| # | Company | Amount | Rank | Status |
|---|---|---|---|---|
| 1 | L1₹2.8 CrAccepted-AOC | ₹2.8 Cr | L1 | Accepted-AOC AS PER UPLOADED |
| 2 | Not Admitted-Finance | - | - | Not Admitted-Finance Not qualified for AOC |
| 3 | Not Admitted-Finance | - | - | Not Admitted-Finance Not qualified for AOC |
Tender Value
Refer Docs
EMD Value
₹7.4 L
Closing Date
9 Mar 2024, 12:00 pmClosed
SUPERINTENDING ENGINEER
SUPERINTENDING ENGINEER GANDAK IRRIGATION WORK CIRCLE-1, GORAKHPUR
RESTORATION AND DEMARCATION WORKS OF JAMUNIYA DY. FROM KM. 0.000 TO KM. 14.400 IN DISTRICT KUSHINAGAR
2024_UPIDC_909441_4
05/SE/2023-24
Open Tender
Civil Works
Item Wise
180 days
PADRAUNA
Please refer Tender documents.
2 documents required · 2 mandatory
₹6,064
₹7.4 L
Yes
19 Sept 2024
2 Mar 2024
9 Mar 2024
2 Mar 2024
9 Mar 2024
2 Mar 2024
Amount
Earthwork in Restoration of canal section with its proper disposal & their dressing within 30 mtr lead & 1.5m lift with manual compaction etc for proper completion of work as directed of Engineer in charge as per drawing and I.D. specification.(External)
Earth work in internal section including lift upto 1.5m and lead upto 30m, including cost of driver/assistant driver, POL, maintencance of machine, contractor profit, taxes etc but excluding leveling, dressing & compaction etc for proper completion of work as directed of Engineer in charge as per drawing and I.D. specification..
Earth work in digging foundation in all type of soil with all lead and lift including refilling the trench and proper disposal of excess earth etc for proper completion of work as directed of Engineer in charge as per drawing and I.D. specification.(For Outlet & Tail fall)
Earth work in digging foundation in all type of soil with all lead and lift including refilling the trench and proper disposal of excess earth etc for proper completion of work as directed of Engineer in charge as per drawing and I.D. specification.(For Boundry piller & Kilometere Stone)
Dismantling of old V.R.B. and proper disposal including all cost of materials, T&P and labours etc for proper completion of work as directed of Engineer in charge as per drawing and I.D. specification.
Earth work in digging foundation in all type of soil with all lead and lift including refilling the trench and proper disposal of excess earth etc for proper completion of work as directed of Engineer in charge as per drawing and I.D. specification.(For VRB)
Earth work for making Ramp and correction of bank, Diversion and making jeepable service road including all cost of materials, T&P and labours and other accessories required for proper completion of work as directed of Engineer in charge as per drawing and I.D. specification.
Dry brick on Edge soling including prepration of sub-grade to prescrib Slope,filing joint with mortor T&P etc for proper completion of work as directed of Engineer in charge as per drawing and I.D. specification.
Dry brick on Edge soling including prepration of sub-grade to prescrib Slop ,filing joint with mortar T&P etc for proper completion of work as directed of Engineer in charge as per drawing and I.D. specification.(Reuse of brick from diversion in approach road)
Cement Concrete with 40mm gauge Ist class Brick ballast, coarse sand and cement in proportion of 1:4:8 below C.C. Lining including cost of all materials labour and T&P and other accessories required for proper completion of work as directed of Engineer in charge as per drawing and I.D. specification.
Laying C.C. 1:3:6 in foundation with cement, sonbhadra coarse sand and dala grit (12.5 mm to 20 mm) including all cost of materials, T&P, labours and other accessories required for proper completion of work as directed of Engineer in charge as per drawing and I.D. specification.(For VRB & Tail fall)
Laying C.C. 1:3:6 in foundation with cement, sonbhadra coarse sand and dala grit (12.5 mm to 20 mm) including all cost of materials, T&P, labours and other accessories required for proper completion of work as directed of Engineer in charge as per drawing and I.D. specification.(For Outlet)
Centering and shuttering for R.C.C. work including all cost of materials, T&P, labours and other accessories required for proper completion of work as directed of Engineer in charge as per drawing and I.D. specification.(For VRB)
Centering and shuttering for R.C.C. work including all cost of materials,T&P labours and other accessories required for proper completion of work as directed of Engineer in charge as per drawing and I.D. specification.(For Outlet)
Centering and shuttering for Kilometere Stone including all cost of materials,T&P,labours and other accessories required for proper completion of work as directed of Engineer in charge as per drawing and I.D. specification.(For Kilometere Stone)
Centering and shuttering for R.C.C. Precast boundry piller size 150x150x1650 (mm) including all cost of materials,T&P,labours and other accessories required for proper completion of work as directed of Engineer in charge as per drawing and I.D. specification.
Providing one coat of VG -30 bitumen painting with two layer of tarfelt again followed by second coat of bitumen on abutment and pier before laying R.C.C. Slab including cost of all material labour and T & P etc for proper completion of work as directed of Engineer in charge as per drawing and I.D. specification.
Bending, binding cutting placing in position rainforcement steel including cost of binding wire and tack wilding with material and other accessories required for proper completion of work as directed of Engineer in charge as per drawing and I.D. specification.
Laying RCC work in 1:1:2 (M-25) Sonbhadra coarse sand of FM not less then 2.50 and dala grit (10mm to 20mm) for Slab, Wearing Coat and abutment cap stir including all cost of materials, T&P, labours and other accessories required for proper completion of work as directed of Engineer in charge as per drawing and I.D. specification.(For VRB)
Laying RCC work in 1:1:2 (M-25) Sonbhadra coarse sand of FM not less then 2.50 and dala grit (10mm to 20mm) for Slab, Wearing Coat and abutment cap stir including all cost of materials, T&P, labours and other accessories required for proper completion of work as directed of Engineer in charge as per drawing and I.D. specification.(For Kilometere Stone)
Laying C.C. work in 1:1.5:3 (M-20) Sonbhadra coarse sand of FM. not less then 2.50 and dala grit (12.5mm to 20mm) including all cost of materials, T&P, labours and other accessories required for proper completion of work as directed of Engineer in charge as per drawing and I.D. specification.
Laying C.C. work in 1:2:4 (M-15) Sonbhadra coarse sand of FM. not less then 2.50 and dala grit (12.5mm to 20mm) for C.C Lining including all cost of materials, T&P, labours and other accessories required for proper completion of work as directed of Engineer in charge as per drawing and I.D. specification.(For VRB)
Laying C.C. work in 1:2:4 (M15) sonbhadra coarse sand of FM. Not less then 2.00 and dala grit (4.750mm to 10mm.) including all cost of materials,T&P and labours and other accessories required for proper completion of work as directed of Engineer in charge as per drawing and I.D. specification.(For Outlet)
C.C. work in 1:2:4 (M15) in foundation with sonbhadra coarse sand of FM. Not less then 2.00 and dala grit (10mm to 20mm) including all cost of materials,T&P and labours and other accessories required for proper completion of work as directed of Engineer in charge as per drawing and I.D. specification.(For Boundry Piller)
Ist class brick work in 1:4 cement mortar with class brick M-150, sonbhadra coarse sand of FM. Not less then 2.50, including all cost of materials, T&P, labours and other accessories required for proper completion of work as directed of Engineer in charge as per drawing and I.D. specification.
Struck deep Cement Pointing with 1:2 cement mortar with sonbhadra coarse sand of FM. Not less then 2.50, including all cost of materials, T&P, labours and other accessories required for proper completion of work as directed of Engineer in charge as per drawing and I.D. specification.
12 mm thick plaster with cement mortar inproportion of 1:4 cement and sand of 1.25 F.M. over brick work minium thickness not be less than 10 mm including supply of all materials,labour and T&P etc required for proper completion of work as directed of Engineer in charge as per drawing and I.D. specification.
Finising of walls with water proofing cement paint of approved make such as super Snowcem,Durrocem,Robiacem Guttucem,supreme quality of required shade on uncoated wall surface (one coat ) over one coat white cement primer to give evenshades after thoroughly brushing the surface to remove all dirt and remains of loose powedered material including curing and cost of material etc for proper completion of work as directed of Engineer in charge as per drawing and I.D. specification.
Supply and fixing PVC Kulawa pipe 160mm I.S.I marked,labour, T&p etc. required for proper completion of worK.
Supply and fixing PVC Kulawa pipe 110mm I.S.I marked,labour, T&p etc. required for proper completion of worK.
Providing and Laying of LDPE Film on footing box including cost of all material,labour and T&P etc. required for proper completion of work as directed of Engineer in charge as per drawing and I.D. specification.
Fixing of RCC Precast Boundry Piller/Kilometere Stone including cost of all material,labour and T&P etc. required for proper completion of work as per direction of Engineer-in-charge.
Supply and laying of 18 MM thick joint filler board in construction joint including cost of all material, labour, T&P required for proper completion of work as directed of Engineer in charge as per drawing and I.D. specification.
Fixing wheel guard stone including cost of all material, labour, T&P etc required for proper completion of work as directed of Engineer in charge as per drawing and I.D. specification.
Writing letter for details of canal boundary for proper completion of work as directed of Engineer in charge as per drawing and I.D. specification.
Sign board at site for Notice including cost of all material, labour, T&P etc required for proper completion of work as directed of Engineer in charge as per drawing and I.D. specification.
tech_bid_open.pdf
tech_eval.pdf
fin_bid_open.pdf
boq_comp_chart.xlsx
xlsx
fin_eval.pdf
aoc.pdf
Download all tender documents and submit your bid
Disclaimer: TenderKart has made every reasonable effort to ensure that the information on this page is accurate and authentic, however it cannot be held liable for any third-party claims or losses or any damages. TenderKart makes no warranty, expressed or implied, as to the results obtained from the use of this information. If you notice any error or omission, please let us know at .