Tender ID
Eligibility, documents, scope and key termsEligibility, required documents, scope of work and key terms of this tender, in one click.
| # | Company | Amount | Rank | Status |
|---|---|---|---|---|
| 1 | L1₹19.1 LAccepted-AOC MANDI HIMACHAL PRADESH | L1 | Accepted-AOC Awarded | |
| 2 | L2₹22.0 L+₹49,904 (2.32%)Rejected-Finance | L2 | Rejected-Finance 2nd Lowest | |
| 3 | L3₹22.2 L+₹73,980 (3.44%)Rejected-Finance | L3 | Rejected-Finance 3rd Lowest |
Tender Value
Refer Docs
EMD Value
₹47,800
Closing Date
30 Jun 2021, 4:00 pmClosed
Eligibility, documents, scope and key termsEligibility, required documents, scope of work and key terms of this tender, in one click.
Executive Engineer Division No-IHPPWD Shimla-3
Executive Engineer Division No-IHPPWD Shimla-3
Digging of road from Shamshanghat way to Dhalli Chowk on Sanjauli Dhalli Bye Pass Road
2021_PWD_48779_8
SD-I-CTR-Tender-4016 dt 3-6-2021
Open Tender
Civil Works
Item Rate
60 days
Shimla
AS per SBD
14 documents required · 14 mandatory
₹500
₹47,800
23 Jan 2023
23 Jun 2021
1 Jul 2021
23 Jun 2021
30 Jun 2021
23 Jun 2021
75 days
Amount
Providing and laying in position cement concrete of specified grade excluding the cost of centering and shuttering - All work up to plinth level including carriage of materials in all leads and lifts as per directions of the Engineer-in-Charge. (i) 1:2:4 (One cement : two coarse sand) : four graded stone aggregate 20 mm(twenty milimetre) nominal size)
Providing and laying cement concrete in retaining walls, return walls, walls (any thickness) including attached pilasters, columns, piers, abutments, pillars, posts, struts, buttresses, string or lacing courses, parapets, coping, bed blocks, anchor blocks, plain window sills, fillets, sunken floor etc., up to floor five level, excluding the cost of centering, shuttering and finishing including carriage of materials in all leads and lifts as per the directions of the Engineer-in-Charge. (i)1:3:6 (One cement : three coarse sand) : Six graded stone aggregate 20 mm (Twenty milimetre) nominal size)
Earth work in excavation by mechanical means (Hydraulic excavator) / manual means in foundation trenches or drains (not exceeding 1.5 m (One point five metre) in width or 10 sqm (ten Square Metre)on plan) in all kinds of soil. including dressing of sides and ramming of bottoms including setting out, construction of shoring and bracing, removal of stumps and other deleterious materials and disposal in all leads and lifts including dressing of sides and bottom and back filling in trenches with excavated suitable materials. All work of rock cutting by blasting shall be carried out by taking all necessary precautions against soil erosion damage to hill side water pollution etc. and to protect stability of hill side rock shall be excavated with chiseling and wedging out rock (where blasting is prohibited) all earth work in cutting/ excavation including rock excavation shall be carried out true to lines grades, side slopes, width , camber super elevation and level as shown on the drawings or as directed by the Engineer-in-charge hauling and stacking of materials useful for construction at suitable sites and safe disposal of unsuitable cut materials in specified dimension or as directed by the Engineer-in-Charge. If the foundation of the structure is in an area with stagnant water or water is met with in the excavation due to spring seepage rain and other causes it shall be remove by suitable diversion bailing out or pumping as directed and the area of the foundation or embankment shall be kept dry. All the surplus excavated earth to be dumped at dumping site(dumping sites will be arranged by the contractor on his own cost).Any loss to the public or private property during the course of excavation shall be the sole responsibility of the contractor which shall have to be dully compensated by him at his on cost in all cases. including carriage of materials in all leads and lifts as per the directions of the Engineer-in-Charge.
White washing with lime to give an even shade including carriage of materials in all leads and lifts as per directions of the Engineer-in-Charge. (i) Old work (two or more coats)
Clearing jungle including uprooting of rank vegetation, grass, brush wood, trees and saplings of girth up to 30 cm(thirty centimetre) measured at a height of 1 m above ground level and removal of rubbish up to a distance of 50 m(fifty metre) outside the periphery of the area cleared including carriage of materials in all leads and lifts as per directions of the Engineer-in-Charge.
20 mm (twenty milimetre)cement plaster of mix including carriage of materials in all leads and lifts as per directions of the Engineer-in-Charge.(i)1:4 (One cement: four fine sand )
BHARAT SINGH CHAUHAN
Suresh Vekta
stage.html
html • 0.05 MB
tech_bid_open.pdf
tech_eval.pdf
fin_bid_open.pdf
boq_comp_chart.xlsx
xlsx
fin_eval.pdf
aoc.pdf
Tap a document below to read it instantly. You can also download everything as a ZIP if you prefer.
details.html
html • 0.03 MB
Download all tender documents and submit your bid
Disclaimer: TenderKart has made every reasonable effort to ensure that the information on this page is accurate and authentic, however it cannot be held liable for any third-party claims or losses or any damages. TenderKart makes no warranty, expressed or implied, as to the results obtained from the use of this information. If you notice any error or omission, please let us know at .