epoxy primer (60 - 70 microns) one coat of MIO epoxy undercoating (100 - 120 microns DFT) & one coat of Aromatic polyurethane (30 - 35 microns DFT) including epoxy thinner consumables and T&P hire charges. | 483 | M² | 442 ₹2,51,913.48 | 423 ₹2,41,084.62 |
Tender Value
Refer Docs
EMD Value
₹60,000
Closing Date
20 Nov 2025, 2:00 pmClosed
CE/NCTPS-I
CE/NCTPS-I
NCTPS I SEMII Circle ECHS Renewal and strengthening of most corroded damaged trestles brazing and Gusset plates in the counter weight area at eastern western side of BCN 42A and 42B
2025_EB_620624_1
CE/NCTPSI/SE/MII/SpNo113/25-26
Open Tender
Power/Energy Projects/Products
60 days
NCTPS Chennai
refer to tender document
3 documents required · 3 mandatory
₹0
₹60,000
Yes
18 Mar 2026
6 Nov 2025
21 Nov 2025
6 Nov 2025
20 Nov 2025
6 Nov 2025
Amount
I. Material Portion: ISA 110x110x10
ISA 65 x 65x8
ISA 50 x50x6
MS Plate 12mm Tk
II.Labour Portion: Dismantling of existing severely corroded/damaged technological structures for BCN-42 A & 42B which involves cutting, leading and removal of damaged portion including crane, hire charges, T&P charges consumables etc.
Utilizing iron & steel structural materials lifting, loading, transporting and unloading in the work spot including all hire charges.
Fabrication of Angle plate for technological structures in BCN-42 A & 42B by marking, cutting & fabrication of utilizing iron & steel structural including crane hire charges, consumables and T&P hire charges.
Erection of new fabricated material for technological structures in BCN-42 A & 42B by leading, lifting, fixing in the conveyor, providing necessary scaffolding arrangements including consumables and T&P hire charges.
Cleaning the surface with shot blasting the structures of chennal and plates including cost of shots, hire charges of compressor, scaffolding arrangements including consumables and T&P hire charges.
Labour charges for painting with three coats of paint with a total dry film thickness (DFT) of 190 to 225 Microns ie. Painting with one coat of zinc phosphate epoxy primer (60 - 70 microns) one coat of MIO epoxy undercoating (100 - 120 microns DFT) & one coat of Aromatic polyurethane (30 - 35 microns DFT) including epoxy thinner consumables and T&P hire charges.
Cost of paint for one coat of zinc phosphate epoxy primer (60 - 70 microns DFT), in the structures of chennal and plates.
Cost of paint for one coat of Sea Green (100 - 120 microns DFT), in the structures of chennal and plates.
Cost of paint with one coat of Aromatic polyurethane (30 - 35 microns DFT) with a total DFT of 190 to 225 microns in the structures of chennal and plates.
Erection of necessary scaffolding arrangements tie bracing for counter weight in BCN-42 A & 42B upto 15 mtr elevation for all the two sides of the counter weight BCN-42 A & 42B and dismantling the scaffolding arrangement after completing the work including cost of consumable & T&P's.
Renga Engineering Works India Pvt Ltd (BID ID -1515970)
stage.html
html • 0.04 MB
tech_eval.pdf
boq_comp_chart.xlsx
xlsx
fin_eval.pdf
aoc.pdf
Tap a document below to read it instantly. You can also download everything as a ZIP if you prefer.
details.html
html • 0.03 MB
Tendernotice_1.pdf
PDF • 0.67 MB
BOQ_742145.xls
BOQ • 0.33 MB
Download all tender documents and submit your bid