Loading…
India Infra Updates on WhatsApp
Join the Tenderkart WhatsApp channel for India Infra Updates
Loading…
Tender ID
Eligibility, documents, scope and key termsEligibility, required documents, scope of work and key terms of this tender, in one click.
| # | Company | Status |
|---|---|---|
| 1 | Admitted-Finance | Admitted-Finance |
| 2 | Admitted-Finance | Admitted-Finance |
Tender Value
Refer Docs
EMD Value
₹5,000
Closing Date
10 Apr 2024, 12:00 pmClosed
Eligibility, documents, scope and key termsEligibility, required documents, scope of work and key terms of this tender, in one click.
SE EDC-II ALIGARH
ALIGARH
EDC2A-73/2023-24
2024_DVVNL_914852_4
EDC2A-73/2023-24
Open Tender
Electrical Works
Item Rate
365 days
KHAIR
Please refer Tender documents.
2 documents required · 2 mandatory
₹1,180
DVVNL AGRA WEBSITE
₹5,000
16 Apr 2024
5 Apr 2024
10 Apr 2024
5 Apr 2024
10 Apr 2024
5 Apr 2024
Amount
Cartage of following poles from Store centre or from any other place to the respective site of work through the Kachha Pacca road including the work of its loading & unloading at the respective ends, also including the work of dragging etc. and also including the cost of labour, T&P carrier etc. required for proper completion of work. (Dist. 0 to 50 Kms.).
PCC poles 8.5 Mtr./ST poles 11/13 Mtr.
Cartage of line material viz LT Cable, Conductor/ GI earth wire, Barbed wire, Cross Arm, Angle, Channel, Insulator, various Clamps, XLPE cable, Cable, Stone pad & other line material from Store centre or from any other place to the respective site of work through the Kachha Pacca road including the work of its loading & unloading at the respective end, also including the work of dragging etc. and also including the cost of labour, T&P carrier etc. required for proper completion of work. (Dist. 0 to 50 Kms.).
Erection of single support including complete H.T/L.T fittings (with drilling & Cutting) as per RESSPO manual and as per direction of Engineer incharge including the cost of labour, T & P and carrier etc. required for proper completion of work.
PCC poles 8.5 Mtr./ST poles 11/13 Mtr.
Dismentling of old and damaged 33 KV & 11 KV Line on Double pole/Section pole after dismentling of all accessories. It includes the work of cartage, cost of labour, T&P carrier etc. required for proper completion of work.
Erection of double pole/Section Pole on PCC /ST pole including the work of complete line (With drilling & Curtting) as per RESSPO norm manual and as per direction of Engineer Incharge including the cost of labour, T & P and carrier etc. required for proper completion of work.
Erection and grouting of stay set including the work of nozzling etc. as per RESSPO manual and also including the cost of arrangement of all grouting material, labour, T&P etc. required for proper completion of work.
Providing and fixing of stay insulator.
Grouting of PCC poles 8.5 Mtr./ ST poles 11 Mtr/13 Mtr.. Long as per RESSPO norms
Making the plinth of Steel poles.
Fixing of earthing rod as per RESSPO manual and as per direction of supervising engineer including the cost of labour, T&P etc. Required for proper completion of work.
Chopping of tree branches which are touching to HT/LT lines.
Retighting of stay complete with nozelling & binding including cost of labour T&P etc required for proper completion of work.
Straightening of tilted PCC/Steel pole at various places as per direction of JE.
Laying, sagging, stringing, binding and jumpering etc. of new/old line conductor on the newly/old erected pole as per RESSPO manual and as per direction of supervising engineer, including the cost of arrangement of labour, T&P carrier etc. required for proper completion of work.
ACSR Weasal Conductor
ACSR DOG Conductor
ABC 3x120+1x95+1x16 sq.mm/ABC 3x95+1x70+1x16 sq.mm/ABC 3x50+1x35+1x16 sq.mm
Re-sagging of loose HT/LT line conductor as per direction of superwising engineer. It includes the cost of labour T&P carrier etc. required for proper completion of work.
ACSR Weasal Conductor
ACSR Dog Conductor
Replacement/Re-fixing of following damaged/ disturbed/de-aligned accessories:-
33 KV Disc Insulator with fitting
33 KV Pin Insulator with pin
33 KV V-type Cross Arm
11 KV Disc Insulator with fitting
11 KV Pin Insulator with pin
11 KV V-type Cross Arm
F bracket
Providing & Fixing of Clamps of LT, Cross Arm Holding, F-Clamp, Stay Clamp, Danger board clamp with Nut & Bolts.
Providing/Fixing of missing Nut bolts and washer
Dismantling and removal of existing conductor from the various area preparing their coils and then stacking in the respective JE’s (Store) as per direction of Supervising Engineer. It includes the work of cartage, cost of labour, T&P carrier etc. required for proper completion of work.
ACSR Weasal Conductor/GI wire.
ACSR Dog Conductor
Guarding of old 11 KV line damaged due to storm by laying two nos. GI wire parallel and fixing of lacings (tilli) at a distance at 2-3 Mtr. as per RESSPO manual and also including the cost of arragement of labour, T & P etc. required for proper completion of work.
Filling of 3x70/3x120/3x185/3x300 Sq.mm. 33 KV & 11 KV XLPE heat shrinkable cable jointing kits indoor & outdoor type including the cost of labour T&P carrier etc for proper completion of work. (In Case of jointing kit not available from store so will be provided by the contractor.)
Repairing of 3x70/3x120/3x185/3x300 Sq.mm 33 KV & 11 KV under ground cable by Straight Through after digging trench of 600 mm. wide, 1500 mm deep, providing the fine sand cushion beneath and above the cable. The cable shall be duly protected by Ist class bricks, two on either side and third on top of the cable, laid in series one after the other. The work includes supplying of fine sand and bricks, filling and ramming of the left out soil, closing the trench and levelling. Spare cable shall be left and buried in the trench in the shape of rings at both ends. All material (except cable), labour, T&P carrier etc, required for proper completion of work will be arranged by the contractor at his own cost.
Safe carriage of Old line material viz. Conductor, G.I. Earth wire, ABC conductor, Cross Arm, Angle, Channel, Insulators, Clamps & other line material from any other place or from site of work to the work of its loading & unloading at the respective ends including the cost of labour, T&P and carrier etc. required for proper completion of work.
M/S PMC INFRATECH
tech_bid_open.pdf
tech_eval.pdf
fin_bid_open.pdf
boq_comp_chart.xlsx
xlsx
Download all tender documents and submit your bid
Disclaimer: TenderKart has made every reasonable effort to ensure that the information on this page is accurate and authentic, however it cannot be held liable for any third-party claims or losses or any damages. TenderKart makes no warranty, expressed or implied, as to the results obtained from the use of this information. If you notice any error or omission, please let us know at .