Loading…
Loading…
| # | Company | Amount | Rank | Status |
|---|---|---|---|---|
| 1 | L1₹33.5 LAccepted-AOC | ₹33.5 L | L1 | Accepted-AOC lowest |
| 2 | L2₹34.0 L+₹55,236.81 (1.65%)Rejected-Finance 238 5A PURANI P A C COLONY ASHOK NAGAR ETAWAH | ₹34.0 L+₹55,236.81 (1.65%) | L2 | Rejected-Finance L2 Higher Rate Quoted |
| 3 | L3₹34.2 L+₹72,626.72 (2.17%)Rejected-Finance GRAM PO DUDHI SONBHADRA U P | ₹34.2 L+₹72,626.72 (2.17%) | L3 | Rejected-Finance L3 Higher Rate Quoted |
| 4 | Not Admitted-Fee/PreQual/Technical | - | - | Not Admitted-Fee/PreQual/Technical Others-Contractor requested to reject his bid. as per his application he is busy in other work, by mistake he has submitted his bid. also told that he is unable to do work. |
| 5 | Not Admitted-Fee/PreQual/Technical GRAM PO NAKHERA DISTRICT MIRZAPUR | - | - | Not Admitted-Fee/PreQual/Technical Others-Contractor requested to reject his bid. as per his application his health is not good so due to his health issue he is unable to do work. |
| Sl No | Description | Qty | Unit | PANKAJ KUMAR GUPTA L3 | RAJESH SINGH L2 | M/S PARWATI CONSTRUCTION L1 |
|---|---|---|---|---|---|---|
| 1.00 | Dismantling of Damaged stone boulder & stacking with all lead & lift including all cost of labours, T&P, all taxes for proper completion of work. | 520.18 | M2 | 87.62 ₹45,578.17 | 87.17 ₹45,344.09 | 85.76 ₹44,610.64 Lowest |
| 2.00 | E.W. in benching on top, U/s & D/s of embankment in all type of soil with all lead & lift including all cost of labours, T&P, all taxes for proper completion of work. | 1,102.5 | M3 | 75.93 ₹83,712.83 | 75.55 ₹83,293.88 | 74.32 ₹81,937.8 Lowest |
| 3.00 | E.W. in embanment on top, U/S & D/S in all type of soil with all lead & lift including all cost of labours, T&P, all taxes for proper completion of work. 1) By Manual Lead upto 100 M total lead 10% | 1,537.69 | M3 | 108.6 ₹1,66,993.13 | 108.05 ₹1,66,147.4 | 106.3 ₹1,63,456.45 Lowest |
| 4.00 | ii) By Manual Lead upto 210 M total lead 15% | 2,306.53 | M3 | 144.99 ₹3,34,423.78 | 144.25 ₹3,32,716.95 | 141.91 ₹3,27,319.67 Lowest |
| 5.00 | iii) By Manual Lead upto 300 M total lead 20% | 3,075.38 | M3 | 162.81 ₹5,00,702.62 | 161.98 ₹4,98,150.05 | 159.35 ₹4,90,061.8 Lowest |
| 6.00 | IV) By Manual Lead upto 610 M total lead 55% | 8,457.28 | M3 | 216.27 ₹18,29,055.95 | 215.17 ₹18,19,752.94 | 211.68 ₹17,90,237.03 Lowest |
| 7.00 | Laying 150mm thick stone Kattal with all lead & lift including all cost of Materials, labours, T&P, all taxes for proper completion of work. | 205.33 | M3 | 1,240.17 ₹2,54,644.11 | 1,233.91 ₹2,53,358.74 | 1,213.87 ₹2,49,243.93 Lowest |
| 8.00 | Supplying and laying 230 mm thick stone Boulder with all lead & lift including all cost of Materials, labours, T&P, all taxes for proper completion of work. | 94.45 | M3 | 1,679.73 ₹1,58,650.5 | 1,671.25 ₹1,57,849.56 | 1,644.1 ₹1,55,285.25 Lowest |
| 9.00 | Supplying & Laying 230mm thick old stone Boulder over Laid Stone Kattal with all lead & lift including all cost of Materials, labours, T&P, all taxes for proper completion of work. | 220.39 | M3 | 217.8 ₹48,000.94 | 216.7 ₹47,758.51 | 213.18 ₹46,982.74 Lowest |
Tender Value
Refer Docs
EMD Value
₹70,000
Closing Date
4 Jan 2022, 3:00 pmClosed
EE ICD Robbertsganj
EE ICD Irrigation Coloney Bdhauli Robbertsganj
RESTORATION OF EMBANKMENT, U/S, D/S SLOPE WITH BOULDER PITCHING OF CHERUI BUNDHI FROM CH. KM 1.020 TO KM 1.510 IN NAGWA BLOCK OF DISTRICT SONEBHADRA LOT-1
2021_UPIDC_667526_1
Tender Notice No-4-EEICD-2021-22
Open Tender
Civil Works
Item Rate
90 days
SONEBHADRA
Please refer Tender documents.
2 documents required · 2 mandatory
₹300
₹70,000
20 Jul 2026
30 Dec 2021
4 Jan 2022
30 Dec 2021
4 Jan 2022
30 Dec 2021
Amount
Dismantling of Damaged stone boulder & stacking with all lead & lift including all cost of labours, T&P, all taxes for proper completion of work.
E.W. in benching on top, U/s & D/s of embankment in all type of soil with all lead & lift including all cost of labours, T&P, all taxes for proper completion of work.
E.W. in embanment on top, U/S & D/S in all type of soil with all lead & lift including all cost of labours, T&P, all taxes for proper completion of work. 1) By Manual Lead upto 100 M total lead 10%
ii) By Manual Lead upto 210 M total lead 15%
iii) By Manual Lead upto 300 M total lead 20%
IV) By Manual Lead upto 610 M total lead 55%
Laying 150mm thick stone Kattal with all lead & lift including all cost of Materials, labours, T&P, all taxes for proper completion of work.
Supplying and laying 230 mm thick stone Boulder with all lead & lift including all cost of Materials, labours, T&P, all taxes for proper completion of work.
Supplying & Laying 230mm thick old stone Boulder over Laid Stone Kattal with all lead & lift including all cost of Materials, labours, T&P, all taxes for proper completion of work.
RAJESH SINGH
PANKAJ KUMAR GUPTA
stage.html
html • 0.05 MB
tech_eval.pdf
fin_bid_open.pdf
boq_comp_chart.xlsx
xlsx
fin_eval.pdf
aoc.pdf
Tap a document below to read it instantly. You can also download everything as a ZIP if you prefer.
details.html
html • 0.03 MB
Download all tender documents and submit your bid
Disclaimer: TenderKart has made every reasonable effort to ensure that the information on this page is accurate and authentic, however it cannot be held liable for any third-party claims or losses or any damages. TenderKart makes no warranty, expressed or implied, as to the results obtained from the use of this information. If you notice any error or omission, please let us know at .