| # | Company | Amount | Rank | Status |
|---|---|---|---|---|
| 1 | L1₹106.3 CrAccepted-AOC PJB GREEN WAY 11 3RD FLOOR ASHLEY PARK M G ROAD BENGALURU 560001 KARNATAKA | BENGALURU | BENGALURU URBAN | KARNATAKA | 560001 | ₹106.3 Cr | L1 | Accepted-AOC Being L1 |
| 2 | L2₹119.3 CrRejected-Finance | ₹119.3 Cr | L2 | Rejected-Finance Being L2 |
| 3 | L3₹205.8 CrRejected-Finance GODREJ WATERSIDE TOWER NO 1 OFFICE 803 8TH FLOOR PLOT NO 5 BLOCK DP SECTOR V SALT LAKE CITY KOLKATA 700091 | KOLKATA | KOLKATA | WEST BENGAL | 700091 | ₹205.8 Cr | L3 | Rejected-Finance Being L3 |
| Sl No | Description | Qty | Unit | RNS INFRASTRUCTURE LIMITED L2 | PJB Engineers Pvt Ltd L1 | Cemindia Projects Limited L3 |
|---|---|---|---|---|---|---|
| 1.01 | Schedule A-Construction of Formation in Embankments, Cuttings including Blanketing, Ramp, ROB, Minor Bridges, RUB, ERS/Retaining Wall, Sacrificial Retaining Wall, Drains, Boundary Wall and Fencing works on both side of BSTP alignment of length 2 x 5.80 Km (Ch: 18.400 Km To Ch: 24.200 Km) (Balance Works) for BSTP Corridor & also IR Corridor and Elevated Viaduct of length 185m (24.200 To 24.385) for BSTP Corridor and other related Infrastructural works from Yeshwanthpur to Chikkabanawara including validation of Design and Stability check wherever applicable for works executed by previous contractor (excluding Station Buildings), of Corridor - 2 of Bengaluru Suburban Transport Project (BSTP)”. | 1 | Nos | 1,15,80,00,000 ₹115.8 Cr | 1,03,49,00,000 ₹103.5 Cr | 1,99,57,00,000 ₹199.6 Cr |
| 1.02 | Schedule B-Detailed Design and Engineering for all Civil Works including design validation and stability check for the work executed by previous contractor including design of Temporary & Miscellaneous works which are to be executed in Schedule-C (if any). | 1 | Nos | 1,50,00,000 ₹1.5 Cr | 80,00,000 ₹80 L | 4,27,00,000 ₹4.3 Cr |
| 1.03 | Schedule C-Miscellaneous Items for works which are not covered in Schedule A&B are to be executed under schedule of rates 2023-24 and its amendment or latest, published by Government Departments KPWD/USSOR/CPWD/ BWSSB/BESCOM/KPTCL. | 1 | Nos | 2,00,00,000 ₹2 Cr | 2,00,00,000 ₹2 Cr | 2,00,00,000 ₹2 Cr |
Updated dates
Tender Value
Refer Docs
EMD Value
₹1 Cr
Closing Date
4 Feb 2026, 3:00 pmClosed
GM Procurement KRIDE
Samparka Soudha, 1st Floor, Dr. Rajkumar Road, Opposite Orion Mall, Rajajinagar 1st Block, Bengaluru 560010
Design and Construction of Formation in Embankments, Cuttings including Blanketing, Ramp, ROB, Minor Bridges, RUB, ERS/Retaining Wall, Sacrificial Retaining Wall, Drains, Boundary Wall and fencing At-Grade Section of 5.80 Km and Ele Viaduct of 185m
2025_KRIDE_254270_1
KRIDE/BSTP/C2/PACKAGE-3/2025
Open Tender
Civil Works
548 days
Bangalore
Please refer Tender documents.
7 documents required · 7 mandatory
₹25,000
Bi-RIDE
₹1 Cr
KRIDE Office, Bangalore
13 Apr 2026
4 Nov 2025
5 Feb 2026
4 Nov 2025
4 Feb 2026
22 Dec 2025
4 Nov 2025 - 22 Nov 2025
13 Jan 2026
Schedule A-Construction of Formation in Embankments, Cuttings including Blanketing, Ramp, ROB, Minor Bridges, RUB, ERS/Retaining Wall, Sacrificial Retaining Wall, Drains, Boundary Wall and Fencing works on both side of BSTP alignment of length 2 x 5.80 Km (Ch: 18.400 Km To Ch: 24.200 Km) (Balance Works) for BSTP Corridor & also IR Corridor and Elevated Viaduct of length 185m (24.200 To 24.385) for BSTP Corridor and other related Infrastructural works from Yeshwanthpur to Chikkabanawara including validation of Design and Stability check wherever applicable for works executed by previous contractor (excluding Station Buildings), of Corridor - 2 of Bengaluru Suburban Transport Project (BSTP)”.
Schedule B-Detailed Design and Engineering for all Civil Works including design validation and stability check for the work executed by previous contractor including design of Temporary & Miscellaneous works which are to be executed in Schedule-C (if any).
Schedule C-Miscellaneous Items for works which are not covered in Schedule A&B are to be executed under schedule of rates 2023-24 and its amendment or latest, published by Government Departments KPWD/USSOR/CPWD/ BWSSB/BESCOM/KPTCL.
stage.html
html • 0.04 MB
techsummary_292648.pdf
BOQ Comparative Chart
xlsx
fin_eval.pdf
aoc.pdf
Tap a document below to read it instantly. You can also download everything as a ZIP if you prefer.
details.html
html • 0.04 MB
Tendernotice_1.pdf
PDF • 0.39 MB
C2Package3TenderDocument.rar
Tender Documents • 26.52 MB
C2Package3Tenderdrawings1.rar
Tender Documents • 35.06 MB
C2Package3Attachment3GTIReports.pdf
Tender Documents • 0.07 MB
BOQ_292648.xls
BOQ • 0.39 MB
Download all tender documents and submit your bid