Loading…
Loading…
| # | Company | Amount | Rank | Status |
|---|---|---|---|---|
| 1 | L1₹60.2 LAccepted-AOC | L1 | Accepted-AOC L1 | |
| 2 | L2₹65.9 L+₹5.6 L (9.35%)Rejected-AOC | L2 | Rejected-AOC L2 | |
| 3 | L3₹71.0 L+₹10.8 L (17.9%)Rejected-AOC | L3 | Rejected-AOC L3 | |
| 4 | L4₹72.0 L+₹11.8 L (19.6%)Rejected-AOC | L4 | Rejected-AOC L4 |
Tender Value
₹66.2 L
EMD Value
₹1.3 L
Closing Date
22 Dec 2021, 5:00 pmClosed
Deputy Conservator of Forests (WL),DNH,Silvassa
Deputy Conservator of Forests (WL),DNH,Silvassa
Construction of RCC Compound wall for Forest Rest House at Khanvel.
2021_UTDNH_5678_1
E Tender Notice No 11 OF 2021-22 (WL)
Open Tender
Civil Works - Buildings
Item Rate
60 days
UT OF DNH
As per NIT refer
3 documents required · 3 mandatory
₹1,000
Deputy Conservator of Forests (WL),DNH,Silvassa
₹1.3 L
1 Jan 2022
8 Dec 2021
23 Dec 2021
8 Dec 2021
22 Dec 2021
8 Dec 2021
Amount
Dismentling G.I. pipes G.S.W.pipes abd A.C. rain water pipes with fittings and clamps including stacking the materials with all lead and lift ( for any dia, of pipe)
Dismentling steel work including distempering and stacking the materials with all lead and lift.
Demolition and disposal of unserviceable materials with all lead and lift.(i) Cement concrete.
Excavationfor foundation upto 1.5 m depth including sorting out and stacking of useful materials and disposing off the excavated stuff upto 50 Meter lead.(A) Loose or soft soil
Providing material & labour for filling in foundation and plinth with RUBBLE under floors including filling gravel in gaps and consolidating deposited layers by ramming water etc. complete.
Providing material & labour for laying cement concrete 1:2:4 (1- Cement : 2- Coarse sand : 4- graded stone aggregates 20 mm nominal size) and curing complete excluding cost of formwork in (A) Foundation & plinth.
Providing material & labour for laying controlled cement concrete M.200 and curing complete excluding the cost of formwork and reinforcement for reinforced concrete work in (A) Foundations, footings, Base of columns and Mass concrete.
Providing material & labour for laying controlled cement concrete M.200 and curing complete excluding the cost of formwork and reinforcement for reinforced concrete work in (C) Slabs,landing,shelves,Balconies Lintels, Beams, Girders and Cantilever upto floor two level.
Providing material & labour for formwork of sheathing steel sheets so as to give a fair finish including centering shuttering strutting and propping etc. Height of propping and centering below supporting floor to ceiling not exceeding 4 M. and removal of the same for in situ reinforced concrete and plain concrete work in. (A) Foundations Footings Bases of Columns etc. and Mass concrete .
Providing material & labour for formwork of sheathing steel sheets so as to give a fair finish including centering shuttering strutting and propping etc. Height of propping and centering below supporting floor to ceiling not exceeding 4 M. and removal of the same for in situ reinforced concrete and plain concrete work in. (A) Foundations Footings Bases of Columns etc. and Mass concrete.Providing formwork of ordinary timber planking so as to give a rough finish including centering shuttering strutting and propping etc. height of propping and centering below supporting floor to ceiling not exceeding 4 M. and removal of the same for in situ reinforced concrete and plain concrete work in. (G) Columns PillarsPosts and struts. (1) Square Rectangular Polygonal in plan .
Providing material & labour for laying controlled cement concrete M.200 and curing complete excluding the cost of formwork and reinforcement for reinforced concrete work in (D) Columns, Pillars posts and struts upto floor two level (above PL).
Providing material & labour for filling plinth with Unscreen Gravel floors including watering, ramming consolidating and dressing etc. complete.
Providing material & labour for Brick work using common burnt clay building bricks having crushing strength not less than 35 kg./Sq.Cm. Cement Mortar 1:5. (1- Cement : 5 -fine sand) for superstructure above plinth level upto floor two level & curing complete as directed.
Providing material & labour for 20mm thick sand faced cement plaster on walls upto height 10 metres above ground level consisting of 12mm thick backing coat of C.M. 1:3 (1-cement : 3-sand) and 8mm thick finishing coat of C.M. 1:1 (1-cement : 1-sand) etc. & curing complete.
Providing material & labour for fixing TMT Bar FE 500/500D reinforcement for R.C.C. work including bending, binding and placing in position complete upto floor two level
Providing material & labour for Finishing wall with weather proof exterior emulsion paint on wall surface (two coats) to give an required shape even shade after thoroughly brushing the surface to remove all dirt, and remains of loose powdered materials.etc complete.
Providing material & labour for Supplying and fixing reinforced concrete heavy duty non-pressure pipes with collars for culverts including setting and joining the pipes in C.M. 1:2 watering and laying (to level or slope) of I.S. class NP2 of following internal diameters.(iii) 600mm dia.
Babariya Construction
Poojan Infrastructure
Avadh Construction
stage.html
html • 0.05 MB
tech_bid_open.pdf
tech_eval.pdf
fin_bid_open.pdf
boq_comp_chart.xlsx
xlsx
fin_eval.pdf
aoc.pdf
Tap a document below to read it instantly. You can also download everything as a ZIP if you prefer.
details.html
html • 0.03 MB
Download all tender documents and submit your bid
Disclaimer: TenderKart has made every reasonable effort to ensure that the information on this page is accurate and authentic, however it cannot be held liable for any third-party claims or losses or any damages. TenderKart makes no warranty, expressed or implied, as to the results obtained from the use of this information. If you notice any error or omission, please let us know at .