Loading…
Loading…
| # | Company | Amount | Rank | Status |
|---|---|---|---|---|
| 1 | L1₹23.5 LAccepted-AOC | ₹23.5 L | L1 | Accepted-AOC L1 |
| 2 | L2₹24.9 LRejected-AOC | ₹24.9 L | L2 | Rejected-AOC L2 |
| Sl No | Description | Qty | Unit | M/s. SS Builders | nallathambi |
|---|---|---|---|---|---|
| 1.00 | Dismantling, clearing away and carefully stacking materials useful for re-use PCC etc., complete as per standard specification | 30 | cum | 12,900 ₹15,222 | 12,570 ₹14,832.60 |
| 2.00 | Earth work excavation for foundation in Hard stiff clay, stiff black cotton, hard red earth, shales murram, gravel,stoney earth and earth mixed with small size boulders and Sand, silt or other loose soil, wet sand,or silt not under water, light black cotton soil, sandy loam ordinary soil and to full depth as may be directed except in hardrock requiring blasting inclusive of shoring shuttering and baling out water and cleaning and levelling the site etc.,complete SS.20B 10 cum | 164 | cum | 15,580 ₹18,384.40 | 14,825.6 ₹17,494.21 |
| 3.00 | Plain Cement Concrete 1:4:8 (one cement four fine aggregates and eight coarse aggregates) using 40mm size ISS HBG metal including cost and conveyance of all materials to site and including for the mixing, laying and labour charges and all incidential charges such as water providing etc., complete as per standard specification | 87 | cum | 4,74,150 ₹5.6 L | 4,70,061 ₹5.5 L |
| 4.00Centering for soffits of RCC slabs of plane surface like lintels, beams ,etc.,including strutting 3m high using mild steel sheets of size 90cm X 60cm X and B.G 10 stiffened with M.S angles of size 25mm X 25mm X 3mm laid over silver Oak (C.W) joists of size 10cm X 6.5cm (spaced at about 90cm c/c )and supported dy casurina props of 10cm to 13cm dia (spaced of 75cm C/C) complying with standard specification and directed - 10 m 2 (P & D)Data 38 | |||||
| 4.01 | side wall | 203 | SQM | 1,92,850 ₹2.3 L | 1,86,658.5 ₹2.2 L |
| 4.02 | Slab | 4.5 | SQM | 5,400 ₹6,372 | 5,000.85 ₹5,901 |
| 5.00 | Plain Cement Concrete 1:1.5:3 (One part of Cement, one and half part of Crushed Sand (M- Sand), three coarse aggregates) using 20mm size ISS HBG metal including cost and conveyance of all materials to site and including for the mixing, laying and labour charges etc., complete as per standard specification | 5 | cum | 37,500 ₹44,250 | 37,100 ₹43,778 |
| 6.00 | Supplying, fabricating, and placing in position of mild steel for all reinforced cement concrete works including cost and conveyance of steel and binding wire and all other labour charges for cutting bending tying grills charges for cutting, bending tying grills, straightening welding charges etc, complete complying with standard specification. | 4,620 | Cum | 5,08,200 ₹6.0 L | 4,30,122 ₹5.1 L |
| 7.00 | Reinforced Cement concrete 1:1.5 :3 (one cement, one and half sand & three course aggregate) using 20mm gauge hand broken/ and broken granite stone for all RCC items of works excluding centering shuttering and cost of reinforcement but including curing etc.,complete and also including fixing fan clamps and fixtures in rcc works wherever necessary as directed by departmental officer etc., complete. | 67 | Cum | 6,36,500 ₹7.5 L | 6,15,562.5 ₹7.3 L |
| 8.00 | Manufacturing, supplying and fixing Precast Reinforced Cement Concrete slabs of following thickness in RCC M20 concrete using following HBGS jelly excluding cost of reinforcement steel in position but including cost of moulding charges, casting of slab, finishing, curing and fixing in position in all floors etc., complete complying with standard specification and as directed. | 100 | Sqm | 1,00,000 ₹1.2 L | 92,100 ₹1.1 L |
Tender Value
₹28 L
EMD Value
₹28,000
Closing Date
27 Oct 2025, 3:00 pmClosed
The Commissioner
New COlony 3rd Main Road,Chrompet
TCMC - Laying CC Road And Contruction Of SWD With Covered Slab at Eswari Nagar Pudhukudiirupu in Ward No.15 Tambaram City Municipal Corporation Zone II
2025_DMA_615676_1
171/2025/E1 Z2
Open Tender
Civil Works - Roads
90 days
Tambaram City Municipal Corporation Zone II
Please refer Tender documents.
2 documents required · 2 mandatory
₹0
₹28,000
7 Feb 2026
18 Oct 2025
27 Oct 2025
18 Oct 2025
27 Oct 2025
18 Oct 2025
Dismantling, clearing away and carefully stacking materials useful for re-use PCC etc., complete as per standard specification
Earth work excavation for foundation in Hard stiff clay, stiff black cotton, hard red earth, shales murram, gravel,stoney earth and earth mixed with small size boulders and Sand, silt or other loose soil, wet sand,or silt not under water, light black cotton soil, sandy loam ordinary soil and to full depth as may be directed except in hardrock requiring blasting inclusive of shoring shuttering and baling out water and cleaning and levelling the site etc.,complete SS.20B 10 cum
Plain Cement Concrete 1:4:8 (one cement four fine aggregates and eight coarse aggregates) using 40mm size ISS HBG metal including cost and conveyance of all materials to site and including for the mixing, laying and labour charges and all incidential charges such as water providing etc., complete as per standard specification
Centering for soffits of RCC slabs of plane surface like lintels, beams ,etc.,including strutting 3m high using mild steel sheets of size 90cm X 60cm X and B.G 10 stiffened with M.S angles of size 25mm X 25mm X 3mm laid over silver Oak (C.W) joists of size 10cm X 6.5cm (spaced at about 90cm c/c )and supported dy casurina props of 10cm to 13cm dia (spaced of 75cm C/C) complying with standard specification and directed - 10 m 2 (P & D)Data 38
side wall
Plain Cement Concrete 1:1.5:3 (One part of Cement, one and half part of Crushed Sand (M- Sand), three coarse aggregates) using 20mm size ISS HBG metal including cost and conveyance of all materials to site and including for the mixing, laying and labour charges etc., complete as per standard specification
Supplying, fabricating, and placing in position of mild steel for all reinforced cement concrete works including cost and conveyance of steel and binding wire and all other labour charges for cutting bending tying grills charges for cutting, bending tying grills, straightening welding charges etc, complete complying with standard specification.
Reinforced Cement concrete 1:1.5 :3 (one cement, one and half sand & three course aggregate) using 20mm gauge hand broken/ and broken granite stone for all RCC items of works excluding centering shuttering and cost of reinforcement but including curing etc.,complete and also including fixing fan clamps and fixtures in rcc works wherever necessary as directed by departmental officer etc., complete.
Manufacturing, supplying and fixing Precast Reinforced Cement Concrete slabs of following thickness in RCC M20 concrete using following HBGS jelly excluding cost of reinforcement steel in position but including cost of moulding charges, casting of slab, finishing, curing and fixing in position in all floors etc., complete complying with standard specification and as directed.
Vibrated C.C.M 20 Grade (1:1.5:3) mix 65% of 25mm,25% of12mm and 10% of 6mm IRC size metal including cost and conveyance of all materials to site and including for the mixing, laying, watering,curing and compacting concrete, cost of form work, centering labour therefore including all leads of water vibration charges working in heights wherever necessary, cost premoulded expansion joints (Bitumen Pad),etc., and labour charges etc., complete as per standard specification
stage.html
html • 0.04 MB
tech_eval.pdf
fin_eval.pdf
aoc.pdf
boq_comp_chart.xlsx
xlsx
Tap a document below to read it instantly. You can also download everything as a ZIP if you prefer.
details.html
html • 0.03 MB
Tendernotice_1.pdf
PDF • 0.60 MB
BOQ_735614.xls
BOQ • 0.40 MB
Download all tender documents and submit your bid