Tender Value
₹9.5 L
Closing Date
10 Jul 2023, 3:00 pmClosed
BDO(VP)
t.kallupatti
Madurai District Construction of Waiting Shed,Cement Floor and Compound wall in Samathuva Mayanam in P.Muthulingapuram village and Panchayat.in T. Kallupati Block
2023_RDTN_334968_1
05/TKP/AGAMT-II/2023-24
Open Tender
Civil Works
Works
90 days
T.Kallupatti
Class III
2 documents required · 2 mandatory
₹0
Exempted
17 Jul 2023
5 Jul 2023
11 Jul 2023
5 Jul 2023
10 Jul 2023
5 Jul 2023
Amount
Madurai District Construction of Waiting Shed,Cement Floor and Compound wall 40m in Samathuva Mayanam in P.Muthulingapuram village @ Panchayat. in T. Kallupati Block
Earth work excavation for foundation in all class of soils except hard rock requiring blasting but shoring shuttering and baling out water wherever necessary and refilling the sides of the foundation with excavated earth in layers of not more than 15 cm thick well rammed and consolidated and depositing the surpous earth in all palces shown by the departmental officers with initial lead and lift etc including levelling the site etc., complete with standard specification in hard stiff cllay, stiff black cotton soil, hard fred earth, shale murums, gravel stoney earth, and earth mixed with 50% fair sized boulders, and hard gravelly soil in foundation.
Supllying filling with filling M.sand in layers not more than 15 cm thick ,well rammed, wattered and compacted etc,complete
Supplying and filling of conveyed earth with a lead of KM for basement filling inculding cost and conveyance of all materiales curing etc ,complete.
Cement concrete 1:4:8 (one cement, five sand, and Ten hard broken stone) Using 40mm ISS size Hand Broken granite stone Jelly for Foundation and Flooring including labour charges for mixing concrete watering and laying the concrete in layers not more than 15 cms thick compacting etc complete complying with standard specification etc complete.
Supplying and erection centering for sides and soffits inculding necessary supports and structing for plain surfaces such as RCC Slab,Lintel,Beam coloum,sunshade etc complete.,
Supplying, fabricating and placing in position Mild Steel / Ribbed Tor Steel grills for all RCC works as per design given including cost of steel and G.I. binding wire in all floors etc. complete complying with standard specification. (Contractor has to make his own arrangements for the supply of steel and binding wire)
R.Cement concrete 1:11/2:3 mix using 20 mmHBGS metal inculding cost and coveyance of all materials to site including labour for mixing ,laying,curing etc complete.,
Brick work using country bricks of size 83/4"x41/4"x23/4" in cement mortar 1:5 (One cement and five M.Sand) including curing neat finishing, etc., complete complying with standard specifiction.
Cement concrete 1:2:4 mix using 20mm HBG metal including cost and conveyance of all materials and all labour charges etc complete.
Plastering with cm 1:3 10mm thick including cost and conveyance and all labour charges etc complete
Plastering with Cement Mortar 1:5 (One cement and Five M.Sand), 12mm thick in all floors including curing etc. complete complying with standard specification and as directed by the departmental officers.
Weathering course in brick jelly lime concrete using broken brick jelly of size 20mm uniform gauge in pure slaked lime (no crushed stone M.Sand to be used) to the proportion of brick jelly to lime being 32:12.5 by volume and laid over the RCC roof slab in a single layer of required slope and finished by beating the concrete with wooden beaters of approved pattern, keeping the surface constantly wet by sprinkling lime jaggery water, etc., complete as per standard specification and as directed by the deparmental officers.
Finishing the top of roof with one course of machine pressed tiles of size 230mm x 230mm x 20mm of approved quality set in Cement Mortar 1:3 (One Cement and Three Crushed stone M.Sand) 12mm thick mixed with water proofing compound conforming to ISS at 2% by weight of cement used and the joints pointed neatly to full depth of tiles with the same cement mortar mixed with red oxide and water proofing compound including curing etc., complete complying with standard specification and as directed by the departmental officers
Granaolithic floor finish of 25 mm thick in PCC 1:2:4 using 10-12 mmHBGS Jelly inculding curing ete.complete.,
Painting two coats with oil bound Distember over one coat of Primier (using White Cement as primer ) in all floors including brushes etc ., complete etc
Painting two coats with ready mixed Plastic emulsion of first class quality paint and of approved colour over a priming coat ,inculding through scrapping, clean removal of dirt etc. complete and inculding necessary plasterof paris , putty whereever required .
CONSTRUTION OF NEW COMPOUND WALL IN Samathuva Burilaground in P.Muthulingapuram village and Panchayat
Earth work excavation for foundation in all class of soils except hard rock requiring blasting but shoring shuttering and baling out water wherever necessary and refilling the sides of the foundation with excavated earth in layers of not more than 15 cm thick well rammed and consolidated and depositing the surpous earth in all palces shown by the departmental officers with initial lead and lift etc including levelling the site etc., complete with standard specification in hard stiff cllay, stiff black cotton soil, hard fred earth, shale murums, gravel stoney earth, and earth mixed with 50% fair sized boulders, and hard gravelly soil in foundation.
Cement concrete 1:4:8 (one cement, five sand, and Ten hard broken stone) Using 40mm ISS size Hand Broken granite stone Jelly for Foundation and Flooring including labour charges for mixing concrete watering and laying the concrete in layers not more than 15 cms thick compacting etc complete complying with standard specification etc complete.
Supplying and erection centering for sides and soffits inculding necessary supports and structing for plain surfaces such as RCC Slab,Lintel,Beam coloum,sunshade etc complete.,
Supplying, fabricating and placing in position Mild Steel / Ribbed Tor Steel grills for all RCC works as per design given including cost of steel and G.I. binding wire in all floors etc. complete complying with standard specification. (Contractor has to make his own arrangements for the supply of steel and binding wire)
R.Cement concrete 1:11/2:3 mix using 20 mmHBGS metal inculding cost and coveyance of all materials to site including labour for mixing ,laying,curing etc complete.,
Brick work using country bricks of size 83/4"x41/4"x23/4" in cement mortar 1:5 (One cement and five M.Sand) including curing neat finishing, etc., complete complying with standard specifiction.
Plastering with cm 1:5 12mm thick including cost and conveyance and all labour charges etc complete
Painting two coats with ready mixed Plastic emulsion of first class quality paint and of approved colour over a priming coat ,inculding through scrapping, clean removal of dirt etc. complete and inculding necessary plasterof paris , putty whereever required .
GST Amount for providing Service to Government Contract Works for the above Construction Works. { GST Amount is the Total GST Amount for total overall quoted amount above this row in column "BB" for all works in this package}
PPS CONSTRUCTION
stage.html
html • 0.03 MB
tech_eval.pdf
boq_comp_chart.xlsx
xlsx
Tap a document below to read it instantly. You can also download everything as a ZIP if you prefer.
details.html
html • 0.03 MB
Download all tender documents and submit your bid
Disclaimer: TenderKart has made every reasonable effort to ensure that the information on this page is accurate and authentic, however it cannot be held liable for any third-party claims or losses or any damages. TenderKart makes no warranty, expressed or implied, as to the results obtained from the use of this information. If you notice any error or omission, please let us know at .