| # | Company | Amount | Rank | Status |
|---|---|---|---|---|
| 1 | L1₹70 LAdmitted-Finance | ₹70 L | L1 | Admitted-Finance |
| 2 | L2₹70.7 LAdmitted-Finance | ₹70.7 L | L2 | Admitted-Finance |
| Sl No | Description | Qty | Unit | NIRANJAN HOJAI L1 | BORDIP LANGTHASA L2 |
|---|---|---|---|---|---|
| 1.00 | Earthwork in excavation for structures as per drawing and technical specification Clause 305.1 including setting out, construction of shoring and bracing, removal of stumps and other deleterious material and disposal upto a lead of 50m, dressing of sides and bottom and backfilling in trenches with excavated suitable material. (ii)Ordinary rock (not requiring blasting)Upto 3.00m depth. | 629.41 | Cum | 216.94 ₹1.4 L | 225 ₹1.4 L |
| 2.00 | Loading of Earth, Sand, Moorum, Manure, Fly ash, by manual means including lead upto 30M. | 629.28 | Cum | 67.71 ₹42,608.55 | 70 ₹44,049.60 |
| 3.00 | UnLoading of Earth, Sand, Moorum, Manure, Fly ash, by manual means including lead upto 30M. | 629.28 | Cum | 42.13 ₹26,511.57 | 45 ₹28,317.60 |
| 4.00 | Haulage excluding Loading & Unloading : Haulage of materials by tipper excluding cost of loading, unloading and stacking.
Case-I:Surfaced Road =15.00km
@Rs.14.90/m³/km=Rs.223.50/cum | 629.28 | Cum | 265.97 ₹1.7 L | 270 ₹1.7 L |
| 5.00 | Providing concrete for plain/ reinforced concrete in open foundations complete as per drawings and technical specifications Clause 802, 803, 1202 & 1203(A)With crushed Stone(I)PCC Gr M-10 ;Nominal mix 1:3:6 | 29.41 | Cum | 6,400.77 ₹1.9 L | 6,500 ₹1.9 L |
| 6.00 | Supplying, fitting and placing TMT (Fe-500 D) reinforcement bar (From Primary Producer: TATA/ SAIL/ Esser Steel/ Jindal steel/Shyam steel/RINL) in substructrue complete as per drawings and technical specification Clauses 1002, 1005, 1010 & 1202 | 19.73 | tonne | 67,084.7 ₹13.2 L | 68,000 ₹13.4 L |
| 7.00 | Plain/reinforced cement concrete in substructure complete as per drawings and technical specification Clauses 802, 804, 805, 806, 807, 1202 ans 1204(A)With Crushed Stone(IV)RCC Gr M-25 (i)For height upto 5 m | 382.94 | Cum | 8,416.87 ₹32.2 L | 8,500 ₹32.5 L |
| 8.00 | Providing weepholes in brick masonry/stone masonry, plain/ reinforced concrete abutment, wing rall, return wall,with 100mm dia AC pipe extending through full width of the structure with slope of 1(V):20(H) towards drawing face complete as per drawing and technical specification. | 355 | Each | 141.85 ₹50,356.75 | 145 ₹51,475 |
| 9.00 | Providing and laying filter media with granular crushed aggregates as per specification to a thickness of not less than 600 mm with smaller size towards the soil and bigger size towards the wall and providing over the entire surface behind abutment, wing wall, return wall to the full height, compacted to firm condition complete as per drawing and technical specification Clause 1204.3.8 | 820.8 | Cum | 2,183.65 ₹17.9 L | 2,190 ₹18.0 L |
| 10.00 | Plastering with Cement Mortar (1:4), 15 mm thick on brickwork in substructure as per technical specification clauses 613.4 & 1204 | 319.2 | Sqm | 154.19 ₹49,217.45 | 160 ₹51,072 |
Tender Value
₹70 L
EMD Value
₹1.4 L
Closing Date
8 Jan 2026, 2:00 pmClosed
Chief Engineer,PWRD
O/o the Chief Engineer PWRD,Assam,Guwahati-03
Recovery and Reconstruction of Haflong Mission Road under NDRF(PDNA-2022) for the year 2025-26.
2025_PWD_49668_5
CE/Commn/192/2025-26/9
Open Tender
Civil Works – Roads
30 days
Dima Hasao
Please refer Tender documents.
4 documents required · 4 mandatory
₹1,400
₹1.4 L
Yes
O/o the Chief Engineer PWRD,Assam,Guwahati-03
29 Jan 2026
26 Dec 2025
8 Jan 2026
26 Dec 2025
8 Jan 2026
26 Dec 2025
26 Dec 2025 - 8 Jan 2026
2 Jan 2026
Earthwork in excavation for structures as per drawing and technical specification Clause 305.1 including setting out, construction of shoring and bracing, removal of stumps and other deleterious material and disposal upto a lead of 50m, dressing of sides and bottom and backfilling in trenches with excavated suitable material. (ii)Ordinary rock (not requiring blasting)Upto 3.00m depth.
Loading of Earth, Sand, Moorum, Manure, Fly ash, by manual means including lead upto 30M.
UnLoading of Earth, Sand, Moorum, Manure, Fly ash, by manual means including lead upto 30M.
Haulage excluding Loading & Unloading : Haulage of materials by tipper excluding cost of loading, unloading and stacking. Case-I:Surfaced Road =15.00km @Rs.14.90/m³/km=Rs.223.50/cum
Providing concrete for plain/ reinforced concrete in open foundations complete as per drawings and technical specifications Clause 802, 803, 1202 & 1203(A)With crushed Stone(I)PCC Gr M-10 ;Nominal mix 1:3:6
Supplying, fitting and placing TMT (Fe-500 D) reinforcement bar (From Primary Producer: TATA/ SAIL/ Esser Steel/ Jindal steel/Shyam steel/RINL) in substructrue complete as per drawings and technical specification Clauses 1002, 1005, 1010 & 1202
Plain/reinforced cement concrete in substructure complete as per drawings and technical specification Clauses 802, 804, 805, 806, 807, 1202 ans 1204(A)With Crushed Stone(IV)RCC Gr M-25 (i)For height upto 5 m
Providing weepholes in brick masonry/stone masonry, plain/ reinforced concrete abutment, wing rall, return wall,with 100mm dia AC pipe extending through full width of the structure with slope of 1(V):20(H) towards drawing face complete as per drawing and technical specification.
Providing and laying filter media with granular crushed aggregates as per specification to a thickness of not less than 600 mm with smaller size towards the soil and bigger size towards the wall and providing over the entire surface behind abutment, wing wall, return wall to the full height, compacted to firm condition complete as per drawing and technical specification Clause 1204.3.8
Plastering with Cement Mortar (1:4), 15 mm thick on brickwork in substructure as per technical specification clauses 613.4 & 1204
Please Enable Macros to View BoQ information
stage.html
html • 0.03 MB
tech_eval.pdf
boq_comp_chart.xlsx
xlsx
Tap a document below to read it instantly. You can also download everything as a ZIP if you prefer.
details.html
html • 0.03 MB
Tendernotice_1.pdf
PDF • 2.76 MB
Tendernotice_2.pdf
PDF • 8.23 MB
Tendernotice_3.pdf
PDF • 0.56 MB
BOQ_78899.xls
BOQ • 1.27 MB
Download all tender documents and submit your bid