| # | Company | Amount | Rank | Status |
|---|---|---|---|---|
| 1 | L1₹1.1 CrAccepted-Finance | ₹1.1 Cr | L1 | Accepted-Finance OK |
| 2 | L2₹1.2 Cr+₹13.7 L (12.5%)Accepted-Finance NOT SPECIFIED | ₹1.2 Cr+₹13.7 L (12.5%) | L2 | Accepted-Finance OK |
Tender Value
₹90 L
EMD Value
₹90,000
Closing Date
22 Mar 2023, 5:00 pmClosed
SE ETC NOIDA
220 KV SUB-STATION SECTOR-20 NOIDA
EXISTING 132 KV BAY TO OTHER END 132 KV BAY AND OTHER ASSOCIATED WORKS FOR SHIFTING OF 132 KV HYBRID SWITCHGEAR BUSCOUPLER BAY AT 220 KV SUBSTATION SECTOR-129 NOIDA ON TURN-KEY BASIS
2023_UPTCL_765609_2
E-ST-40/ETCN/2022-23
Open Tender
Electrical Works
Item Rate
60 days
NOIDA
Please refer Tender documents.
2 documents required · 2 mandatory
₹7,080
EE ETD NOIDA
₹90,000
10 Apr 2023
15 Feb 2023
23 Mar 2023
15 Feb 2023
22 Mar 2023
15 Feb 2023
Amount
Part-A Supply Portion
supply of 132 kV 1CX630 sq.mm. Aluminium conductor XLPE insulated corrugated Al sheathed Power cable (Construction as per IEC-60502-2 and testing as per IEC-60840)
Normal straight through joint/ Insulated Joint suitable for above cable with all accessories
Outdoor Type Polymeric type Complete End Termination kit suitable for above cable with all accessories
Single phase link box with SVL as required
Three phase link box with/without SVL as required
Single core 300 sq.mm. copper conductor PVC insulated 6.6 kV grade earthing cable
Single core 300 sq.mm. copper conductor PVC insulated 6.6 kV grade Bonding cable
Aluminium alloy trefoil clamps
Aluminium alloy Single clamps
Terminal connector
HDPE Pipe suitable for XLPE Cable
Warning tape
Route Marker
RCC Slab
Part-B (Work)
Route survey & prepration of drawing including digging of trial pits for specified route length
Shifting of 132 KV 630 sqmm Al Cond. UG cable (3+1spare) from store to site
Excavation of trench (1.5m)
Sand bedding and laying of all (3+1 spare) single core cable in excavated trench along with approach cable in excavated trench (including jointing and installation of Approach cable)
Laying of all (3+1 spare) single core cable through HDPE pipes in road/Rail crossing along with installation of approach cable
Backfilling of trench with sand, installation of RCC cover, warning tape, routel marker & filling and leveling of excavated earth
Installation of outdoor end termination
Installation of straight throught joint Kit
Installation of three phase link boxes with/without SVL.
Installation of single phase link boxes with/without SVL.
Costruction of foundation of 145 Hybrid switchgear at new location.
Shifting works of 132 kV Hybrid bus-coupler bay
Testing & commissioning
Providing and fixing of cable structure for 5 No. end terminations
Other miscellaneous Erection works required to complete the job.
G R C AND SONS
tech_bid_open.pdf
tech_eval.pdf
fin_bid_open.pdf
boq_comp_chart.xlsx
xlsx
fin_eval.pdf
Download all tender documents and submit your bid
Disclaimer: TenderKart has made every reasonable effort to ensure that the information on this page is accurate and authentic, however it cannot be held liable for any third-party claims or losses or any damages. TenderKart makes no warranty, expressed or implied, as to the results obtained from the use of this information. If you notice any error or omission, please let us know at .