| # | Company | Quoted % | Amount | Rank | Status |
|---|---|---|---|---|---|
| 1 | L1₹3.2 LAdmitted-Finance | +0.00% | ₹3.2 L | L1 | Admitted-Finance |
| 2 | L2₹3.3 L+₹8,767.57 (2.70%)Admitted-Finance | +2.70% | ₹3.3 L+₹8,767.57 (2.70%) | L2 | Admitted-Finance |
| 3 | L3₹3.4 L+₹15,262.07 (4.70%)Admitted-Finance MALIKPETH TAL MOHOL DIST SOLAPUR 413213 | MALIKPETH | SOLAPUR | MAHARASHTRA | 413213 | +4.70% | ₹3.4 L+₹15,262.07 (4.70%) | L3 | Admitted-Finance |
Tender Value
₹3.2 L
Closing Date
17 Sept 2026, 5:00 pmClosed
SARPANCH AND GRAMPANCHAYAT ADHIKARI DARFAL
GRAMPANCHAYAT DARFAL TAL-MADHA
1)Repairing Of Water supply scheme At Darphal 2)Constructing RCC Underground GutterAt Darphal.Tal.Madha Dist.Solapur.
2026_SOLAP_1337724_1
01/2026-27
Open Tender
Civil Works
Percentage
180 days
GRAMPANCHAYAT DARFAL TAL-MADHA
Please refer Tender documents.
2 documents required · 2 mandatory
₹200
Exempted
21 Sept 2026
10 Sept 2026
18 Sept 2026
10 Sept 2026
17 Sept 2026
10 Sept 2026
This is a percentage-rate BOQ. The schedule below shows estimated quantities and rates. Bidders quote a single percentage above or below the total estimated cost.
| Sl No | Description | Qty | Unit | Est. Rate | Est. Amount |
|---|---|---|---|---|---|
| 1 | 01.Repairing Of Water supply scheme At Darphal.Tal.Madha Dist.Solapur. | - | - | - | - |
| 2 | Item No. 1 :- Excavation for foundation / pipe trenches in earth soils of all types, sand, gravel and soft murum, including removing the excavated material up to a distance of 50 meters and lifts as below, stacking and spreading as directed, normal dewatering, preparing the bed for foundation and excluding backfilling, etc. complete (lift 0 to 1.5 M) For 200 mm RCC NP 2 Pipe | 243 | CUM | 165 | ₹40,095 |
| 3 | Item No. 2:- Excavation for foundation / pipe trenches in hard murum including removing the excavated material up to a distance of 50M and lifts as below, stacking and spreading as directed by Engineer-in-charge, normal dewatering, preparing the bed for foundation and excluding backfilling, etc. complete.(lift 0 to 1.5M) | 48.6 | CUM | 187 | ₹9,088.2 |
| 4 | Item No. 5:- Filling in plinth and floors murum bedding in trenches with approved murum from excavated materials from foundation in 15 cm to 20 cm layers including watering and compaction, etc. complete. | 72.9 | CUM | 92 | ₹6,706.8 |
| 5 | Item No. 6 :-Providing and supplying in standard lengths ISI mark rigid unplasticised PVC pipes suitable for potable water with solvent cement joints including cost of couplers, as per IS specification no.4985/1988 including all local and central taxes, transportation, freight charges, octroi, inspection charges, loading, unloading, conveyance to the departmental stores and including cost of jointing material i.e. solvent cement, etc. complete. 90 mm Dia. PVC 4 Kgcm2 | 360 | RMT | 160 | ₹57,600 |
| 6 | Item No. 6 :-Providing and supplying in standard lengths ISI mark rigid unplasticised PVC pipes suitable for potable water with solvent cement joints including cost of couplers, as per IS specification no.4985/1988 including all local and central taxes, transportation, freight charges, octroi, inspection charges, loading, unloading, conveyance to the departmental stores and including cost of jointing material i.e. solvent cement, etc. complete. 75 mm Dia. PVC 4 Kgcm2 | 450 | RMT | 115 | ₹51,750 |
| 7 | Item No. 7 :-Lowering, laying and jointing PVC pipes and specials of following class and diameter including cost of conveyance from stores to site of works including cost of all labour, material, except cement solvent, giving satisfactory hydraulic testing as per IS code, etc. complete. 90 mm Dia. PVC 4 Kgcm2 | 360 | RMT | 35 | ₹12,600 |
| 8 | Item No. 7 :-Lowering, laying and jointing PVC pipes and specials of following class and diameter including cost of conveyance from stores to site of works including cost of all labour, material, except cement solvent, giving satisfactory hydraulic testing as per IS code, etc. complete. 75 mm Dia. PVC 4 Kgcm2 | 450 | RMT | 28 | ₹12,600 |
| 9 | Item No. 11 :- Refilling the trenches with available excavated stuff with soft material first over pipeline and then hard material in 15 cm layers with all leads and lifts including consolidation, surcharging etc. complete. | 216.71 | CUM | 92 | ₹19,937.32 |
| 10 | Item No. 12 :- Providing double flange sluice valve confirming for IS- 14846 including worn gear arrangements as per test pressure, stainless steel spindle, caps, including inspection charges, transportation upto departmental store, unloading, stacking excluding GST levied by GOI & GOM in all respect etc. complete. | 1 | Nos | 5,959 | ₹5,959 |
stage.html
html • 0.03 MB
tech_bid_open.pdf
tech_eval.pdf
fin_bid_open.pdf
boq_comp_chart.xlsx
xlsx
Tap a document below to read it instantly. You can also download everything as a ZIP if you prefer.
details.html
html • 0.03 MB
Tendernotice_1.pdf
PDF • 0.57 MB
BOQ_2287552.xls
BOQ • 0.24 MB
Download all tender documents and submit your bid
Disclaimer: TenderKart has made every reasonable effort to ensure that the information on this page is accurate and authentic, however it cannot be held liable for any third-party claims or losses or any damages. TenderKart makes no warranty, expressed or implied, as to the results obtained from the use of this information. If you notice any error or omission, please let us know at .