| # | Company | Amount | Rank | Status |
|---|---|---|---|---|
| 1 | L1₹14.1 CrAccepted-AOC SAMANTARAPUR PO JARADAGADA PS JARADA DIST GANJAM PIN 761005 | GANJAM | ODISHA | 761005 | ₹14.1 Cr Quoted ₹11.9 Cr | L1 | Accepted-AOC 1st lowest |
| 2 | L2₹11.9 Cr+₹3.2 L (0.27%)Rejected-Finance | ₹11.9 Cr+₹3.2 L (0.27%) | L2 | Rejected-Finance other than 1st lowest |
| 3 | L2₹11.9 Cr+₹3.2 L (0.27%)Rejected-Finance AT PO BHUBANESWAR LANE 4 NAYAPALLI NUASAHI WARD NO 34 DIST KHURDA ODISHA | BHUBANESWAR | KHURDA | ODISHA | ₹11.9 Cr+₹3.2 L (0.27%) | L2 | Rejected-Finance other than 1st lowest |
| 4 | L2₹11.9 Cr+₹3.2 L (0.27%)Rejected-Finance BALIGADIA PO PS JANKIA DIST KHORDHA | JANKIA | KHORDHA | ODISHA | ₹11.9 Cr+₹3.2 L (0.27%) | L2 | Rejected-Finance other than 1st lowest |
Tender Value
₹13.3 Cr
EMD Value
₹13.3 L
Closing Date
17 Jun 2025, 5:00 pmClosed
Executive Engineer (Central Tender Cell)
Executive Engineer (Central Tender Cell),BMC,ICOMC TOWER
Construction of drain from ISKON NH-16 to Drain-10 via Behera Sahi
2025_ORULB_114123_2
BMC-EE-Tender Cell-19/2025-26 Dt. 30.05.2025
Open Tender
Civil Works - Others
Percentage
180 days
BMC AREA
Please refer Tender documents.
2 documents required · 2 mandatory
₹10,000
₹13.3 L
Yes
UG floor,Office Chamber of EE Central Tender Cell,
22 Jan 2026
3 Jun 2025
18 Jun 2025
3 Jun 2025
17 Jun 2025
3 Jun 2025
3 Jun 2025 - 9 Jun 2025
10 Jun 2025
This is a percentage-rate BOQ. The schedule below shows estimated quantities and rates. Bidders quote a single percentage above or below the total estimated cost.
| Sl No | Description | Qty | Unit | Est. Rate | Est. Amount |
|---|---|---|---|---|---|
| 1 | Dismantling and removing RC.C. columns beams slab staircase landing lintels including stacking the useful materials for reuse and removing the debris within 50m lead as per the direction of the engineer in charge. | 978 | Cum | 1,696.95 | ₹16,59,618.57 |
| 2 | Dismantlling and removing cement concrete including stacking the useful materials for re-use and removing debries within 50mtr lead as per the direction of the engineer in charge | 1,019.5 | Cum | 859 | ₹8,75,752.42 |
| 3 | Earth work excavation in Hard soil using two cum Bucket Hydraluc Excavator with all leads and lifts and transpotation of ecavated matiral by mechcanical means and direction of Engg -in-charge. | 920.02 | Cum | 240.75 | ₹2,21,494.19 |
| 4 | Excavation, loading, unloading and carriage by mechanical means of all kinds of soil including stoney earth, gravel and moorum etc. inter-spread with boulder upto 1/2cum size with all leads, lifts including trimming of slope and bed to design section and depositing the excavated materials away from work site & within a initial lead of 5km. from the place of excavation as per the specification and as directed by the Engineer-in-Charge. | 17,989.18 | Cum | 218.5 | ₹39,30,636.7 |
| 5 | Conveyance of excavated materials such as rough stone, metal, khoa, chips, sand, surki, quarry rubbish, moorum, laterite stone washed gravel, flyash and earth away from the work site by mechanical means including loading and unloading and depositing the same within 5km truck lead as per the direction of the Engineer in charge. | 1,850 | Cum | 160.68 | ₹2,97,258 |
| 6 | Filling in foundation with sand well watered & rammed including cost, conveyance, royalty & taxes etc. complete of all materials to work site as the specification approved by the department and direction of Engineer in charge. | 3,337.08 | Cum | 519.79 | ₹17,34,582.86 |
| 7 | Concrete (1.3:6) with 4cm size Hard Granite Crusher Broken metal including all cost, conveyance, royalty & taxes etc.compete of all materials to work site as per approved by the e eRMdepartment & direction of Engineer-in-charge | 1,520.11 | Cum | 6,160.3 | ₹93,64,317.83 |
| 8 | Rigid Smooth centerinmg and Shuttering including false work and removing the same after casting etc. complete. Drain and Culvert. R.C.C. Foundation, Plinth Band, Footings, Bases of Columns, Mass Concrete & Precast Slabs etc. in Ground Floor. | 2,118.98 | sqm | 250.28 | ₹5,30,338.09 |
| 9 | Rigid Smooth centerinmg and Shuttering including false work and removing the same after casting etc. complete. Drain and Culvert. R.C.C. Walls and Fins including attached Pillasters in Ground Floor | 17,139.2 | sqm | 1,074.4 | ₹1,84,14,356.48 |
| 10 | Rigid Smooth centerinmg and Shuttering including false work and removing the same after casting etc. complete. Drain and Culvert. R.C.C. floor and roofslab, landings balconies, projecting sun-shades and chajjas upto 4.30 mtr height. | 1,370 | sqm | 762.1 | ₹10,44,077 |
stage.html
html • 0.05 MB
tech_bid_open.pdf
tech_eval.pdf
fin_bid_open.pdf
boq_comp_chart.xlsx
xlsx
fin_eval.pdf
aoc.pdf
Tap a document below to read it instantly. You can also download everything as a ZIP if you prefer.
details.html
html • 0.03 MB
BOQ_541918.xls
BOQ • 0.24 MB
172184219.pdf
Tender Documents • 0.78 MB
172184222.html
Tender Documents • 0.05 MB
Download all tender documents and submit your bid
Disclaimer: TenderKart has made every reasonable effort to ensure that the information on this page is accurate and authentic, however it cannot be held liable for any third-party claims or losses or any damages. TenderKart makes no warranty, expressed or implied, as to the results obtained from the use of this information. If you notice any error or omission, please let us know at .