Loading…
Loading…
| # | Company | Quoted % | Amount | Rank | Status |
|---|---|---|---|---|---|
| 1 | L1₹36.4 LAdmitted-Fee/PreQual/Technical/Finance | -23.77% | ₹36.4 L | L1 | Admitted-Fee/PreQual/Technical/Finance |
| 2 | L2₹40.6 LAdmitted-Fee/PreQual/Technical/Finance | -15.00% | ₹40.6 L | L2 | Admitted-Fee/PreQual/Technical/Finance |
Tender Value
₹47.7 L
EMD Value
₹95,480
Closing Date
12 May 2026, 6:00 pmClosed
xen
bda bharatpur
W B M road construction work annual under the jurisdiction of Executive Engineer 3
2026_UITBR_556650_1
online nit 07(2026-2027)05 bharatpur Development Authorit
Open Tender
Civil Works - Roads
Percentage
365 days
bda bharatpur
Please refer Tender documents.
2 documents required · 2 mandatory
₹500
Secretary, bda
₹95,480
Yes
19 May 2026
6 May 2026
13 May 2026
6 May 2026
12 May 2026
6 May 2026
This is a percentage-rate BOQ. The schedule below shows estimated quantities and rates. Bidders quote a single percentage above or below the total estimated cost.
| Sl No | Description | Qty | Unit | Est. Rate | Est. Amount |
|---|---|---|---|---|---|
| 1 | Item Code [R3 ]:Item Type [road] ::Construction of Embankment with Material Obtained from Borrow Pits Construction of embankment with approved material obtained from borrow pits with a lift up to 1.5 m, transporting to site, spreading, grading to required slope and compacting to meet requirement of Tables 300-1 and 300-2 with a lead up to 50 m as per MoRTH Specification Clause 305.3 (With Lead for 20K.M)
Sub Item Code [R3 + 4.1]: Construction of Embankment with Material Obtained from Borrow Pits Construction of embankment with approved material obtained from borrow pits with a lift up to 1.5 m, transporting to site, spreading, grading to required slope and compacting to meet requirement of Tables 300-1 and 300-2 with a lead up to 50 m as per MoRTH Specification Clause 305.3 (With Lead for 20K.M) (With Lead for 20K.M) | 8,775 | CUM | 169.25 | ₹14,85,168.75 |
| 2 | Item Code [R4 2025 4.2]:Item Type [road] ::Plant Mix Method Providing laying spreading and compacting specified graded sand, gravel (crushed stone) as per Table 400-1,400-2 or any other course material as per design mix, as per CBR in sub base course including premixing the material at OMC in wet mix plant, carriage of mixed material spreading in uniform layers with motor grader F.E loader on a prepared base and compacting with vibratory roller to achieve desired density (as per I.S.2720) including all material, labor, machinery, lighting guarding, barricading and maintenance of diversion complete.[MoRTH specification : Clause 401]. By mechanical means.
Sub Item Code [R4 2025 4.2 + R4 2025 4.2.1]: Plant Mix Method Providing laying spreading and compacting specified graded sand, gravel (crushed stone) as per Table 400-1,400-2 or any other course material as per design mix, as per CBR in sub base course including premixing the material at OMC in wet mix plant, carriage of mixed material spreading in uniform layers with motor grader F.E loader on a prepared base and compacting with vibratory roller to achieve desired density (as per I.S.2720) including all material, labor, machinery, lighting guarding, barricading and maintenance of diversion complete.[MoRTH specification : Clause 401]. By mechanical means. For Grading-I Material | 1,800 | Cum | 882 | ₹15,87,600 |
| 3 | Item Code [R4 2025 4.4.1.2]:Item Type [road] ::Using Crusher Broken Aggregate
Sub Item Code [R4 2025 4.4.1.2 + R4 2025 4.4.1.2.2]: Using Crusher Broken Aggregate By Mechanical Means | 900 | Cum | 1,016 | ₹9,14,400 |
| 4 | Item Code [R4 2025 4.4.2.1]:Item Type [road] ::WBM Grading 2 Providing, laying, spreading and compacting stone aggregates of specific sizes to water bound macadam specification including spreading in uniform thickness, hand packing, rolling with smooth wheel roller 80-100 kN in stages to proper grade and camber, applying and brooming, stone screening to fill-up the interstices of coarse aggregate, watering and compacting to the required density Grading 2 as per MoRTH Specification Clause 404. using Crusher borken aggregate
Sub Item Code [R4 2025 4.4.2.1 + R4 2025 4.4.2.1.2]: WBM Grading 2 Providing, laying, spreading and compacting stone aggregates of specific sizes to water bound macadam specification including spreading in uniform thickness, hand packing, rolling with smooth wheel roller 80-100 kN in stages to proper grade and camber, applying and brooming, stone screening to fill-up the interstices of coarse aggregate, watering and compacting to the required density Grading 2 as per MoRTH Specification Clause 404. using Crusher borken aggregate By Mechanical Means | 720 | Cum | 1,093 | ₹7,86,960 |
stage.html
html • 0.02 MB
finance_991064.pdf
boq_comp_chart.xlsx
xlsx
Tap a document below to read it instantly. You can also download everything as a ZIP if you prefer.
details.html
html • 0.03 MB
Tendernotice_1.pdf
PDF • 3.04 MB
BOQ_991064.xls
BOQ • 0.31 MB
Download all tender documents and submit your bid
Disclaimer: TenderKart has made every reasonable effort to ensure that the information on this page is accurate and authentic, however it cannot be held liable for any third-party claims or losses or any damages. TenderKart makes no warranty, expressed or implied, as to the results obtained from the use of this information. If you notice any error or omission, please let us know at [email protected].