Loading…
Loading…
| # | Company | Amount | Rank | Status |
|---|---|---|---|---|
| 1 | L-1₹99.5 LAccepted-AOC | L-1 | Accepted-AOC L-1 | |
| 2 | L-2₹1.0 Cr+₹4.5 L (4.47%)Rejected-Finance MIHINPURWA BAHRAICH | BAHRAICH | UTTAR PRADESH | 271801 | L-2 | Rejected-Finance L-2 | |
| 3 | L-3₹1.1 Cr+₹7.6 L (7.62%)Rejected-Finance | L-3 | Rejected-Finance L-3 |
Tender Value
₹1.1 Cr
EMD Value
₹1.1 L
Closing Date
12 Sept 2022, 4:00 pmClosed
SE
132 KV S/S GHAZIPUR
DIVERSION OF 1.11 Km. 400KV ANPARA-SARNATH (L-5) AND ANPARA-MAU (L-6) D/C LINE BETWEEN TOWER NO. 421 TO 424 DUE TO INFRINGING IN R.O.W. OF NHAI (RING ROAD PHASE-II) UNDER ETD-GHAZIPUR
2022_UPTCL_716521_2
E-tender No. 31 ETC(GZP)/2022-23
Open Tender
Electrical Works
Turn-key
120 days
Varanasi
Please refer Tender documents.
2 documents required · 2 mandatory
₹12,744
EE ETD Ghazipur
₹1.1 L
11 Oct 2022
5 Sept 2022
13 Sept 2022
5 Sept 2022
12 Sept 2022
5 Sept 2022
Amount
PART-(A) SUPPLY
Accessories for Tower
Number plate
Danger plate
Phase plate (Set of three)
Materials for pipe type earthing
Accessories for ACSR Moose Conductor
Twin Spacer Vibration Damper
Mid span compresson joint
Rigid Spacer for jumper
Repair sleeve
Bundle Spacer for conductor
Accessories for 7/3.67mm. Ground wire
Tension Clamp
Mid span compresson joint E/W
Vibration Damper
Flexible copper bond
Accessories for Hardware & insulator
Double Tension clamp & Hardware suitable for Twin ACSR Moose conductor (including steel dead end, alluminium dead end with jumper cone, corona ring, arcing hom, insulator) fitting plate and D-cycle bolt.)
160 KN Composit polymer rubber insulator for 400 KV line.
PART-(B)WORK
Detail survey & profilling
Check survey & peg marking
Cost of excavation of 400 KV tower foundation pits including all earth work, back filling, leveling etc.
Setting of Stub including all foundation work but excluding the cost of concreting and excavation for following 400 KV D/C tower.
DD+6 Mtr
DD+9 Mtr
Cost of concreting for all type of 400 KV D/C tower foundation including cost of cement, dewatering, shoring and shuttering, curing but excluding cost of reinforcement bars Twith 1:1.5:3 concrete.
M20 Concrete nominal mix 1:1.5:3
M1O Concrete nominal mix 1:3:6
Erection of superstructure of 400 KV DD-type tower and their extention wherever required including all works above ground level excluding hoisting of insulator, hardware & accessories but including fitting of danger plate, phase plate, and bird guard, fixing & punching. (The contractor will be provide 02 No's erection gang at least on site)
Tack welding of all the bolts up to height one section of the tower or 5 meter from the ground level whicheveris higher with three tacks at 120 separation of minimum 10mm thickness with 10mm/12mm electrode and application of zinc alluminium paints on the affected surface including cost of all materials.
Laying, stringing, tensioninig, clamping, jointing etc of TwinMoose ACSR bundle conductor including making jumper, hoisting of insulator, fitting of all necessary hardware and accessories i.e. fitting of armour rods, vibration dampers etc. on all six phases of 400 KV D/C lines.(The contractor will be provide 02 No's stringing gang at least on site.)
Laying, stringing, tensioninig, clamping, jointing etc of earth wire including fitting of all necessary hardware and accessories for 02No. Earth wire including cost of labour and T&P charges to complete the job satisfactory.
Ground work including earth work etc for pipe type earthing including cost of coke and salt.
Installation of reinforcement bars in RCC foundation including cost of steel reinforcement bars with cutting, bending, placing, binding etc.
De-stringing or all six Phases, de-hoisting of insulator, rolling of dismantaled conductor and all associated work.
De-stringing of 02 No's OPGW/ earthwire, rolling of dismentaled OPGW earthwire, and all associated work.
Dismentaling, counting, stacking of existing 400 KV D/C tower and all other associated work.
Shifting, counting, stacking & loading of line materials like 400 KV D/C tower parts, coductor, fittings etc from 400 KV S/S Sarnath/220 KV S/S Sahupuri store Varanasi to diversion point of above line and unloading, stacking of line materials and other all associated work including cost of labour and T&P charges. (Distance approx 50 Km.)
Transpotation of all Dismantaled materials including shifting up to loading point, loading into vehicle, transpotation & unloading at Sarnath/Sahupuri store Varanasi. (Distance approx 50 Km.)
Star Construction
Bhagwati Traders
tech_bid_open.pdf
tech_eval.pdf
fin_bid_open.pdf
boq_comp_chart.xlsx
xlsx
fin_eval.pdf
aoc.pdf
Download all tender documents and submit your bid
Disclaimer: TenderKart has made every reasonable effort to ensure that the information on this page is accurate and authentic, however it cannot be held liable for any third-party claims or losses or any damages. TenderKart makes no warranty, expressed or implied, as to the results obtained from the use of this information. If you notice any error or omission, please let us know at .