| # | Company | Amount | Rank | Status |
|---|---|---|---|---|
| 1 | L1₹15.9 LAccepted-Finance | L1 | Accepted-Finance Accepted due to lowest rate | |
| 2 | L2₹16.0 L+₹7,829.98 (0.49%)Rejected-Finance | L2 | Rejected-Finance Rejected due to higher rate |
Tender Value
₹16 L
EMD Value
₹1.6 L
Closing Date
21 Sept 2026, 12:00 pmClosed
EXECUTIVE ENGINEER CD-2 PWD HARDOI (HQ-BILGRAM)
EXECUTIVE ENGINEER CD-2 PWD HARDOI (HQ-BILGRAM)
Reconstruction of Balamau-Lucknow Road to Chirkati Link road including with 5-year maintenance.
2026_CEUCZ_1184427_1
2045/10 MG / 2026 DATE 01.09.2026
Open Tender
Civil Works
Percentage
90 days
EXECUTIVE ENGINEER CD-2 PWD HARDOI (HQ-BILGRAM)
Please refer Tender documents.
2 documents required · 2 mandatory
₹944
₹1.6 L
Yes
25 Sept 2026
11 Sept 2026
21 Sept 2026
11 Sept 2026
21 Sept 2026
11 Sept 2026
This is a percentage-rate BOQ. The schedule below shows estimated quantities and rates. Bidders quote a single percentage above or below the total estimated cost.
| Sl No | Description | Qty | Unit | Est. Rate | Est. Amount |
|---|---|---|---|---|---|
| 1 | Providing, laying, spreading and compacting stone aggregates of specific sizes to water bound macadam specification including spreading in uniform thickness, hand packing, rolling with smooth wheel roller 80-100 kN in stages to proper grade and camber, applying and brooming, stone screening/binding materials to fill-up the interstices of coarse aggregate, watering and compacting to the required density grading 2 as per Technical Specification Clause 405. Including all taxes and labour cess but excluding GST | 10 | Cum | 4,850 | ₹48,500 |
| 2 | Providing, laying, spreading and compacting stone aggregates of specific sizes to water bound macadam specification including spreading in uniform thickness, hand packing, rolling with smooth wheel roller 80-100 kN in stages to proper grade and camber, applying and brooming, stone screening to fill-up the interstices of coarse aggregate, watering and compacting to the required density Grading 3as per Technical Specification Clause 405. Including all taxes and labour cess but excluding GST | 137 | Cum | 4,900 | ₹6,71,300 |
| 3 | Brick edging in both sides of road of 1st class brick deep laid with mud mortar all labour finished to the required templete and in proper alignment and also including dressing and ramming the excavated earthincluding all labour T&P sudries required for proper completion of the work with material. Including all taxes and labour cess but excluding GST | 0.49 | KM | 87,500 | ₹42,875 |
| 4 | Prime Coat (i) Low porosity
Providing and applying primer coat with bitumen emulsion (SS-1) on prepared surface of granular base including cleaning of road surface and spraying primer at the rate of 0.70 kg/sqm using mechanical means as per Technical Specification Clause 502 Including Biumen, all taxes and labour cess but excluding GST | 1,837.5 | Sqm | 55 | ₹1,01,062.5 |
| 5 | Providing and applying tack coat with Bitumen VG-10 using bitumen distributor at the rate of 0.30kg per sqm on the prepared surface cleaned with Hydraulic broom as per Technical Specification Clause 503. Including Biumen, all taxes and labour cess but excluding GST | - | Sqm | 20 | - |
| 6 | Providing, laying and rolling of open-graded premix carpet of 20 mm thickness composed of 13.2 mm to 5.6 mm aggregates either using VG-10 Bitumen and level to serve as wearing course on a previously prepared base, including mixing in a suitable plant, laying and rolling with a three wheel 80-100 kN static roller capacity, finished to required level and grades as per Technical Specification Clause 508 Including Biumen, all taxes and labour cess but excluding GST | - | Sqm | 225 | - |
| 7 | Providing and laying seal coat with VG-10 Bitumen sealing the voids in a bituminous surface laid to the specified levels, grade and cross fall using Type C as per Technical Specification Clause 510 A.By Manual Means. Including Biumen, all taxes and labour cess but excluding GST | - | Sqm | 82 | - |
| 8 | Construction of subgrade and earthen shoulders with approved material obtained from borrow pits with all lifts and leads, transporting to site, spreading, grading to required slope and compacted to meet requirement of Table 300.2 with lead upto 1000 m as per Technical Specification Clause 303.1. Including all taxes and labour cess but excluding GST | 220 | Cum | 95 | ₹20,900 |
| 9 | Maintenance of Road Work constructed road for next five yrears after completion the contractor shall be paid total maintenance cost for five year in the form of installment as below, The payment shall the inclusive of cess but excluding GST. Payment shall be done as per satisfaction of engineer in charge regarding maintenance work carried out by contractor.. (Including all taxes and labour cess but excluding GST)
(i) From completion of 1 Year to 2nd year 0.75% | 0.49 | KM | 23,000 | ₹11,270 |
| 10 | (ii) 2nd year to 3rd year 1.50% | - | KM | 46,000 | - |
stage.html
html • 0.04 MB
tech_bid_open.pdf
tech_eval.pdf
fin_bid_open.pdf
boq_comp_chart.xlsx
xlsx
fin_eval.pdf
Tap a document below to read it instantly. You can also download everything as a ZIP if you prefer.
details.html
html • 0.03 MB
Tendernotice_1.pdf
PDF • 0.57 MB
Tendernotice_2.pdf
PDF • 0.44 MB
BOQ_2228204.xls
BOQ • 0.23 MB
TenderNotice2045.pdf
PDF • 0.56 MB
Download all tender documents and submit your bid
Disclaimer: TenderKart has made every reasonable effort to ensure that the information on this page is accurate and authentic, however it cannot be held liable for any third-party claims or losses or any damages. TenderKart makes no warranty, expressed or implied, as to the results obtained from the use of this information. If you notice any error or omission, please let us know at .