Loading…
Loading…
Tender Value
₹24.7 L
EMD Value
₹49,485
Closing Date
9 Oct 2026, 6:00 pm
PO ALIPURDUAR
DOOARSKANYA ALIPURDUAR
Construction of Boundary Wall at Alipurduar Subodh Sen Smriti Blind School at Pararpara GP under Alipurduar I Block
2026_DMA_5075451_3
WBBCWD/142/PO-APD/2026-2027
Open Tender
CIVIL WORKS
Percentage
90 days
Falakata
Please refer Tender documents.
2 documents required · 2 mandatory
₹0
₹49,485
25 Sept 2026
25 Sept 2026
12 Oct 2026
25 Sept 2026
9 Oct 2026
25 Sept 2026
This is a percentage-rate BOQ. The schedule below shows estimated quantities and rates. Bidders quote a single percentage above or below the total estimated cost.
| Sl No | Description | Qty | Unit | Est. Rate | Est. Amount |
|---|---|---|---|---|---|
| 1 | Earth work in excavation by mechanical means (Hydraulic excavator) / manual means in foundation trenches or drains (not exceeding 1.5 m in width or 10 sqm on plan), including dressing of sides and ramming of bottoms, for all lift, including getting out the excavated soil and disposal of surplus excavated soil as directed, within a lead of 50 m. (a) All kinds of soil. | 100.82 | cum | 260.3 | ₹26,243.45 |
| 2 | Filling available excavated earth (excluding rock) in trenches, plinth, sides of foundations etc. in layers not exceeding 20cm in depth, consolidating each deposited layer by ramming and watering, lead up to 50 and for all lift. | 20.16 | cum | 196 | ₹3,951.36 |
| 3 | Dry brick on edge flooring in required pattern with bricks of class designation 7.5 on a bed of 12 mm mud mortar, including filling joints with Jamuna sand, with common burnt clay non modular bricks. | 97.43 | sqmt. | 792.05 | ₹77,169.43 |
| 4 | Providing and laying in position cement concrete of specified grade excluding the cost of centering and shuttering - All work up to plinth level. 1:3:6 (1 Cement : 3 coarse sand (zone-III) derived from natural sources : 6 graded stone aggregate 40 mm nominal size derived from natural sources). | 28.17 | cum | 7,178.75 | ₹2,02,225.39 |
| 5.1 | Centering and shuttering including strutting, propping etc. and removal of form for Foundations, footings, bases of columns, etc. for mass concrete. | 180 | sqmt. | 392.15 | ₹70,587 |
| 5.2 | Lintels, beams, plinth beams, girders, bressumers and cantilevers | 165 | sqmt. | 736.4 | ₹1,21,506 |
| 5.3 | Columns, Pillars, Piers, Abutments, Posts and Struts | 150 | Sqmt. | 961.3 | ₹1,44,195 |
| 6 | Providing and laying in position cement concrete of specified grade excluding the cost of centering and shuttering - All work up to plinth level. 1:1½:3 (1 Cement: 1½ coarse sand (zone-III) derived from natural sources : 3 graded stone aggregate 20 mm nominal size derived from natural sources). | 34.41 | cum | 8,340.85 | ₹2,87,008.65 |
| 7 | Providing and laying cement concrete in retaining walls, return walls, walls (any thickness) including attached pilasters, columns, piers, abutments, pillars, posts, struts, buttresses, string or lacing courses, parapets, coping, bed blocks, anchor blocks, plain window sills, fillets, sunken floor etc., up to floor five level, excluding the cost of centering, shuttering and finishing: 1:1½:3 (1 cement : 1½ coarse sand (zone-III) derived from natural sources : 3 graded stone aggregate 20 mm nominal size derived from natural sources). | 20.7 | cum | 10,357.55 | ₹2,14,401.28 |
| 8.1 | Steel reinforcement for R.C.C. work including straightening, cutting, bending, placing in position and binding all complete upto plinth level. Thermo-Mechanically Treated bars of grade Fe-500D or more. | 2,600 | kg | 107.85 | ₹2,80,410 |
Tap a document below to read it instantly. You can also download everything as a ZIP if you prefer.
details.html
html • 0.03 MB
Tendernotice_1.pdf
PDF • 2.90 MB
BOQ_5165612.xls
BOQ • 0.32 MB
Download all tender documents and submit your bid
Disclaimer: TenderKart has made every reasonable effort to ensure that the information on this page is accurate and authentic, however it cannot be held liable for any third-party claims or losses or any damages. TenderKart makes no warranty, expressed or implied, as to the results obtained from the use of this information. If you notice any error or omission, please let us know at .