| # | Company | Quoted % | Amount | Rank | Status |
|---|---|---|---|---|---|
| 1 | L1₹7.9 LAdmitted-Fee/PreQual/Technical/Finance | -0.01% | ₹7.9 L | L1 | Admitted-Fee/PreQual/Technical/Finance |
| 2 | L2₹7.9 L+₹79.10 (0.01%)Admitted-Fee/PreQual/Technical/Finance | +0.00% | ₹7.9 L+₹79.10 (0.01%) | L2 | Admitted-Fee/PreQual/Technical/Finance |
Tender Value
₹7.9 L
EMD Value
₹15,820
Closing Date
11 Sept 2026, 4:00 pmClosed
Executive Engineer RnB Division Kulgam
Executive Engineer RnB Division Kulgam
Repair/Augmentation of the presiding Officers chamber in the newly Relocated Building of the NIA Court Complex Kulgam
2026_PWDJK_323113_11
62/2026-27/RnB/Kul/6115-25 Dtd 01-09-2026
Open Tender
Civil Works
Percentage
15 days
Kulgam
Please refer Tender documents.
2 documents required · 2 mandatory
₹300
Account No. 0470010200000099
₹15,820
19 Sept 2026
3 Sept 2026
12 Sept 2026
3 Sept 2026
11 Sept 2026
3 Sept 2026
This is a percentage-rate BOQ. The schedule below shows estimated quantities and rates. Bidders quote a single percentage above or below the total estimated cost.
| Sl No | Description | Qty | Unit | Est. Rate | Est. Amount |
|---|---|---|---|---|---|
| 1Engagement of carpenter, assistant carpenters, JCB for repair, renovation of old existing structure/easing of doors, windows and other allied works complete. | |||||
| 1.01 | 4 labours for 2days | 8 | No | 550.85 | ₹4,406.8 |
| 1.02 | 4 carpenter for 2days | 8 | No | 593.22 | ₹4,745.76 |
| 2 | Demolishing brick work in cement mortar manually/by mechanical means including stacking of serviceable material and disposal of unserviceable material within 50 metres lead as per direction of Engineer-in-Charge. | 1.98 | Cum | 1,277.97 | ₹2,530.38 |
| 3 | Dismantling tile work in floors and roofs laid in cement mortar including stacking material within 50 metres lead. Thickness of tiles 10 mm to 25 mm. | 15 | Sqm | 49.97 | ₹749.55 |
| 4 | Earth work in bulk excavation by mechanical means (hydraulic excavator) over areas exceeding 30 cm in depth, 1.5 m in width as well as 10 m² on plan, including disposal of excavated earth lead up to 50 metres and lift up to 1.5 m, as directed by Engineer-in-Charge. | 33.73 | Cum | 164.2 | ₹5,538.47 |
| 5 | Filling available excavated earth (excluding rock) in trenches, plinth, sides of foundations etc. in layers.not exceeding 20cm in depth, consolidating each deposited layer by ramming and watering, lead upto 50m and lift upto 1.5m | 33.73 | Cum | 190.83 | ₹6,436.7 |
| 6 | Providing, laying, spreading and compacting stone soling of specified sizes in uniform thickness, rolling, watering and compacting, including all carriages and lifts up to the site of work complete job. | 1.77 | Cum | 720.34 | ₹1,275 |
| 7 | Providing and laying in position specified grade of cement concrete, excluding the cost of centering and shuttering, all work up to plinth level:1:4:8 (1 cement : 4 coarse sand : 8 graded stone aggregate) | 0.98 | Cum | 4,856.78 | ₹4,759.64 |
| 8 | Making plinth protection 50 mm thick of cement concrete 1:3:6 (1 cement : 3 coarse sand : 6 graded stone aggregate 20mm nominal size)over 75 mm bed of dry brick ballast 40mm nominal size well rammed and consolidated and grouted with fine sand incl. finishing the top smooth and curing. | 2.43 | Sqm | 485.59 | ₹1,179.98 |
stage.html
html • 0.02 MB
finance_1086647.pdf
boq_comp_chart.xlsx
xlsx
Tap a document below to read it instantly. You can also download everything as a ZIP if you prefer.
details.html
html • 0.03 MB
Tendernotice_1.pdf
PDF • 1.67 MB
BOQ_1086647.xls
BOQ • 0.28 MB
Download all tender documents and submit your bid
Disclaimer: TenderKart has made every reasonable effort to ensure that the information on this page is accurate and authentic, however it cannot be held liable for any third-party claims or losses or any damages. TenderKart makes no warranty, expressed or implied, as to the results obtained from the use of this information. If you notice any error or omission, please let us know at .