| 1 | L1₹10.8 LAdmitted-Finance | ₹10.8 L | L1 | Admitted-Finance |
| Sl No | Description | Qty | Unit | M/S SAVIOUR ENVIROTECH L1 |
|---|---|---|---|---|
| 1.01 | Operation & maintenance of water treatment plant at 300bedded hostel withoperation & maintenance of the WTP shall be done to ensure smooth running, efficiently and economically. The effluent from the plant shall meet the desired limit as specified in IS : 10500 & CPHEEO manual of water supply & treatment, whichever is more stringent.
The basic requirements as listed below are to be followed by the Contractor before commissioning & during Operation & Maintenance period of the WTP :
(a) A set of recommended spares for trouble free operation of the Electrical, Mechanical, instrumentation equipments are to be kept by the agency at his cost.
(b) Proper and adequate stock of tools & plants and items like gland packing belts, lubricating oils, greases are to be kept by the agency at his cost.
(c) Servicing schedule of preventive maintenance as suggested by the manufacturer has to be strictly adhered to.
(d) Training of Agency’s operators in proper operating procedures & maintenance practice.
(e) Compliance with agreed operation & maintenance schedules including logging of all activities to the due satisfaction of the owner.
(f) Observation of Safety Precautions and procedures
as per site requirement complete as per direction of EIC. | 12 | per month | 20,700 ₹2.5 L |
| 1.02 | Cleaning and desilting of gully trap chamber, including removal of
rubbish mixed with earth etc. and disposal of same, all as per the
direction of Engineer-in-charge. as & when required | 64 | Each | 4,000 ₹2.6 L |
| 1.03 | Cleaning of chocked sewer line by diesel running vehicle mounting
hydraulic operated high pressure suction cum jetting sewer cleaning
machine fitted with pump having 4000 litres suction capacity and
6000 litres water jetting tank capacity including skilled operator,
supervising engineer etc. for cleaning and partial desilting of manholes
and dechocking of sewer lines. Dechocking and flushing of sewer
line from one manhole to another by high pressure jetting system of
2200 PSI for sewer line from 150mm dia upto 300mm as & when required | 846.14 | meter | 301 ₹2.5 L |
| 1.04 | Cleaning of under ground sump, Over Head R.C.C. Tank ( independent
staging) including disposal of slit and rubbish, all as per direction of
Engineer-in-Charge. The cleaning shall consist following operations:-
(i) Tank shall be emptied of water by pumping & bottom shall be
cleaned of silt and other deposits.
(ii) Entire surface area of the sump shall then scrubbed thoroughly
with wire brush etc. and pressure washed with water.
(iii) Chlorination of RCC internal surface by liquid chlorine.
(iv) The treated surface shall be dried using air jetting and all loose
particles shall be removal from the surface.
(v) Finally the surface shall be treated with ultraviolet radiation etc.
as per direction of Engineer-in-Charge. as & when required | 1,299.87 | sqm | 250 ₹3.2 L |
Tender Value
₹13.3 L
EMD Value
₹26,685
Closing Date
12 May 2026, 2:00 pmClosed
Regional Director
Sports Authority of India, Sarojini Nagar, Lucknow
OPERATION and MAINTENANCE OF WATER TREATMENT PLANT (WTP) including cleaning of sewer chambers, water tanks at SAI NSRC Lucknow
2026_SAI_905331_1
SAI/LKO/O and M- WTP/2026-2027/CN-117910
Open Tender
Civil Works
Sports Authority of India, Sarojini Nagar
Please refer Tender documents.
3 documents required · 3 mandatory
₹0
₹26,685
Yes
26 May 2026
22 Apr 2026
13 May 2026
22 Apr 2026
12 May 2026
22 Apr 2026
22 Apr 2026 - 8 May 2026
| Sl No | Description | Qty | Unit | Est. Rate | Est. Amount | Item Code |
|---|---|---|---|---|---|---|
| 1.01 | Operation & maintenance of water treatment plant at 300bedded hostel withoperation & maintenance of the WTP shall be done to ensure smooth running, efficiently and economically. The effluent from the plant shall meet the desired limit as specified in IS : 10500 & CPHEEO manual of water supply & treatment, whichever is more stringent.
The basic requirements as listed below are to be followed by the Contractor before commissioning & during Operation & Maintenance period of the WTP :
(a) A set of recommended spares for trouble free operation of the Electrical, Mechanical, instrumentation equipments are to be kept by the agency at his cost.
(b) Proper and adequate stock of tools & plants and items like gland packing belts, lubricating oils, greases are to be kept by the agency at his cost.
(c) Servicing schedule of preventive maintenance as suggested by the manufacturer has to be strictly adhered to.
(d) Training of Agency’s operators in proper operating procedures & maintenance practice.
(e) Compliance with agreed operation & maintenance schedules including logging of all activities to the due satisfaction of the owner.
(f) Observation of Safety Precautions and procedures
as per site requirement complete as per direction of EIC. | - | per month | - | - | BI01010001010000000000000515BI0100001113 |
| 1.02 | Cleaning and desilting of gully trap chamber, including removal of
rubbish mixed with earth etc. and disposal of same, all as per the
direction of Engineer-in-charge. as & when required | - | Each | - | - | BI01010001010000000000000515BI0100001114 |
| 1.03 | Cleaning of chocked sewer line by diesel running vehicle mounting
hydraulic operated high pressure suction cum jetting sewer cleaning
machine fitted with pump having 4000 litres suction capacity and
6000 litres water jetting tank capacity including skilled operator,
supervising engineer etc. for cleaning and partial desilting of manholes
and dechocking of sewer lines. Dechocking and flushing of sewer
line from one manhole to another by high pressure jetting system of
2200 PSI for sewer line from 150mm dia upto 300mm as & when required | 1 | meter | - | - | BI01010001010000000000000515BI0100001115 |
| 1.04 | Cleaning of under ground sump, Over Head R.C.C. Tank ( independent
staging) including disposal of slit and rubbish, all as per direction of
Engineer-in-Charge. The cleaning shall consist following operations:-
(i) Tank shall be emptied of water by pumping & bottom shall be
cleaned of silt and other deposits.
(ii) Entire surface area of the sump shall then scrubbed thoroughly
with wire brush etc. and pressure washed with water.
(iii) Chlorination of RCC internal surface by liquid chlorine.
(iv) The treated surface shall be dried using air jetting and all loose
particles shall be removal from the surface.
(v) Finally the surface shall be treated with ultraviolet radiation etc.
as per direction of Engineer-in-Charge. as & when required | 1 | sqm | - | - | BI01010001010000000000000515BI0100001116 |
stage.html
html • 0.03 MB
tech_bid_open.pdf
tech_eval.pdf
fin_bid_open.pdf
boq_comp_chart.xlsx
xlsx
Tap a document below to read it instantly. You can also download everything as a ZIP if you prefer.
details.html
html • 0.03 MB
Tendernotice_1.pdf
PDF • 0.28 MB
Tenderdocument.pdf
Tender Documents • 1.72 MB
BOQ_951593.xls
BOQ • 0.25 MB
Download all tender documents and submit your bid