| # | Company | Amount | Rank | Status |
|---|---|---|---|---|
| 1 | L1₹3.0 LAccepted-AOC GIRIDIH AREA GIRIDIH | GIRIDIH | JHARKHAND | 815301 | ₹3.0 L Quoted ₹2.5 L | L1 | Accepted-AOC L1 |
| 2 | L2₹3.0 LRejected-Finance TETULMURI SIJUA DHANBAD | DHANBAD | JHARKHAND | 818142 | ₹3.0 L | L2 | Rejected-Finance L2 |
| 3 | L3₹4.1 LRejected-Finance DATTUMURI BASTI 22 12 SIJUA DHANBAD | DHANBAD | DHANBAD | JHARKHAND | 828121 | ₹4.1 L | L3 | Rejected-Finance L3 |
| Sl No | Description | Qty | Unit | M/S ZEE ENTERPRISES L1 | ZED ENTERPRISES L3 | Tara Enterprises L2 |
|---|---|---|---|---|---|---|
| 1.00Repair and maintenance, including replacement of cork sheet, bushing, insulator, copper stud, and other related accessories of HT transformers at various locations, including 1 MVA transformers at Town Supply and Beniadih, in the Giridih Area. | ||||||
| 2.00Repair and maintenance Changing of Cork sheet Bushing Insulator and copper Stud and other related accessories of 02 Nos 200 KVA HT Transformer (i) 11KV/440V Workshop (ii) 11 Kv/440, 02 No water supply | ||||||
| 3.00 | Top cover Opening and fitting the same after cleaning | 2 | Job | 4,925 ₹9,850 | 25,000 ₹50,000 | 1,500 ₹3,000 |
| 4.00 | Internal and external cable connection Opening and refitting the Same | 2 | Job | 7,387 ₹14,774 | 2,500 ₹5,000 | 2,500 ₹5,000 |
| 5.00 | Cork Sheet Changing of Primary and secondary Bushing | 14 | Nos | 1,231 ₹17,234 | 900 ₹12,600 | 900 ₹12,600 |
| 6.00 | Cork Sheet Changing of Top Cover | 2 | Nos | 2,364 ₹4,728 | 2,000 ₹4,000 | 2,000 ₹4,000 |
| 7.00 | Copper Stud Secondary Side with nut check washer | 8 | Nos | 2,400 ₹19,200 | 3,500 ₹28,000 | 3,500 ₹28,000 |
| 8.00 | Copper Stud Primary side with nut check nut washer | 6 | Nos | 2,100 ₹12,600 | 2,500 ₹15,000 | 2,500 ₹15,000 |
| 9.00 | Changing of bushing Insulator Primary and secondary Side | 14 | Nos | 800 ₹11,200 | 1,300 ₹18,200 | 1,300 ₹18,200 |
| 10.00 | Repairing of Top Changer | 2 | Job | 3,447 ₹6,894 | 2,500 ₹5,000 | 2,500 ₹5,000 |
Tender Value
₹3.4 L
EMD Value
₹4,400
Closing Date
9 Mar 2026, 6:00 pmClosed
SO EnM GIRIDIH AREA
GM OFFICE, BANIADIH GIRIDIH AREA, CCL
SO(EnM)/GRD/E-NIT/25-26/35 Dtd- 27.02.2026
2026_CCL_354926_1
SO(EnM)/GRD/E-NIT/25-26/35 Dtd- 27.02.2026
Open Tender
Electrical and Maintenance Works
15 days
GIRIDIH AREA
LETTER OF BID, GST, PAN, UNDERTAKING, DSC CERTIFICATE, WORK EXPERIENCE, LEGAL STATUS OF FIRM, SITE VISIT REPORT, LABOR LICENCE OR DECLARATION, CMPF OR EPF REGISTRATION, ELECTRICAL LICENSE
4 documents required · 4 mandatory
₹4,400
8 Apr 2026
27 Feb 2026
10 Mar 2026
27 Feb 2026
9 Mar 2026
27 Feb 2026
27 Feb 2026 - 5 Mar 2026
Repair and maintenance, including replacement of cork sheet, bushing, insulator, copper stud, and other related accessories of HT transformers at various locations, including 1 MVA transformers at Town Supply and Beniadih, in the Giridih Area.
Repair and maintenance Changing of Cork sheet Bushing Insulator and copper Stud and other related accessories of 02 Nos 200 KVA HT Transformer (i) 11KV/440V Workshop (ii) 11 Kv/440, 02 No water supply
Top cover Opening and fitting the same after cleaning
Internal and external cable connection Opening and refitting the Same
Cork Sheet Changing of Primary and secondary Bushing
Cork Sheet Changing of Top Cover
Copper Stud Secondary Side with nut check washer
Copper Stud Primary side with nut check nut washer
Changing of bushing Insulator Primary and secondary Side
Repairing of Top Changer
Repair and Maintenance changing of Cork Sheet , Bushing insulator and copper Stud and other related accessories of 3 Nos, 150 KVA HT Transformer (i) 2.2 KV/220V(ii) 2.2 KV /440V DAV School (iii) 2.2 KV/550V Karmaljore Pump
Top cover Opening and fitting the same after cleaning
Internal and external cable connection Opening and refitting the Same
Cork Sheet Changing of Primary and secondary Bushing
Cork Sheet Changing of Top Cover
Copper Stud Secondary Side with nut check washer
Copper Stud Primary side with nut check nut washer
Changing of bushing Insulator Primary and secondary Side
Repairing of Top Changer
Repair and Maintenance of 01 Nos 1MVA Transformer, 11KV/2.2 Town Supply and Beniadih Sub-Station
Repair and Maintenance of 01 Nos 1MVA Transformer, 11KV/2.2 Town Supply and Beniadih Sub-Station
Internal and External cable connection and refitting
Cork Sheet Changing of Primary and secondary Bushing
Cork Sheet Changing of Top Cover
Cork Sheet changing of conservator tank
Cork Sheet changing Buchloz Relay
Repairing of Top Changer
Copper Stud Secondary Side with nut washer
Copper Stud Primary side with nut check nut washer
Changing of bushing Insulator Primary and secondary Side
Total impact of GST for the purpose of CTC
Please Enable Macros to View BoQ information
stage.html
html • 0.04 MB
techsummary_367758.pdf
finsummary_367758.pdf
aoc.pdf
finance_367758.pdf
boq_comp_chart.xlsx
xlsx
Tap a document below to read it instantly. You can also download everything as a ZIP if you prefer.
details.html
html • 0.05 MB
Tendernotice_1.pdf
PDF • 1.88 MB
Tendernotice_2.pdf
PDF • 0.79 MB
Tendernotice_3.pdf
PDF • 0.58 MB
BOQ_367758.xls
BOQ • 0.29 MB
Download all tender documents and submit your bid