| # | Company | Amount | Rank | Status |
|---|---|---|---|---|
| 1 | L1₹11.1 CrAccepted-Finance GOODBYE BAZAR HATHRAS | HATHRAS | HATHRAS | UTTAR PRADESH | ₹11.1 Cr | L1 | Accepted-Finance Accepted |
| 2 | L2₹12.5 CrRejected-Finance 7C GOVIND NAGAR MATHURA | MATHURA | ₹12.5 Cr | L2 | Rejected-Finance Rejected Because Quoted higher rate |
| 3 | L3₹12.8 CrRejected-Finance G 17 RAMGHAT ROAD GYAN SAROVAR COLONY ALIGARH | ALIGARH | ALIGARH | UTTAR PRADESH | ₹12.8 Cr | L3 | Rejected-Finance Rejected Because Quoted higher rate |
| 4 | L4₹13.5 CrRejected-Finance SURYA FACTORY SORAN ROAD ALIGARH | ALIGARH | ALIGARH | UTTAR PRADESH | ₹13.5 Cr | L4 | Rejected-Finance Rejected Because Quoted higher rate |
| 5 | L5₹14.7 CrRejected-Finance E 13 NIRBHAY NAGAR GALLANA ROAD AGRA | AGRA | ₹14.7 Cr | L5 | Rejected-Finance Rejected Because Quoted higher rate |
Tender Value
₹18.7 Cr
EMD Value
₹30 L
Closing Date
20 Dec 2025, 12:00 pmClosed
Superintending Engineer Aligarh Circle PWD Aligarh
Office of The SE, Aligarh Circle, P.W.D., Aligarh
Widening and strengthening work of Panethi-Hanuman Chowki Road (O.D.R.)
2025_CEALG_1096673_1
5816/Cashier(C.D.-1 A.)-A.C./25-26 Date 06-10-2025
Open Tender
Civil Works - Roads
365 days
Aligarh
Please refer Tender documents.
2 documents required · 2 mandatory
₹2,354
₹30 L
Office of The SE, Aligarh Circle, P.W.D., Aligarh
2 Jan 2026
5 Dec 2025
20 Dec 2025
5 Dec 2025
20 Dec 2025
5 Dec 2025
15 Dec 2025
Amount
Dismantling of flexible pavements and disposal of dismantled materials up to a lead of 1000 metres, stacking serviceable and unserviceable materials separately As per Morth Specification. 202, S.I. 2.05 (Including cost of all Material, labour, T&P, Labour Cess and All other Taxes but Excluding G.S.T.), As per Direction by E/I.
Excavation for roadwork in soil with hydraulic excavator including cutting and loading in tippers, trimming bottom and side slopes, in accordance with requirements of lines, grades and cross sections, and transporting to the embankment location within all lifts and lead. (Including cost of all Material, labour, T&P, Labour Cess and All other Taxes but Excluding G.S.T.), As per Direction by E/I.
Construction of embankment with approved material obtained from borrow pits with all lifts and leads, transporting to site, spreading, grading to required slope and compacting to meet requirement of table 300-2. (Including cost of all Material, labour, T&P, Labour Cess and All other Taxes but Excluding G.S.T.), As per Direction by E/I.
Construction of sub-grade and earthen shoulders with approved material obtained from borrow pits with all lifts & leads, transporting to site, spreading, grading to required slope and compacted to meet requirement of table No. 300-2 Carted earth 5 km (Including cost of all Material, labour, T&P, Labour Cess and All other Taxes but Excluding G.S.T.), As per Direction by E/I.
Construction of granular sub-base by providing coarse graded material, spreading in uniform layers with motor grader on prepared surface, mixing by mix in place method with rotavator at OMC, and compacting with vibratory roller to achieve the desired density, complete as per clause 401. (Including cost of all Material, labour, T&P, Labour Cess and All other Taxes but Excluding G.S.T.), As per Direction by E/I.
Providing , laying, spreading and compacting graded stone aggregate to wet mix macadam specification including premixing the material with water at OMC in mechanical mix plant carriage of mixed material by tipper to site, laying in uniform layers with paver in sub-base / base course on well prepared surface and compacting with vibratory roller to achieve the desired density. as per MORTH Specification clause-406 (Including cost of all Material, labour, T&P, Labour Cess and All other Taxes but Excluding G.S.T.), As per Direction by E/I.
Providing and applying primer coat with SS2 grade bitumen emulsion on prepared surface of granular Base including clearing of road surface and spraying primer at the rate of 0.70 to 1.00 kg/sqm using mechanical means. complete. as morth specification no 502 (Including cost of all Material, labour, T&P, Labour Cess and All other Taxes but Excluding G.S.T.), As per Direction by E/I.
Providing and laying dense graded bituminous macadam with higher capacity batch type HMP using crushed aggregates of specified grading, premixed with bituminous binder (VG-30) @ 4.5 per cent by weight of total mix and filler, transporting the hot mix to work site, laying with a hydrostatic paver finisher with sensor control to the required grade, level and alignment, rolling with smooth wheeled, vibratory and tandem rollers to achieve the desired compaction as per MoRTH specification clause No. 505 complete in all respects. (Including cost of all Material, labour, T&P, Labour Cess and All other Taxes but Excluding G.S.T.), As per Direction by E/I.
Providing and applying tack coat with bitumen emulsion using emulsion pressure distributor at the rate of 0.20 kg per sqm on the prepared bituminous surface cleaned with mechanical broom. as morth specification no 503. (Including cost of all Material, labour, T&P, Labour Cess and All other Taxes but Excluding G.S.T.), As per Direction by E/I.
Providing and laying bituminous concrete with higher capacity batch type hot mix plant using crushed aggregates of specified grading, premixed with bituminous binder (VG-40) @ 5.4 per cent of mix and filler, transporting the hot mix to work site, laying with a hydrostatic paver finisher with sensor control to the required grade, level and alignment, rolling with smooth wheeled, vibratory and tandem rollers to achieve the desired compaction as per MORTH specification clause No. 507 complete in all respects (Including cost of all Material, labour, T&P, Labour Cess and All other Taxes but Excluding G.S.T.), As per Direction by E/I.
Excavation for roadwork in soil with hydraulic excavator including cutting and loading in tippers, trimming bottom and side slopes, in accordance with requirements of lines, grades and cross sections, and transporting to the embankment location within all lifts and lead. (Including cost of all Material, labour, T&P, Labour Cess and All other Taxes but Excluding G.S.T.), As per Direction by E/I.
Construction of granular sub-base by providing coarse graded material, spreading in uniform layers with motor grader on prepared surface, mixing by mix in place method with rotavator at OMC, and compacting with vibratory roller to achieve the desired density, complete as per clause 401. (Including cost of all Material, labour, T&P, Labour Cess and All other Taxes but Excluding G.S.T.), As per Direction by E/I.
Providing, laying, spreading and compacting stone aggregates of specific sizes to water bound macadam specification including spreading in uniform thickness, hand packing, rolling with 3 wheeled steel/ vibratory roller 8-10 tonnes in stages to proper grade and camber, applying and brooming requisite type of screening/ binding Materials to fill up the interstices of coarse aggregate, watering and compacting to the required density. (G-3) (Including cost of all Material, labour, T&P, Labour Cess and All other Taxes but Excluding G.S.T.), As per Direction by E/I.
Construction of un-reinforced, dowel jointed, plain cement concrete pavement over a prepared sub base with 43 grade cement @ 410 kg per cum, coarse and fine aggregate conforming to IS 383, maximum size of coarse aggregate not exceeding 25 mm, mixed in a batching and mixing plant as per approved mix design, transported to site, laid with a fixed form or slip form paver, spread, compacted and finished in a continuous operation including provision of contraction, expansion, construction and longitudinal joints, joint filler, separation membrane, sealant primer, joint sealant, debonding strip, dowel bar, tie rod, admixtures as approved, curing compound, finishing to lines and grades as per drawing (Including cost of all Material, labour, T&P, Labour Cess and All other Taxes but Excluding G.S.T.), As per Direction by E/I.
Construction of embankment with approved material obtained from borrow pits with all lifts and leads, transporting to site, spreading, grading to required slope and compacting to meet requirement of table 300-2. (Including cost of all Material, labour, T&P, Labour Cess and All other Taxes but Excluding G.S.T.), As per Direction by E/I.
Earth work in excavation of foundation of structures as per drawing and technical specification, including setting out, construction of shoring and bracing, removal of stumps and other deleterious matter, dressing of sides and bottom and backfilling with approved material. As Per Morth Specification (Including cost of all Material, labour, T&P, Labour Cess and All other Taxes but Excluding G.S.T.), As per Direction by E/I.
Plain cement concrete 1:3:6 nominal mix in foundation with crushed stone aggregate 40 mm nominal size mechanically mixed, placed in foundation and compacted by vibration including curing for 14 days. complete as per drawings and technical specifications Clause 3 (M-10) (Including cost of all Material, labour, T&P, Labour Cess and All other Taxes but Excluding G.S.T.), As per Direction by E/I.
Plain/Reinforced Cement Concrete in Open Foundation complete as per Drawing and Technical Specifications1500, 1700 & 2100 (P.C.C. M-15) (Including cost of all Material, labour, T&P, Labour Cess and All other Taxes but Excluding G.S.T.), As per Direction by E/I.
Plain/Reinforced Cement Concrete in Open Foundation complete as per Drawing and Technical Specifications. 1500, 1700 & 2100 (P.C.C. M-20) (Including cost of all Material, labour, T&P, Labour Cess and All other Taxes but Excluding G.S.T.), As per Direction by E/I.
Plain/Reinforced Cement Concrete in Open Foundation complete as per Drawing and Technical Specifications 1500, 1700 & 2100 (R.C.C. M-20) (Including cost of all Material, labour, T&P, Labour Cess and All other Taxes but Excluding G.S.T.), As per Direction by E/I.
Supplying, Fitting and Placing un-coated HYSD bar Reinforcement in Foundation complete as per Drawing and Technical Specifications. (Including cost of all Material, labour, T&P, Labour Cess and All other Taxes but Excluding G.S.T.), As per Direction by E/I.
Providing & Laying of 350 mm dia. N.P.-4 Hume Pipe in Porper Position as directed by E.I. including Cost Of Material,Labour and T&P etc. complete. (Including cost of all Material, labour, T&P, Labour Cess and All other Taxes but Excluding G.S.T.), As per Direction by E/I.
Providing & Laying of 600 mm dia. N.P.-4 Hume Pipe in Porper Position as directed by E.I. including Cost Of Material,Labour and T&P etc. complete. (Including cost of all Material, labour, T&P, Labour Cess and All other Taxes but Excluding G.S.T.), As per Direction by E/I.
Providing & Laying of 900 mm dia. N.P.-4 Hume Pipe in Porper Position as directed by E.I. including Cost Of Material,Labour and T&P etc. complete. (Including cost of all Material, labour, T&P, Labour Cess and All other Taxes but Excluding G.S.T.), As per Direction by E/I.
05 Year Maintenance Charge @ 2.50% Routine Maitenance of road for 05 Years after the competion of work (Vide shasanadesh No. 17/2024/सा0-113/23-1-2024-23-1099/113/2023 Dated 16.01.2024 & letter No. 36890C/RMC/Mool-23-24 Dated 17.02.2024 of ENC PWD. Rate Excluding of G.S.T.) 1-1st Year @ Nill
2nd Year @ 0.25%
3rd Year @ 0.50%
4th Year @ 0.75%
5th Year @ 1.00%
M/s Akash Deep Construction Compnay (BID ID -5758424)
M/S SHIVA ASSOCIATES (BID ID -5729494)
M/s Hanu Infrastructure Pvt Ltd (BID ID -5739837)
SAMRIDDHI NIRMAN PVT. LTD. (BID ID -5757539)
SIDDHARTH CONSTRUCTION (BID ID -5756981)
tech_eval.pdf
boq_comp_chart.xlsx
xlsx
fin_eval.pdf
Tap a document below to read it instantly. You can also download everything as a ZIP if you prefer.
details.html
html • 0.03 MB
Tendernotice_1.pdf
PDF • 5.81 MB
BOQ_2019044.xls
BOQ • 0.37 MB
Download all tender documents and submit your bid