| # | Company | Amount | Rank | Status |
|---|---|---|---|---|
| 1 | L1₹1.4 CrAccepted-AOC GRAM MADHAIYA DHARMASINH NAJRA BIROLA KHAIR DISTRICT ALIGARH | KHAIR | ALIGARH | UTTAR PRADESH | ₹1.4 Cr | L1 | Accepted-AOC Reason |
| 2 | L2₹1.6 CrRejected-Finance | ₹1.6 Cr | L2 | Rejected-Finance unReasons |
| 3 | L3₹1.8 CrRejected-Finance MUGALGARHI MAJRA FULRAI TEHSEEL SIKANDRARAO HATHRAS | ₹1.8 Cr | L3 | Rejected-Finance unReasons |
Tender Value
₹2.3 Cr
EMD Value
₹13.4 L
Closing Date
19 Mar 2026, 12:00 pmClosed
SE BSR Cricle Bulandshahar
SE BSR Cricle Bulandshahar
New Construction of Khurja Pahasu Chhatari SH 63 Village banel to Pahasu Rajwahe Patri village Allipura Link road
2026_CEMRT_1124039_9
2567/96M(3)/E-Tender/BSR/25 Dt. 27.02.2026
Open Tender
Civil Works - Roads
180 days
khujra
Please refer Tender documents.
2 documents required · 2 mandatory
₹2,714
₹13.4 L
Yes
8 May 2026
12 Mar 2026
19 Mar 2026
12 Mar 2026
19 Mar 2026
12 Mar 2026
PART A Bituminous Construction of embankment with approved material obtained from borrow pits with a lift upto 1.5 m, transporting to site, spreading, grading to required slope and compacting to meet requirement of Tables 300.1 and 300.2 with a lead upto 1000 m as per Technical Specification Clause 301.5 (for embankment with ordinary soil) but excluding cost of GST.
(Cement Treated Sub base) providing, laying and spreading in uniform layers with motor grader on a prepared sub grade/Sub base, Cement @ 2% by weight to the spread Material manually,mixing in place with Rotavator and compacting with Road roller at OMC to achieve the desired unconfined compressive strength and form a layer of base. Including cost of all material, labour, T&P,and royalty but excluding cost of GST.
(Cement Treated Base) providing, laying and spreading in uniform layers with motor grader on a preparedSub base, Cement @ 4% by weight to the spread Material manually,mixing in place with Rotavator and compacting with Road roller at OMC to achieve the desired unconfined compressive strength and form a layer of base. Including cost of all material, labour, T&P, and royalty but excluding cost of GST.
Brick edging on both side of the road of M-150 bricks 7 cm. wide. 11 cm. deep, laid with mud mortar including labour & supply of bricks finished to the required template and in proper alignment and also including dressing and ramming the excavated earth as directed by the Engineer-in-charge but excluding cost of GST.
Providing and applying tack coat with bitumen VG-10 using bitumen pressure distributor at the rate of 0.30 kg per sqm on the prepared granular/ Bituminous surfaces treated with primer & cleaned with Hydraulic broom as per Technical Specification Clause 503. Including cost of, all material, Bitumen, labour, T&P, all taxes and labour cess complete but excluding cost of GST.
Providing, laying and rolling of open-graded premix carpet of 20 mm thickness composed of 13.2 mm to 5.6 mm aggregates using VG-10 grade bitumen to required line, grade and level to serve as wearing course on a previously prepared base, including mixing in a suitable plant, laying and rolling with a three wheel 80-100 kN static roller capacity, finished to required level and grades as per Technical Specification Clause 508 Including cost of, all material, Bitumen, labour, T&P, royality , all taxes and labour cess complete but excluding cost of GST.
Providing and laying seal coat by manual means with VG-10 Grade Bitumen sealing the voids in a bituminous surface laid to the specified levels, grade and cross fall using Type C as per Technical Specification Clause 510. Including cost of, all material, Bitumen, labour, T&P, royality, all taxes and labour cess complete but excluding cost of GST.
Construction of subgrade and earthen shoulders with approved material obtained from borrow pits with all lifts and leads, transporting to site, spreading, grading to required slope and compacted to meet requirement of Table 300.2 with lead upto 1000 m as per Technical Specification Clause 303.1. With ordinary earth work but excluding cost of GST.
PART B Cemented Earth work in excavation of foundation of structures as per drawing and technical specification, including setting out, construction of shoring and bracing, removal of stumps and other deleterious matter, dressing of sides and bottom and backfilling with approved material but excliuding cost of GST
Providing concrete for Plain cement concrete 1:3:6 (M-10) in open foundation complete as per drawing and technical specifications Clauses 802,803,1202&1203 Sr No. 11.4 Ref No.800 & 1200 in leveling coarse including supply of all material, labour, T&P all taxes royalty,labour cess etc. required for proper completion of work as per direction by the Engineer In-charge.but excliuding cost of GST
Providing concrete for Reinforced cement concrete (M-25) in open foundation complete as per drawing and technical specifications Clauses 802,803,1202&1203 Sr No. 11.4 Ref No.800 & 1200 with 2cm cement, approved stone grit,coarse sand & cement (excIuding suppIy of reinforcement and its bending, but incIuding its fixing and binding the same with 24 B.W.G.G.I. binding wire) and incIuding necessary centering and shuttering etc. including supply of all material, labour, T&P all taxes,labour cess etc. required for proper completion of work as per direction by the Engineer In-charge but excliuding cost of GST
RCC M25 Providing concrete for Reinforced cement concrete in sub structuren complete as per drawing and technical specifications Clauses 802,803,1202&1203 Sr No. 12.5 Ref No.800 with 2cm cement, approved stone grit,coarse sand & cement (excIuding suppIy of reinforcement and its bending, but incIuding its fixing and binding the same with 24 B.W.G.G.I. binding wire) and incIuding necessary centering and shuttering etc. including supply of all material, labour, T&P all taxes,labour cess etc. required for proper completion of work as per direction by the Engineer In-charge but excliuding cost of GST
Supplying, fitting and placing with MS bar reinforcement (Fe 415) in substructrue complete as per drawings and technical specification Clauses 1002, 1005, 1010 & 1202 including bending for proper and necessary completion of the work and including supply of steel and wastages, bends, hooks and authorised overlapping shall be measurised as per direction of Engineer-in-charge but excluding cost of GST.
Providing & fixing empty cement bags filled with sand upto 1.00 km. lead, hand sewing with suja & sutli and placing in position within 60m including cost of E. C. Bags, all labour, material and T&P required for proper completion of work as per direction of Engineer In-charge . but excliuding cost of GST
Providing & fixing reinforced cement concrete M15 grade Ordinary Kilometre Stone of standard design as per IRC:8 fixing in position including painting and printing, etc as per drawing and Technical Specification Clause 1703. Including cost of all labour, T&P, labour cess and all taxes complete but excluding cost of GST.
Providing & fixing reinforced cement concrete M15 grade 200 m Stone of standard design as per IRC:8 fixing in position including painting and printing, etc as per drawing and Technical Specification Clause 1703. Including cost of all labour, T&P, labour cess and all taxes complete but excluding cos of GST.
Cost of maintenance for Bituminous work portion for IInd Year @ 0.75% as per GO No. 17/2024 SA-113/23-1-2024-23-1099/113/2023 Dated 16.01.2024 or as per Prevailing GO
Cost of maintenance for Bituminous work portion for IIIrd Year @ 1.50% as per GO No. 17/2024 SA-113/23-1-2024-23-1099/113/2023 Dated 16.01.2024 or as per Prevailing GO
Cost of maintenance for Bituminous work portion for IVth Year @ 2.25% as per GO No. 17/2024 SA-113/23-1-2024-23-1099/113/2023 Dated 16.01.2024 or as per Prevailing GO
Cost of maintenance for Bituminous work portion for Vth Year @ 3.00% as per GO No. 17/2024 SA-113/23-1-2024-23-1099/113/2023 Dated 16.01.2024 or as per Prevailing GO
Cost of maintenance for Cement Concrete work portion for IInd Year @ 0.25% as per GO No. 17/2024 SA-113/23-1-2024-23-1099/113/2023 Dated 16.01.2024 as per Prevailing GO
Cost of maintenance for Cement Concrete work portion for IIIrd Year @ 0.50% as per GO No. 17/2024 SA-113/23-1-2024-23-1099/113/2023 Dated 16.01.2024 as per Prevailing GO
Cost of maintenance for Cement Concrete work portion for IVth Year @ 0.75% as per GO No. 17/2024 SA-113/23-1-2024-23-1099/113/2023 Dated 16.01.2024 as per Prevailing GO
Cost of maintenance for Cement Concrete work portion for Vth Year @ 1.00% as per GO No. 17/2024 SA-113/23-1-2024-23-1099/113/2023 Dated 16.01.2024 as per Prevailing GO
Please Enable Macros to View BoQ information
stage.html
html • 0.05 MB
tech_bid_open.pdf
tech_eval.pdf
fin_bid_open.pdf
boq_comp_chart.xlsx
xlsx
fin_eval.pdf
aoc.pdf
Tap a document below to read it instantly. You can also download everything as a ZIP if you prefer.
details.html
html • 0.03 MB
Tendernotice_1.pdf
PDF • 0.91 MB
T.pdf
Tender Documents • 1.84 MB
BOQ_2094632.xls
BOQ • 0.98 MB
Download all tender documents and submit your bid