| # | Company | Amount | Rank | Status |
|---|---|---|---|---|
| 1 | L1₹8.5 CrAccepted-AOC | L1 | Accepted-AOC Being the lowest and reasonable tender | |
| 2 | L2₹8.8 Cr+₹38.3 L (4.53%)Rejected-Finance 11 A KUTCHERY ROAD BALUGANJ AGRA U P 282 001 | AGRA | AGRA | UTTAR PRADESH | 282001 | L2 | Rejected-Finance Not being the lowest tender | |
| 3 | L3₹9.4 Cr+₹92.9 L (11.0%)Rejected-Finance SHOP NO 10 BMC SHOPPING CENTRE MITHA NAGAR GOREGAON WEST MUMBAI 400 104 | MUMBAI | MUMBAI SUBURBAN | MAHARASHTRA | 400104 | L3 | Rejected-Finance Not being the lowest tender | |
| 4 | L4₹9.5 Cr+₹1.1 Cr (12.5%)Rejected-Finance | L4 | Rejected-Finance Not being the lowest tender | |
| 5 | L5₹9.5 Cr+₹1.1 Cr (12.6%)Rejected-Finance ONLOOKER BUILDING 3RD FLOOR 25 SHRI P M ROAD FORT MUMBAI 400 001 | MUMBAI | MAHARASHTRA | 400001 | L5 | Rejected-Finance Not being the lowest tender |
| Sl No | Description | Qty | Unit | Idustrial products India L5 | MUKESH CONSTRUCTION CO L8 | ROY CONSTRUCTION CO L4 | CREATIVE BUILDERS L9 | AMIT ASSOCIATES L7 | Shree Ayyappa Engineering L3 | ACE CORPORATION L1 | S. C. Mangla and Co. L2 | MUKUL BUILDERS LLP L6 |
|---|---|---|---|---|---|---|---|---|---|---|---|---|
| 1.00 | Taking down cement plaster or lime plaster on walls /ceiling of any description from concrete or brick wall etc including raking out joints, hacking for key, scrubbing down with water and disposing off the retreived debris out side MD land including necessary scaffoldings etc complete all as specified and directed | 17,915 | Sqm | 30 ₹5,37,450 | 36 ₹6,44,940 | 20 ₹3,58,300 Lowest | 40 ₹7,16,600 | 59 ₹10,56,985 | 30 ₹5,37,450 | 28 ₹5,01,620 | 29 ₹5,19,535 | 40 ₹7,16,600 |
| 2.00 | Taking down chowkats or frames, exc 1.5 sqm but not exc 4 Sqm each with shutters (Without taking off shutters from the frame) including taking down of hold-fasts by cutting/chasing etc from existing surfaces and also Grills/Guard bars (where exists), complete all as specified and directed. | 1,084 | Each | 200 ₹2,16,800 | 144 ₹1,56,096 | 120 ₹1,30,080 | 210 ₹2,27,640 | 59 ₹63,956 | 120 ₹1,30,080 | 40 ₹43,360 Lowest | 40 ₹43,360 Lowest | 210 ₹2,27,640 |
| 3.00 | Taking down chowkats or frames, not exc 1.5 sqm each with shutters (Without taking off shutters from the frame) including taking down of hold-fasts by cutting/chasing etc from existing surfaces and also Grills/Guard bars (where exists), complete all as specified and directed. | 648 | Each | 200 ₹1,29,600 | 90 ₹58,320 | 120 ₹77,760 | 210 ₹1,36,080 | 76 ₹49,248 | 125 ₹81,000 | 35 ₹22,680 Lowest | 40 ₹25,920 | 210 ₹1,36,080 |
| 4.00 | Taking down and refixing in the same opening shutters of any description exceeding 1 Sq.m but not exceeding 2 Sq.m each complete all as specified and directed. | 4 | Each | 400 ₹1,600 | 180 ₹720 Lowest | 260 ₹1,040 | 400 ₹1,600 | 451 ₹1,804 | 180 ₹720 Lowest | 550 ₹2,200 | 600 ₹2,400 | 400 ₹1,600 |
| 5.00 | Taking down shutters of any description exceeding 1 Sq.m but not exceeding 2 Sq. M each complete all as specified and directed. | 162 | per leaf | 150 ₹24,300 | 90 ₹14,580 | 120 ₹19,440 | 150 ₹24,300 | 41 ₹6,642 | 55 ₹8,910 | 15 ₹2,430 Lowest | 20 ₹3,240 | 150 ₹24,300 |
| 6.00 | Demolition of cement concrete in ground floors (un-reinforced) and paving not exc. 15cm thickness (below or above ground level) including removing debris outside MD land complete all as specified and directed. | 47.19 | Cum | 220 ₹10,381.8 | 900 ₹42,471 | 300 ₹14,157 | 400 ₹18,876 | 193 ₹9,107.67 | 60 ₹2,831.4 Lowest | 90 ₹4,247.1 | 100 ₹4,719 | 400 ₹18,876 |
| 7.00 | Demolition of cement concrete (reinforced) as in roofs, shelves, chajjas, floors (other than ground floors), beams, staircase, landing, chajjas , parapet, water tank and similar suspended work etc. and removal of rubbish/ demolished materials out of MD land complete all as specified and directed. | 36.82 | Cum | 220 ₹8,100.4 | 900 ₹33,138 | 300 ₹11,046 | 400 ₹14,728 | 193 ₹7,106.26 | 400 ₹14,728 | 90 ₹3,313.8 Lowest | 100 ₹3,682 | 400 ₹14,728 |
| 8.00 | Demolition of brickwork built in cement mortar including disposal of debris, etc outside MD land, complete all as specified and directed. | 13.41 | Cum | 220 ₹2,950.2 | 630 ₹8,448.3 | 300 ₹4,023 | 300 ₹4,023 | 221 ₹2,963.61 | 400 ₹5,364 | 40 ₹536.4 Lowest | 50 ₹670.5 | 300 ₹4,023 |
| 9.00 | M&L for brick work with sub class B old size bricks straight or curved on plan exc. 6mtr mean radius, built in cement mortar 1:6, complete all as specified and directed. | 20.6 | Cum | 7,000 ₹1,44,200 | 6,300 ₹1,29,780 | 7,500 ₹1,54,500 | 8,000 ₹1,64,800 | 803 ₹16,541.8 Lowest | 8,400 ₹1,73,040 | 6,200 ₹1,27,720 | 7,700 ₹1,58,620 | 7,400 ₹1,52,440 |
| 10.00 | M&L for Brickwork with sub- class ‘B’ bricks, straight or curved on plan to any radius in half brick thick walls built in CM 1:4 complete all as specified and directed. | 116.64 | Sqm | 800 ₹93,312 | 900 ₹1,04,976 | 700 ₹81,648 Lowest | 800 ₹93,312 | 909 ₹1,06,025.76 | 700 ₹81,648 Lowest | 710 ₹82,814.4 | 800 ₹93,312 | 700 ₹81,648 Lowest |
Tender Value
₹9.2 Cr
EMD Value
₹7.9 L
Closing Date
29 Aug 2026, 6:00 pmClosed
Chief Engineer (Navy) Mumbai
HQ Chief Engineer (Navy) Mumbai, Visvesvaraya Building, Shahid Bhagat Singh Marg, Colaba, Mumbai - 400005
ADDITION ALTERATION AND SPECIAL REPAIRS TO BUILDING NOS C, E, P20, 154, 179, 208, 209 AND 210 AT NCHC POWAI, MUMBAI
2026_MES_784646_1
87980/E8
Open Tender
Civil Works
Item Rate
609 days
Powai
Please refer Tender documents
9 documents required · 9 mandatory
₹3,000
Garrison Engineer (NW) Bhandup
₹7.9 L
Yes
30 Sept 2026
14 Aug 2026
31 Aug 2026
14 Aug 2026
29 Aug 2026
22 Aug 2026
14 Aug 2026 - 19 Aug 2026
| Sl No | Description | Qty | Unit | Est. Rate | Est. Amount |
|---|---|---|---|---|---|
| 1 | Taking down cement plaster or lime plaster on walls /ceiling of any description from concrete or brick wall etc including raking out joints, hacking for key, scrubbing down with water and disposing off the retreived debris out side MD land including necessary scaffoldings etc complete all as specified and directed | 17,915 | Sqm | - | - |
| 2 | Taking down chowkats or frames, exc 1.5 sqm but not exc 4 Sqm each with shutters (Without taking off shutters from the frame) including taking down of hold-fasts by cutting/chasing etc from existing surfaces and also Grills/Guard bars (where exists), complete all as specified and directed. | 1,084 | Each | - | - |
| 3 | Taking down chowkats or frames, not exc 1.5 sqm each with shutters (Without taking off shutters from the frame) including taking down of hold-fasts by cutting/chasing etc from existing surfaces and also Grills/Guard bars (where exists), complete all as specified and directed. | 648 | Each | - | - |
| 4 | Taking down and refixing in the same opening shutters of any description exceeding 1 Sq.m but not exceeding 2 Sq.m each complete all as specified and directed. | 4 | Each | - | - |
| 5 | Taking down shutters of any description exceeding 1 Sq.m but not exceeding 2 Sq. M each complete all as specified and directed. | 162 | per leaf | - | - |
| 6 | Demolition of cement concrete in ground floors (un-reinforced) and paving not exc. 15cm thickness (below or above ground level) including removing debris outside MD land complete all as specified and directed. | 47.19 | Cum | - | - |
| 7 | Demolition of cement concrete (reinforced) as in roofs, shelves, chajjas, floors (other than ground floors), beams, staircase, landing, chajjas , parapet, water tank and similar suspended work etc. and removal of rubbish/ demolished materials out of MD land complete all as specified and directed. | 36.82 | Cum | - | - |
| 8 | Demolition of brickwork built in cement mortar including disposal of debris, etc outside MD land, complete all as specified and directed. | 13.41 | Cum | - | - |
| 9 | M&L for brick work with sub class B old size bricks straight or curved on plan exc. 6mtr mean radius, built in cement mortar 1:6, complete all as specified and directed. | 20.6 | Cum | - | - |
| 10 | M&L for Brickwork with sub- class ‘B’ bricks, straight or curved on plan to any radius in half brick thick walls built in CM 1:4 complete all as specified and directed. | 116.64 | Sqm | - | - |
stage.html
html • 0.07 MB
tech_bid_open.pdf
tech_eval.pdf
fin_bid_open.pdf
boq_comp_chart.xlsx
xlsx
fin_eval.pdf
aoc.pdf
Tap a document below to read it instantly. You can also download everything as a ZIP if you prefer.
details.html
html • 0.03 MB
Tendernotice_1.pdf
PDF • 0.39 MB
87980Tenderpages.pdf
Tender Documents • 2.41 MB
BOQ_879218.xls
BOQ • 0.48 MB
87980TenderAmendment24Aug2026.pdf
PDF • 0.07 MB
Download all tender documents and submit your bid
Disclaimer: TenderKart has made every reasonable effort to ensure that the information on this page is accurate and authentic, however it cannot be held liable for any third-party claims or losses or any damages. TenderKart makes no warranty, expressed or implied, as to the results obtained from the use of this information. If you notice any error or omission, please let us know at .