EXECUTIVE ENGINEER
Head Office at CMRL Administrative Building , Poonamallee High Road, Koyambedu, Chennai-107
Special repairs to loading platform in Godown No.2 and Construction of compound wall in South side of Godown campus at Panjetty Village at Ponneri Taluk in Thiruvallur District.
2024_TCSC_477783_1
18/CED6/Panjetty/2024
Open Tender
Civil Works
Lump-sum
90 days
Ponneri
Please refer Tender documents.
6 documents required · 6 mandatory
₹0
₹18,250
28 Oct 2024
28 Aug 2024
11 Sept 2024
28 Aug 2024
10 Sept 2024
28 Aug 2024
Amount
CIVIL WORK
EARTH WORK excavation for foundation in all classes of soils and subsoils to full depth, as may be directed except in hard rock, requiring blasting including initial leads and lifts and refilling the sides of foundation with excavated earth in 150mm layers well watered rammed and consolidated including depositing surplus earth with in the Godown or inside compound in places shown with initial leads and lifts, clearing, leveling site, shoring, strutting, baling of water wherever necessary etc., complete complying with standard specification and as directed.
Supplying and filling in foundation and basement with clean M.SAND in layers of 150mm thick, well watered, rammed and consolidated including watering etc., complete complying with standard specifications and as directed.
CEMENT CONCRETE 1:5:10(one cement, five sand and ten aggregate)using 40mm gauge hard broken granite stone jelly for foundation including de-watering, side shuttering , strutting, wherever necessary including curing etc., complete complying with standard specifications and as directed.
Reinforcement Cement Concrete 1:1 ½ :3 ( one cement, one and half sand, three aggregate) using 20mm of hard broken granite stone for all RCC works using machine for mixing concrete excluding cost of centering, Strutting, shuttering, and fabrication of reinforcement and placing the grills in position etc., but including finishing and curing etc., complete complying with standard specifications and as directed. In foundation and basement
In Ground floor upto 4.50M height above basement.
Providing FORM WORK for centering the soffits of all reinforcement concrete work including strutting to the required (3 metre) height with mild-steel sheets of size 90cmx60cm 10 gauge stiffened with welded mild steel angles of size 25mmx25mmx3mm laid with country wood joist of average of size 10cmx6.50cm at about 90cm centres with casurina props of 13cm dia at 75cm centre to centre with all nails coir,wedges complete and removing the form work after necessary curing period as directed by the corporations officers. The rates should inclusives of cutting , bending, welding , charges of M.S sheets, M.S. angles etc., Complete Column footing, Plinth beam , top tie beam etc.,
Rectangular beams and floor slabs, tie beams, lintels, landing slab, loft etc.,
Column and sunshade
Supplying and fixing in position 100mm x 50mm x 9.4 kg channel for the face of RAT GUARD EDGING SLAB with MS bolts 16mm dia 45cm long at 2m centres forming protection to the loading platform finishing in flush with the slab with C.M. 1:3(one cement and three sand) etc., complete including painting the exposed surface of MS channel with two coats of ANTI-CORROSIVE METALLIC PAINT over one coat red oxide primer etc., complete complying with standard specification and as directed
Supplying, fabricating and placing in position MS/RTS grills for reinforcement for all R.C.C. works including cost of steel, labour for straightening, bending, cranking, tying grills with 18 gauge galvanized binding wire and placing grills in position complete complying with standard specification and as directed.
BRICK WORK in cement mortar 1:5(One cement, Five sand)using best quality IInd Class Chamber burnt Bricks of size 9”x4 3/8 x2 3/4’ for walls including cost of scaffolding curing , finishing etc., complete complying with standard specifications and as directed. In foundation and basement
In ground floor upto 4.50M height above basement
Supplying and fixing of Bitumen Pad of 12mm thick for Expansion Joints includes cost of Materials, labour charges etc., complete complying with standard specification and as directed by the departmental officers.
PLASTERING with cement mortor 1:5 (one cement and five sand) 12mm thick including cost of scaffolding, finishing, curing etc., complete complying with standard specification and as directed.
PLASTERING with cement mortor 1:3 (one cement and three sand) 12mm thick including cost of scaffolding, finishing, curing etc., complete complying with standard specification and as directed.
Painting the walls with two coats of cement paint of first class approved quality and colour over a priming coat including thorough scrapping, clean removal of dirt, and including necessary plaster of paris putty, wherever required etc., complete complying with standard specification and as directed.
G Murali (BID ID -1128558)
stage.html
html • 0.04 MB
tech_eval.pdf
fin_eval.pdf
aoc.pdf
finance_567448.pdf
boq_comp_chart.xlsx
xlsx
Tap a document below to read it instantly. You can also download everything as a ZIP if you prefer.
details.html
html • 0.03 MB
Download all tender documents and submit your bid
Disclaimer: TenderKart has made every reasonable effort to ensure that the information on this page is accurate and authentic, however it cannot be held liable for any third-party claims or losses or any damages. TenderKart makes no warranty, expressed or implied, as to the results obtained from the use of this information. If you notice any error or omission, please let us know at .