| # | Company | Amount | Rank | Status |
|---|---|---|---|---|
| 1 | L1₹26.4 LAccepted-AOC | L1 | Accepted-AOC Awarded | |
| 2 | L2₹26.5 L+₹12,038.52 (0.46%)Rejected-AOC | L2 | Rejected-AOC Not Awarded |
Tender Value
₹26.4 L
EMD Value
₹52,800
Closing Date
1 Oct 2022, 2:00 pmClosed
E.E., PWD(R), East Guwahati Territorial Road Div.
Bamunimaidan, Guwahati-21
Re-construction of Stone Masonry Guard Wall Adjacent to State Cancer Institute at GMCH Approach Road, Bhagagarh under SOPD (G) for the year 2022-23
2022_PWD_27188_1
EGTRD /GCD-1/ TB-1/ 2022-23 / 2985
Open Tender
Civil Works
Works
90 days
Kamrup
Please refer Tender documents.
6 documents required · 6 mandatory
₹792
Yes
₹52,800
Yes
19 Jan 2023
27 Sept 2022
6 Oct 2022
27 Sept 2022
1 Oct 2022
27 Sept 2022
27 Sept 2022 - 1 Oct 2022
Amount
Earth work in excavation of foundation of structures as per drawing and technical specification, including setting out, construction of shoring and bracing, removal of stumps and other deleterious matter, dressing of sides and bottom and backfilling with approved materials.(I) Ordinary Soil (A) Manual Means (Depth upto 3 m) (Without de-watering)
Removal of unsuitable soil including excavation, loading and disposal upto 1000 m lead but excluding compaction ground supporting embankment subgrade replacement by suitable soil, which shall be paid separately as per Clause 303.5.2 as per Technical Specification Clause 302.3.11
Providing and laying of dry rubble flooring complete as per drawings and technical specifications Clause 1303.3
Plain cement concrete work 1:3:6 nominal mix in foundation with crushed stone agg 40mm nominal size mechanically mixed, placed in foundation and compacted by vibration including curing for 14 days
Stone masonry work in cement mortar 1:3 for substructre complete as per drawing and Technical Specification. A) Random Rubble Masonry
Plastering with cement mortar (1:3) on brick work in sub-structure as per Technical specifications.
Providing weep holes in Brick masonry/Plain/ Reinforced concrete abutment, wing wall/return wall with 100 mm dia AC pipe, .complete as per drawing and technical specifications.
Back filling behind abutment, wing wall and return wall complete as per drawing and technical specification. (B) Sandy materials
Re-onstruction of solid footpath Dismantling of existing structures like culverts, bridges, retaining walls and other structure comprising of masonry, cement concrete, wood work, steel work, including T&P and scaffolding wherever necessary, sorting the dismantled material,disposal of unserviceable material and stacking the serviceable material with all lift and lead of 1000 metres II) Dismantling Brick/Tile work b) in cement mortar for Brick wall
Dismantling of existing structures like culverts, bridges, retaining walls and other structure comprising of masonry, cement concrete, wood work, steel work, including T&P and scaffolding wherever necessary, sorting the dismantled material,disposal of unserviceable material and stacking the serviceable material with all lift and lead of 1000 metres II) Dismantling Brick/Tile work b) in cement mortar for PCC soling
Earth work in excavation of foundation of structures as per drawing and technical specification, including setting out, construction of shoring and bracing, removal of stumps and other deleterious matter, dressing of sides and bottom and backfilling with approved materials.(I) Ordinary Soil (A) Manual Means (Depth upto 3 m) (Without de-watering)
Removal of unsuitable soil including excavation, loading and disposal upto 1000 m lead but excluding compaction ground supporting embankment subgrade replacement by suitable soil, which shall be paid separately as per Clause 303.5.2 as per Technical Specification Clause 302.3.11
Brick masonry work in cement mortar 1:3 for substructre complete as per drawing and Technical Specification. A) Random Rubble Masonry
Plastering with cement mortar (1:3) on brick work in sub-structure as per Technical specifications.
Back filling behind abutment, wing wall and return wall complete as per drawing and technical specification. (B) Sandy materials
Providing brick soling in earthen shoulder with stone/best quality jhama brick, sand packed and laid to true line and level and in panel after preparing the subgrade including earthwork in excavation as directed including all labour and materials and if necessary dewatering, complete.
Plain / Reinforced cement concrete in sub- structure complete as per drawing and technical specifications and steel shuttering formwork. Using concrete Mixer M20
Providing weep holes in Brick masonry/Plain/ Reinforced concrete abutment, wing wall/return wall with 100 mm dia AC pipe, .complete as per drawing and technical specifications.
Tubular steel railing on Medium Weight steel channel (ISMC series) 100mmx50mm (Providing, fixing and erecting 50mm dia steel pipe railing in 3 rows duly painted on medium weight steel channels (ISMC series) 100mmx50mm, 1.2 metres high above ground, 2m center to center, complete as per approved drawings.
Mohammad Chottan Khan
stage.html
html • 0.04 MB
tech_bid_open.pdf
tech_eval.pdf
fin_bid_open.pdf
boq_comp_chart.xlsx
xlsx
fin_eval.pdf
aoc.pdf
Tap a document below to read it instantly. You can also download everything as a ZIP if you prefer.
details.html
html • 0.03 MB
Download all tender documents and submit your bid
Disclaimer: TenderKart has made every reasonable effort to ensure that the information on this page is accurate and authentic, however it cannot be held liable for any third-party claims or losses or any damages. TenderKart makes no warranty, expressed or implied, as to the results obtained from the use of this information. If you notice any error or omission, please let us know at .