| 1 | l1₹10.4 CrAccepted-AOC CHANDAULI | UTTAR PRADESH | 221009 | ₹10.4 Cr | l1 | Accepted-AOC l1 |
| 2 | l2₹10.6 CrRejected-Finance KUKUHAWA POST GAURABADSHAHPUR JANPAD JAUNPUR | ₹10.6 Cr | l2 | Rejected-Finance l2 |
| 3 | Not Admitted-Fee/PreQual/Technical 24 JEEVAN PLAZA VIRAM KHAND 5 GOMTI NAGAR LUCKNOW UTTAR PRADESH | LUCKNOW | LUCKNOW | UTTAR PRADESH | - | - | Not Admitted-Fee/PreQual/Technical Not Complied with technical specification |
| Sl No | Description | Qty | Unit | ARVIND KUMAR SINGH L1 | VIJAY KUMAR SINGH L2 |
|---|---|---|---|---|---|
| 1.00 | E/w in correcting internal section & restoration of Sultanpur parallel branch From Km. 30.500 to Km. 55.200 including all lead and lift with proper disposal. | 8,77,247.41 | cum | 66.6 ₹5,84,24,677.51 | 65 ₹5,70,21,081.65 Lowest |
| 2.00 | Dressing of excavated earth /silt at Sultanpur parallel branch From Km. 30.500 to Km. 55.200 | 8,77,247.41 | cum | 7.5 ₹65,79,355.58 Lowest | 8.5 ₹74,56,602.99 |
| 3.00 | Earth work for making Daula with manual compaction dressing by any means lead upto 30 m & lift upto 1.50m etc. complete in all respect | 21,612.5 | sqm | 100 ₹21,61,250 Lowest | 105 ₹22,69,312.5 |
| 4.00 | E/W in corrceting internal section at v.r.b/d.r.b./f.b. on both side u/s 15 m & d/s up to 10 m including all type of soil, 30m lead and 1.50m lift with manual compaction and dressing to profile . | 28,818.13 | cum | 40.3 ₹11,61,370.64 Lowest | 50 ₹14,40,906.5 |
| 5.00 | Dry earth work in foundation for toe Wall on channels of discharge above 10 Cumecs including lead upto 30M and lift upto 1.5M and its disposal and back filling. | 1,620 | cum | 100 ₹1,62,000 Lowest | 115 ₹1,86,300 |
| 6.00 | Making sub grade for pitching work including watering, compaction and preparation of surface. | 13,340 | sqm | 15 ₹2,00,100 Lowest | 19 ₹2,53,460 |
| 7.00 | Supply & laying of Geo textile (sheet) made of 200 GSM Woven multifilament polyprophylene yarn including all cost of material, labour and T&P etc. | 13,940 | sqm | 100 ₹13,94,000 Lowest | 130 ₹18,12,200 |
| 8.00 | Supplying and pitching of stone boulder for Side Slope from Mirzapur quarry 20 kg to 40 kg including all cost of material, labour and T&P etc. | 6,003 | cum | 4,400 ₹2,64,13,200 Lowest | 4,600 ₹2,76,13,800 |
| 19.00 | Supplying and pitching of stone boulder for toe wall from Mirzapur quarry 20 kg to 40 kg including all cost of material, labour and T&P etc.. | 1,620 | cum | 4,400 ₹71,28,000 Lowest | 4,600 ₹74,52,000 |
Tender Value
Refer Docs
EMD Value
₹23.2 L
Closing Date
19 May 2026, 11:00 amClosed
SUPERINTENDING ENGINEER
O/O SE XITH CIRCLE IW AYODHYA
AS PER NIT 01 LOT03
2026_UPIDC_1147738_3
01/SE-XI/2026-27
Open Tender
Civil Works
Item Rate
270 days
AYODHYA
Please refer Tender documents.
2 documents required · 2 mandatory
₹8,850
₹23.2 L
O/O SE XITH CIRCLE IW AYODHYA
22 Aug 2026
13 May 2026
19 May 2026
13 May 2026
19 May 2026
13 May 2026
13 May 2026
| Sl No | Description | Qty | Unit | Est. Rate | Est. Amount |
|---|---|---|---|---|---|
| 1 | E/w in correcting internal section & restoration of Sultanpur parallel branch From Km. 30.500 to Km. 55.200 including all lead and lift with proper disposal. | 8,77,247.41 | cum | - | - |
| 2 | Dressing of excavated earth /silt at Sultanpur parallel branch From Km. 30.500 to Km. 55.200 | 8,77,247.41 | cum | - | - |
| 3 | Earth work for making Daula with manual compaction dressing by any means lead upto 30 m & lift upto 1.50m etc. complete in all respect | 21,612.5 | sqm | - | - |
| 4 | E/W in corrceting internal section at v.r.b/d.r.b./f.b. on both side u/s 15 m & d/s up to 10 m including all type of soil, 30m lead and 1.50m lift with manual compaction and dressing to profile . | 28,818.13 | cum | - | - |
| 5 | Dry earth work in foundation for toe Wall on channels of discharge above 10 Cumecs including lead upto 30M and lift upto 1.5M and its disposal and back filling. | 1,620 | cum | - | - |
| 6 | Making sub grade for pitching work including watering, compaction and preparation of surface. | 13,340 | sqm | - | - |
| 7 | Supply & laying of Geo textile (sheet) made of 200 GSM Woven multifilament polyprophylene yarn including all cost of material, labour and T&P etc. | 13,940 | sqm | - | - |
| 8 | Supplying and pitching of stone boulder for Side Slope from Mirzapur quarry 20 kg to 40 kg including all cost of material, labour and T&P etc. | 6,003 | cum | - | - |
| 19 | Supplying and pitching of stone boulder for toe wall from Mirzapur quarry 20 kg to 40 kg including all cost of material, labour and T&P etc.. | 1,620 | cum | - | - |
stage.html
html • 0.04 MB
tech_bid_open.pdf
tech_eval.pdf
boq_comp_chart.xlsx
xlsx
fin_eval.pdf
aoc.pdf
Tap a document below to read it instantly. You can also download everything as a ZIP if you prefer.
details.html
html • 0.03 MB
Tendernotice_1.pdf
PDF • 1.07 MB
BOQ_2147791.xls
BOQ • 0.35 MB
LOT03DOCUMENT.pdf
Tender Documents • 3.33 MB
Download all tender documents and submit your bid
Disclaimer: TenderKart has made every reasonable effort to ensure that the information on this page is accurate and authentic, however it cannot be held liable for any third-party claims or losses or any damages. TenderKart makes no warranty, expressed or implied, as to the results obtained from the use of this information. If you notice any error or omission, please let us know at [email protected].